
In a recently released report, the organization, which studied the effects of the 2011 Fukushima Daiichi disaster in Japan, said that only luck kept that incident from being much worse.
“This should serve as a wake-up call to the industry and regulators about the critical importance to be able to monitor the condition of the pools, particularly in the event that something happens like Fukushima,” said Joseph Shepherd, an engineering professor at the California Institute of Technology and lead author of the report. The Nuclear Energy Institute, however, said the safeguards are already in place.
More: The Wall Street Journal
NRC Hits Oyster Creek With ‘White’ Finding

It is one of the lowest safety findings the commission issues, but the commission said the failure was serious enough to merit the violation.
If the finding is affirmed, the plant would be subject to increased federal oversight. Oyster Creek is scheduled for decommissioning in 2019.
More: Micromedia Publications
Entergy, NRC Settle on 2011 Leak at Palisades

The leak, less than one drop per minute, came from a 3-inch pipe flange that showed signs of boric acid corrosion, according to documents. The commission characterized the inadequate reporting of the incident by four workers as “willful.” Entergy defined the problem as a failure of the plant’s “organizational safety culture.”
In lieu of a fine, Entergy agreed to prepare a report on the lessons learned and to upgrade training to include those lessons. It will also take steps to increase transparency with the public, agreeing to hold public meetings to discuss plant safety and to allow the public to ask questions at those meetings.
More: Nuclear Street
New York Senators Call For Stop to Algonquin Project
Democratic Sens. Kirsten Gillibrand and Charles Schumer are asking FERC to shut down construction of the Algonquin Incremental Market pipeline until health and safety reviews are conducted.
The pipeline is to run from Pennsylvania to the Hudson River Valley region in New York. The lawmakers say they are concerned about the safety of residents along the route, as well as the sensitivity because the route takes it close to the Indian Point nuclear station.
Construction on the project, which will nearly double the size of the existing 26-inch pipeline to 42 inches, has already started. FERC said it had not yet received the letter from the senators, but it does not comment on congressional correspondence anyway, according to a spokeswoman.
More: The Journal News
Eastern Shore Gas Applies To FERC for 33-Mile Expansion
Eastern Shore Natural Gas has filed with FERC to expand its natural gas transmission system, including the installation of 33 miles of looping pipeline in Pennsylvania, Delaware and Maryland.
The company would also install 17 miles of expanded line along with pressure equipment in Sussex County, Del. The system improvements would provide an additional 86,000 dekatherms of gas per day, according to the company.
More: Delaware Business Times
Seabrook Cited for Slow Response to Concrete Problem
The Nuclear Regulatory Commission cited NextEra Energy’s Seabrook nuclear plant for a low-level safety violation after a March 24 inspection.
The commission cited the New Hampshire plant because NextEra’s staff delayed completion of structure inspections after being told of an alkali-silica reaction in the plant’s concrete.
NextEra said procedures have been changed since the violation occurred. The commission and NextEra confirmed that the plant’s walls, some up to 4 feet thick, still meet federal structural safety standards.
More: The Daily News of Newburyport
EPA Issues Water Permit Even as Pilgrim Nears Closure

The plant’s owner, Entergy, has said it will retire the plant in 2019. Most of the plant’s spent fuel is stored in pools inside, meaning the plant will still draw water from Cape Cod Bay even after it closes, opponents say. When operating at full power, the 680-MW plant draws more than 500 million gallons per day.
More: The Patriot Ledger

