December 24, 2024

SPP Markets and Operations Policy Committee

SPP
SPP Board Approves Need Dates for Last ITP Projects
SPP’s Board of Directors has approved the winter-weather staging of a pair of transmission projects that have been held up since October by stakeholder concerns.
© RTO Insider LLC 
SPP Stakeholders Endorse Need Dates for Delayed Transmission Projects
SPP stakeholders have endorsed a pair of winter-weather staging dates for transmission projects after two months of discussions and negotiations that delayed their approval by the Board of Directors.
© RTO Insider LLC 
SPP Board Approves $7.65B ITP, Delays Contentious Issue
SPP’s Board of Directors approved the grid operator’s “historic” $7.65 billion package of transmission projects, but delayed a decision on a need date for two of the projects after stakeholders pushed back on staff’s staging recommendations.
© RTO Insider LLC
SPP Markets & Operations Policy Committee Briefs: Oct. 15-16, 2024
SPP says it is devoting significant resources to finally resolve Attachment Z2, a bone of contention among SPP stakeholders since 2016 -- by the end of this decade.
© RTO Insider LLC 
SPP Stakeholders Endorse Record $7.65B Tx Plan
SPP stakeholders have endorsed what one member called an “historic” transmission plan that will eclipse any previous portfolio by a factor of five with a projected cost of $7.65 billion.
© RTO Insider LLC
SPP Considering 765-kV Solution for Permian Basin
SPP is considering a 765-kV solution and several 500-kV proposals in its Permian Basin footprint in Texas and New Mexico as it dabbles with extra-high-voltage transmission lines.
© RTO Insider LLC
SPP Markets and Operations Policy Committee Briefs: July 16-17, 2024
SPP’s Markets and Operations Policy Committee endorsed recommended revision requests from two stakeholder groups as part of the RTO’s effort to strengthen resource adequacy.
SPP
SPP Files to Incorporate Western Entities into RTO
SPP filed bylaw amendments at FERC to place seven Western entities under its tariff that, if approved, will make the RTO the first grid operator with markets in both major interconnections.
© RTO Insider LLC
SPP Markets and Operations Policy Committee: April 16-17, 2024
SPP publicly alerted stakeholders it failed to conduct a tariff-required analysis of several GI queue study clusters during their effort to reduce the backlog of GI requests dating back to 2017.
Entergy
SPP Markets and Operations Policy Committee Briefs: Jan. 16-17, 2024
SPP stakeholders have approved congestion-hedging implementation policies six years in the making that had some likening it to Groundhog Day.

Want more? Advanced Search