November 21, 2024

SPP Markets and Operations Policy Committee

© RTO Insider LLC 
SPP Board Approves $7.65B ITP, Delays Contentious Issue
SPP’s Board of Directors approved the grid operator’s “historic” $7.65 billion package of transmission projects, but delayed a decision on a need date for two of the projects after stakeholders pushed back on staff’s staging recommendations.
© RTO Insider LLC
SPP Markets & Operations Policy Committee Briefs: Oct. 15-16, 2024
SPP says it is devoting significant resources to finally resolve Attachment Z2, a bone of contention among SPP stakeholders since 2016 -- by the end of this decade.
© RTO Insider LLC 
SPP Stakeholders Endorse Record $7.65B Tx Plan
SPP stakeholders have endorsed what one member called an “historic” transmission plan that will eclipse any previous portfolio by a factor of five with a projected cost of $7.65 billion.
© RTO Insider LLC
SPP Considering 765-kV Solution for Permian Basin
SPP is considering a 765-kV solution and several 500-kV proposals in its Permian Basin footprint in Texas and New Mexico as it dabbles with extra-high-voltage transmission lines.
© RTO Insider LLC
SPP Markets and Operations Policy Committee Briefs: July 16-17, 2024
SPP’s Markets and Operations Policy Committee endorsed recommended revision requests from two stakeholder groups as part of the RTO’s effort to strengthen resource adequacy.
SPP
SPP Files to Incorporate Western Entities into RTO
SPP filed bylaw amendments at FERC to place seven Western entities under its tariff that, if approved, will make the RTO the first grid operator with markets in both major interconnections.
© RTO Insider LLC
SPP Markets and Operations Policy Committee: April 16-17, 2024
SPP publicly alerted stakeholders it failed to conduct a tariff-required analysis of several GI queue study clusters during their effort to reduce the backlog of GI requests dating back to 2017.
Entergy
SPP Markets and Operations Policy Committee Briefs: Jan. 16-17, 2024
SPP stakeholders have approved congestion-hedging implementation policies six years in the making that had some likening it to Groundhog Day.
© RTO Insider LLC
SPP Markets and Operations Policy Committee Briefs: Oct. 16-17, 2023
SPP stakeholders approved two revision requests that set resource adequacy policies, but not before rejecting a compromise position offered by two stakeholder groups.
© RTO Insider LLC
SPP Markets and Operations Policy Committee Briefs: July 10-11, 2023

SPP stakeholders endorsed a tariff revision request that adds a winter resource adequacy requirement for load-responsible entities bound by the grid operator’s recent planning reserve margin increase.


Want more? Advanced Search