Greenberg Traurig

NYISO
NYISO Discovers Market Problem, Opens Confidential Investigation
NYISO has identified a software issue that potentially constitutes a market problem and says it will confidentially investigate the impact.
NYISO
NYISO Stakeholders Still Questioning Interconnection Queue Proposal
NYISO took another stab at clarifying the proposed class year queue window concept that will replace its current interconnection queue processes.
NYISO
NYISO Recommends NYPA-Transco Proposal for Long Island Tx Need
NYISO staff selected a proposal by Propel NY Energy to meet the ISO’s Long Island Public Policy Transmission Needs solicitation for transmission lines.
NYISO
NYISO Shares Details of Potential Long Island Tx Projects
NYISO stakeholders learned how the ISO assessed the seven transmission projects chosen from the Public Policy Transmission Need solicitation for Long Island.
©RTO Insider LLC
NYISO Stakeholders Debate Proposed Interconnection Queue Overhaul
NYISO stakeholders discussed the merits and pitfalls of the ISO’s proposed phased window approach to fundamentally rework its interconnection study processes.
NYISO
NYISO Previews Plan to Expedite Interconnection Queue
NYISO updated subcommittee members on a phased window approach to its generator interconnection queue to potentially replace the current process.
Claus Ableiter, CC BY-SA 3.0, via Wikimedia Commons
New York Considering Standards for IBRs
The New York State Reliability Council has approved a uniform set of requirements for inverter-based resources over 20 MW to connect to the NYISO grid.
NYISO
NYISO Finalizes CRIS Tariff Revisions
NYISO presented a proposed timeline for finalizing tariff revisions related to capacity resource interconnection service expiration and transfer rules.
NYISO
NYISO Capacity Accreditation Implementation Worries Stakeholders
NYISO stakeholders expressed reluctance to approve the ISO’s proposed implementation of its new capacity accreditation construct.
Rhododendrites, CC BY-SA 4.0, via Wikimedia Commons
NYISO RNA Raises Concerns over Timing of Peaker Unit Retirements
NYISO’s draft Reliability Needs Assessment found no reliability issues until 2032 but identified tightening transmission security and resource adequacy margins.

Want more? Advanced Search