MISO Transmission Expansion Plan (MTEP)

Meta
CGA Latest to Nudge MISO to Simultaneously Contemplate New Load and New Generation
Clean energy organizations are prodding MISO to contemplate prospective load and generation simultaneously, with Clean Grid Alliance asking MISO to coordinate its annual transmission studies with its interconnection queue studies.
© RTO Insider LLC
Stakeholders Still Asking MISO for Smaller Tx Project Category to Address Congestion After MTEP 24 Study
Stakeholders want MISO to develop a smaller, congestion-relieving transmission study after this year’s near-term congestion study focused on how best to sequence transmission outages needed for construction of long-range transmission projects.
© RTO Insider LLC 
MISO Pauses Long-range Tx Planning in 2025 to go Back to the Futures
MISO will take a breather from its long-range transmission planning over 2025 to retool the 20-year future scenarios that are the foundation of the transmission portfolios.
ITC
$21.8B Long-range Tx Plan Goes to Membership Vote; MISO Resolute, IMM Protesting
MISO members are mulling an advisory vote on whether to support the RTO’s $21.8 billion long-range transmission plan portfolio while tensions simmer over the necessity of the expansion.
ATC and ITC
MISO IMM Makes Closing Arguments Against $21.8B Long-range Tx Plan
MISO Independent Market Monitor David Patton has made a final stand against the RTO’s $21.8 billion long-range transmission plan, while members are advising the MISO Board of Directors that the IMM's opinions on transmission shouldn't hold water.
MISO
MTEP 24 Reaches $6.7B; MISO Ending Rush Island Reliability Agreement in Mid-October
MISO’s 2024 transmission planning cycle is shaping up to include 459 new projects totaling $6.7 billion.
© RTO Insider LLC 
MISO Previews Future Projects to Improve System Planning
MISO has multiple planning topics to tackle on the horizon, with work involving an update of merchant HVDC interconnection procedures, making expedited transmission project reviews more manageable, and evaluating co-located load and generation seeking interconnection.
Entergy
MTEP 24 up to $5.8B; Clean Energy Group Asks for Alternative to Pricey Entergy Reliability Project
MISO’s 2024 Transmission Expansion Plan increased slightly in cost to $5.8 billion while the Southern Renewable Energy Association requested MISO explore an alternative to an Entergy Texas reliability project.
MISO, using Ventyx Velocity Suite
MISO Unable to Find Alternatives to Delayed Entergy Louisiana Tx Project
MISO announced it was unable to land on a suitable substitute for a $260 million Entergy Louisiana reliability project about eight months after it announced an alternatives study.
MISO
MISO Says 2nd LRTP Portfolio Should Run About $20B, Rate Mostly 765 kV
MISO suggested an approximately $20 billion portfolio for its second long-range transmission planning effort that contains several 765-kV line segments.