ISO-NE received six proposals from four different companies in response to its request for proposals to address transmission constraints and interconnect onshore wind in Maine, COO Vamsi Chadalavada told the NEPOOL Participants Committee on Oct. 9.
The costs of the proposals range from about $960 million to $4.04 billion, Chadalavada said. Three of the proposals primarily rely on AC transmission, and three rely on HVDC, he added.
Despite ISO-NE’s attempts to standardize the cost calculation requirements, some of the proposals include the cost of corollary upgrades in their price estimates, Chadalavada said. The RTO will attempt to “create an even playing field” between proposals that included corollary upgrade costs and those that did not, he added.
The Longer-Term Transmission Planning procurement requires proposals to increase the capacity of the Maine-New Hampshire interface to 3,000 MW and the Surowiec-South interface to 3,200 MW, and support the interconnection of at least 1,200 MW of onshore wind in Northern Maine. (See ISO-NE Releases Longer-term Transmission Planning RFP.)
Chadalavada said all proposals claim to meet these basic requirements and that ISO-NE received proposals to increase the Maine-New Hampshire interface to 3,600 MW and Surowiec-South to 3,800 MW.
The Maine-New Hampshire interface currently is limited to 2,000 MW, while Surowiec-South is limited to 1,800 MW. When the New England Clean Energy Connect (NECEC) line comes online — potentially around the end of 2025 — ISO-NE plans to increase the transfer limit of Maine-New Hampshire to 2,200 MW and Surowiec-South to 2,800 because of the upgrades associated with NECEC.
Also at the PC meeting, Chadalavada discussed market operations and performance, noting that energy market costs totaled $358 million in September (based on data through Sept. 30), an increase from $321 million in September 2024.
He said a planned transmission outage from mid-October to mid-November will limit flows from New York to New England to about 1,000 MW and flows from New England to New York to between 500 and 600 MW.
Responding to a stakeholder question about expected power imports from Québec in the coming winter, Chadalavada said ISO-NE’s “expectation is that we are going to see a reduced volume of imports, consistent with the past few years, but when we face really cold conditions, we expect the ties to be fully utilized.”
Imports from Québec have dropped significantly since early 2023, largely because of prolonged drought conditions in the province. Despite the significant reduction in total import volume, Hydro-Québec has continued to send large amounts of power during high-price periods in New England and has earned significant Pay-for-Performance credits in recent capacity scarcity events. (See Drought, Climate Drive Uncertainty on New England Imports from Québec.)
The PC also voted to approve planning procedure and operating procedure changes, including changes that set the load power factor ranges throughout the region. The revisions are “designed to address growing concerns around light-load and high-voltage conditions as the quantity of distributed energy resources on the New England system continues to increase.”




