PJM PC/TEAC Briefs: April 30, 2024
The East Kentucky Power Cooperative presented possible changes to the process for transferring capacity interconnection rights from a retiring generator to a replacement resource.
© RTO Insider LLC
PJM PC/TEAC Briefs: April 2, 2024
The PJM Planning Committee is considering a change to an issue charge framing a discussion on how capacity interconnection rights can be transferred from a retiring generator to a planned resource in the interconnection queue.
PJM
PJM PC/TEAC Briefs: March 5, 2024
The Planning Committee endorsed PJM’s long-term regional transmission planning proposal, advancing manual revisions that would expand the RTO’s planning horizon to 15 years.
© RTO Insider LLC
PJM PC/TEAC Briefs: Feb. 6, 2024
PJM's Planning Committee endorsed revised values for the installed reserve margin and forecast pool requirement used to calculate capacity procurement targets in the 2025/26 Base Residual Auction.
PJM
PJM PC/TEAC Briefs: Jan. 9, 2024

PJM presented a quick fix proposal to introduce a new long-term transmission planning approach that includes a longer 15-year horizon and considers state legislation that could affect generator participation in RTO markets.

PJM
PJM PC/TEAC Briefs: Dec. 5, 2023
PJM’s preliminary load forecast for 2024 sees higher growth for both summer and winter, driven by EVs, data centers and state incentivizes for heat pumps.  
PSEG
PJM PC/TEAC Briefs: Oct. 31, 2023
PJM stakeholders OK'd a manual change necessitated by the growth of data centers and heard reviews of multiple supplemental transmission projects.
PJM
PJM PC/TEAC Briefs: Oct. 3, 2023
The Planning Committee endorsed the recommended values in the 2023 Reserve Requirement Study, which would increase the amount of reserves that PJM aims to procure for the 2027/28 delivery year.
© RTO Insider LLC
PJM PC/TEAC Briefs: Sept. 5, 2023
PJM brought a quick fix solution before the Planning Committee, seeking to address the frequency and magnitude of load forecast adjustments being requested by electric distribution companies.
PJM
PJM PC/TEAC Briefs: Aug. 8, 2023
PJM stakeholders approved a load model for the 2023 reserve requirement study during the Planning Committee's Aug. 8 meeting.