Artificial Island
Delmarva officials are lobbying the PJM board to reject planners’ recommended reliability fix for Artificial Island.
FERC has ruled PJM acted properly in its solicitation of bids to fix a stability issue at Artificial Island, denying a request by losing bidder PSE&G.
A round-up of news from the PJM Transmission Expansion Advisory Committee on June 11, 2015.
Consumer advocates told PJM that Capacity Performance could saddle ratepayers with excessive costs because of its treatment of renewable energy.
PJM planners have selected LS Power to build a new 230-kV transmission line from New Jersey’s Artificial Island to Delaware to address stability issues at the nuclear complex.
PJM planners said they will announce their revised recommendation to address stability problems at the Artificial Island nuclear complex at a special TEAC meeting April 28.
FERC should reject PSE&G's claim that PJM erred in its solicitation of a stability fix for Artificial Island, the RTO said.
FERC needs to do more work to ensure Order 1000 opens transmission development to competition and results in interregional projects, developers said at Infocast’s 18th annual Transmission Summit last week.
A round-up of news from the PJM Transmission Expansion Advisory Committee (PJM TEAC) on Feb. 12, 2015.
PSE&G accused PJM of breaking its own rules in refereeing the competition for the Artificial Island stability fix, suggesting the RTO should start all over.
Want more? Advanced Search