Ten transmission upgrades have been placed in service in New England since October, ISO-NE engineer Jon Breard told the RTO’s Planning Advisory Committee.
PJM will spend only $162,000 to test the winter capabilities of 21 generators totaling 477 MW in 2018, RTO officials told the Operating Committee.
The PJM Board of Managers asked stakeholders for patience with the board’s ongoing investigation into the default of GreenHat Energy’s FTR portfolio.
NERC offered an upbeat report on the long-term health of the nation’s grid, celebrating results from its interconnection-wide frequency response studies.
PJM stakeholder rejected the RTO's proposal to enforce primary frequency response requirements beyond the standards of FERC Order 842.
Energy Storage is glaringly absent from MISO’s potential plans to manage a possible 40% renewable penetration on the grid, stakeholders told the RTO.
PJM is nearing the finish line in determining how it handles the primary frequency response requirements put in place by FERC Order 842.
A new report released says full market participation for renewables will require revisions to electricity markets, particularly in MISO and PJM.
FERC ruled that an existing Montana wind farm is exempt from a commission order requiring new generators to provide primary frequency response.
The Operating Committee endorsed PJM’s recommended winter weekly reserve targets, which consist of monthly values based on weekly peak load.