NECEC Halts Tx Line Construction, Regulators Suspend Env. Permit
DEP Commissioner Melanie Loyzim determined that new statutory changes in Maine would prevent the developers of NECEC from building the line as permitted.
© RTO Insider LLC
Overheard at NECBC Energy Conference: NECEC Line ‘Will be Built’
The recent rejection of the New England Clean Energy Connect transmission line was a top concern for attendees at NECBC's Executive Energy Conference.
Shutterstock
Maine, NY Voters Prioritize Conservation on Election Day
After Maine voters approved a measure to halt construction of the NECEC transmission line, the line's developer filed a lawsuit challenging the referendum.
Avangrid
Avangrid ‘Focused on Defeating’ NECEC Referendum
Avangrid is “focused on defeating” a ballot referendum designed to halt construction of the NECEC transmission line, CEO Dennis Arriola said.
Roger Merchant
Maine Regulators Hear from CMP, Residents on NECEC Permit
A delay of the NECEC transmission line could cost Central Maine Power an extra $67 million, according to CEO Thorn Dickinson.
Shutterstock
First Nations Oppose NECEC; Accuse Hydro-Québec of Energy Injustices
First Nation members held a webinar to explain their opposition to a new transmission line to bring Hydro-Québec’s electricity to New England.
Central Maine Power
FERC Investigating Avangrid-NextEra Dispute over NECEC Interconnection
FERC ordered Avangrid and NextEra to submit additional briefs in their ongoing dispute over the New England Clean Energy Connect transmission project.
P199, CC BY-SA-3.0, via Wikimedia
Scientists, First Nations Say Hydropower is Not Clean Energy
A critic of hydropower says politicians often make “vacuous statements about a particular energy source being clean, but that is not the case.”
Shutterstock
Maine Environmental Regulator Considering Suspension of NECEC Permit
Maine DEP Commissioner Melanie Loyzim is opening a proceeding to consider suspending the permit granted for the NECEC project.
Shutterstock
Maine Judge Vacates Public Land Lease for NECEC Tx Line