PJM MRC and Members Committee Preview
Our summary of the issues scheduled for votes at the PJM MRC and MC on 10/01/15. Each item is listed by agenda number, description and projected time of discussion, followed by a summary of the issue and links to prior coverage.

Below is a summary of the issues scheduled to be brought to a vote at the Markets and Reliability and Members committees Thursday. Each item is listed by agenda number, description and projected time of discussion, followed by a summary of the issue and links to prior coverage in RTO Insider.

RTO Insider will be at the PJM Conference and Training Center in Valley Forge, Pa., covering the discussions and votes. See next Tuesday’s newsletter for a full report. (Note: The meetings were delayed by a week because of the pope’s visit to Philadelphia and relocated to the CTC because facilities were not available in Wilmington on the new date.)

Markets and Reliability Committee

2. PJM Manuals (9:10-9:30)

Members will be asked to endorse the following manual changes:

  • Manual 40: Certification and Training Requirements. Makes miscellaneous edits; clarifies concepts, roles and responsibilities related to PJM’s systematic approach to training; updates the process for member training and PJM certification and reflects changes in terminology of operator titles.
  • Manual M10: Pre-Scheduling Operations. Adds procedures for maintenance outages under Capacity Performance rules: the requirement for PJM members to provide estimated “early return time” for planned outages; ensures that PJM will coordinate rescheduling if it withdraws or withholds approval of a planned outage; references PJM’s authority to withhold or withdraw approval of maintenance outages with at least 72 hours’ notice; adds requirement that maintenance outages be submitted at least three days prior to the operating day of their commencement.
  • Manual 14D: Generator Operational Requirements. Incorporates minor changes to the cold weather testing program for seldom-used generators. (See “Members Choose Status Quo on Winter Testing” in PJM Operating Committee Briefs.)
  • Manual 14B and 14A: Generation and Transmission Interconnection Process. Changes document how PJM will oversee transmission projects that have benefits in at least two categories, including baseline reliability upgrades, market efficiency and public policy. (See PJM Wins OK on Multi-Driver Tx Projects.)

3. PRICE FORMATION (9:30-10:30)

Members will be asked to vote on a proposal to change the $1,000/MWh energy market offer cap. The proposal, hammered out by Direct Energy, Old Dominion Electric Cooperative, the Independent Market Monitor and the PJM Power Providers Group (P3), would cap cost-based offers at $2,000/MWh and allow them to set LMPs, with market-based offers allowed to equal cost-based. Generators with approved fuel cost policies claiming costs above $2,000/MWh would be compensated through make-whole payments. (See related story, Consensus Near on Energy Market Offer Cap?)

Members Committee

CONSENT AGENDA (1:20-1:25)

B. The committee will be asked to endorse Reliability Assurance Agreement revisions regarding external capacity rights. The rule change allows load-serving entities to meet their internal capacity requirements using historic resources under certain conditions: The percentage internal resource requirement is enforced only if the locational deliverability area has been separately modeled due to certain triggers; a fixed resource requirement entity is permitted to terminate its FRR alternative election prior to meeting the minimum five-year commitment period requirement under certain conditions; and first-time elections of the FRR alternative are due four months prior to a Base Residual Auction instead of the current two-month deadline. (See IMEA Reaps Limited Relief from Capacity Rule Change.)

C. New Tariff language reflects the switch from eMkt to Markets Gateway.

ENDORSEMENT (1:25-2:25)

Members will be asked to vote on a proposal to change the $1,000/MWh energy market offer cap. (See MRC agenda item 3, above.)

Capacity MarketEnergy MarketPJM Markets and Reliability Committee (MRC)PJM Members Committee (MC)PJM Other Committees & TaskforcesReliability

Leave a Reply

Your email address will not be published. Required fields are marked *