PJM Plans for Changes in Tx Flows Without Con Ed-PSEG ‘Wheel’
PJM is using a three-pronged approach to prepare for next year’s termination of the Con Ed-PSEG wheel.

By Rory D. Sweeney

Preparing for next year’s termination of the Con Ed-PSEG “wheel,” PJM is using a three-pronged approach to coordinate stakeholder efforts through its Operating, Markets Implementation and Planning committees.

Each committee received updates last week on Consolidated Edison’s decision not to renew the agreement, under which NYISO moves 1,000 MW from upstate generators through Public Service Electric and Gas facilities in northern New Jersey to serve Con Ed load in New York City.

Con Ed said it would not renew the agreement, which began in the 1970s, after receiving a $680 million bill for two transmission upgrades in PSE&G territory — cost allocations that Con Ed complained were unreasonable. (See Con Ed-PSEG ‘Wheel’ Ending Next Spring.)

Overview of PSE&G – ConEd 600 400 Contract (PJM)
PJM and NYISO are determining new protocols for three interconnection facilities (Waldwick, Goethals and Farragut) that, as of next year, will no longer carry 1,000 MW from upstate New York, through PJM and back into NYISO.

PJM assigned Con Ed $629 million of the costs of PSE&G’s $1.2 billion Bergen-Linden Corridor upgrade to address a short-circuit problem; PSE&G was allocated $52 million. Con Ed was also assigned $51 million of PSE&G’s $100 million Sewaren storm-hardening project.

The transmission contract for the wheel expires May 1. Con Ed informed the grid operators that it found cheaper alternatives.

PJM and NYISO are collaborating on a replacement protocol that maintains reliability and is mutually beneficial to both grid operators. The protocol will adhere to FERC’s open access rules and support any existing market-to-market exchanges, PJM said. It will utilize existing infrastructure and won’t address merchant facilities, they said.

The Impact of PARs

Several stakeholders expressed concern that PJM’s goal of “free-flowing ties” would be hampered by the eight phase angle regulators (PARs) that currently govern the direction of flows on lines connecting the RTO with NYISO. There are one each on the A, B and C lines that flow 1,000 MW from PSE&G into New York, three just south of Waldwick on the J and K lines that flow the 1,000 MW into PSEG from upstate and two on the Branchburg-Ramapo 5018 line.

One of PARs on the 5018 line owned by Con Ed failed in June, and it was unclear whether NYISO and Con Ed plan to replace it. Participants asked if the PARs could be removed. “I worry about PJM calling balls and strikes on market optimization,” said Ed Tatum, vice president of transmission for American Municipal Power.

Several participants questioned why the PARs must be kept at all. Speaking after the meeting, Mike Bryson, PJM’s vice president of operations, explained that NYISO has always had a philosophy of using control devices to manage congestion and loop flow.

‘Insider Information’

Other participants expressed concern that the discussions between PJM, NYISO, PSEG and Con Ed haven’t been transparent. Dave Pratzon of GT Power Group, which represents some generators, asked for confirmation that the discussions haven’t included any “insider information.”

Bryson said PJM has ensured that conversations never overstepped the rules. “When we approach that line, we back the parties away,” he said.

Wheel’s New Look

PJM officials said further detail wouldn’t be available until August’s MIC meeting because of the timeline required to approve changes to the PJM-NYISO joint operating agreement. A broader picture wouldn’t be available until September.

Tim Horger, manager of market simulation at PJM, said the New York interface will likely be changed to model what’s “actually going to happen in real time.”

Both NYISO and PJM ran independent studies to determine interchange flows unconstrained by PARs — what they called “natural flow.” The studies were based on a summer peak case and found that 32% would flow over the western ties that connect between the “Twin Tiers” of Pennsylvania and New York, while 68% would interchange between the eastern ties involved with the wheel.

PJM engineer Asanga Perera said that part of the wheel’s benefit today is that the 1,000 MW coming into New York City from New Jersey pushes back on bottlenecks north of the city so it doesn’t see additional congestion.

Cost Allocation

With Con Ed out of the picture, the $680 million in upgrade costs will be reallocated to the existing stakeholders based on guidance in PJM’s manuals, officials said.

In response to a request from Tatum, PJM Vice President of Planning Steve Herling said he would look into providing a document answering frequently asked questions about the change and any public documents that governed the decision-making process.

Company NewsNew JerseyNew YorkPennsylvaniaPJM Market Implementation Committee (MIC)PJM Members Committee (MC)PJM Operating Committee (OC)PJM Other Committees & TaskforcesPJM Planning Committee (PC)ReliabilityTransmission OperationsTransmission Planning

Leave a Reply

Your email address will not be published. Required fields are marked *