Minnesota regulators voted unanimously to require that Amazon demonstrate a need for a 250-unit fleet of backup diesel generators at its proposed data center in the state.
Facing a 40% hike in electricity demand by 2030, New Jersey needs to rapidly craft a plan on how to boost generation and develop its transmission and distribution system, speakers at a conference on the state’s energy future said.
The PJM Planning Committee endorsed by acclamation revisions to Manual 14H to conform with changes to the RTO’s surplus interconnection service process FERC approved in February.
FERC has given the Palisades Nuclear Plant special permission to exceed MISO’s 36-month limit on generator suspensions as owner Holtec International works through the plant’s reopening.
A Brattle Group study found that New York could achieve 8.5 GW in “grid flexibility” measures by 2040, saving consumers more than $2 billion a year.
ERCOT’s Board of Directors has approved staff’s recommendation to pursue the use of 15 mobile generators as an alternative to extending the life of two aging gas units slated for retirement in South Texas.
Public Service Enterprise Group saw an “over-12-fold” increase in mature leads and inquiries from customers exploring “large load and data center projects” over the past year, CEO Ralph LaRossa said in the utility’s fourth-quarter earnings call.
The U.S. Energy Information Administration projects 2025 additions of 32.5 GW of solar, 18.2 GW of storage, 7.7 GW of wind, 4.4 GW of gas and 0.2 GW of all other forms of generation.
PJM stakeholders voted for a third consecutive meeting to delay acting on revisions to Manual 14H intended to clarify when developers may add or remove parcels from their project footprint.
A report released in February by Aurora Energy Research has found that President Donald Trump’s executive orders have put 43 GW of East Coast offshore wind projects at risk of permitting delay.