October 5, 2024

Generation

Georgia Power
Vogtle 3 Activation Delayed Again for Safety Concerns
Southern Co. said that Unit 3 at Vogtle nuclear plant in Ga. suffered yet another delay and is not expected to come online until at least the second quarter.
Shutterstock
Hydro-Quebec’s Leadership Shakeup Could Impact New England
The resignation of CEO Sophie Brochu sent a shockwave through the Canadian energy sector that could reverberate into New England.
PacifiCorp
FERC Approves PacifiCorp’s Interconnection Replacement Rules
FERC approved changes to PacifiCorp’s interconnection procedures that will allow it to use retiring generators’ interconnection capacity for new power plants.
NYISO
NYISO Finalizes CRIS Tariff Revisions
NYISO presented a proposed timeline for finalizing tariff revisions related to capacity resource interconnection service expiration and transfer rules.
U.S. Department of the Interior
DOI’s Klein Picked to Run Bureau of Ocean Energy Management
The U.S. Department of the Interior announced that Elizabeth Klein has been named director of the Bureau of Ocean Energy Management.
Shutterstock
Ohio Law Amended to Declare Natural Gas a Form of ‘Green Energy’
Declaring natural gas green has been a goal of The Empowerment Alliance, an anonymously funded 501(c)(4) nonprofit founded in 2019 with Ohio roots.
© RTO Insider LLC
FERC Accepts SPP Order 845 Compliance Filing, Grants Tx Planning Waiver
FERC has accepted a pair of SPP tariff revisions related to generator interconnection procedures and transmission planning.
Entergy
Regulators File Emergency Motion in Ongoing Grand Gulf Battle
New Orleans city council and the Ark. and La. PSCs filed an emergency motion after an Entergy press release claimed it owed no additional refunds to ratepayers.
Duke Energy
North Carolina Regulators Approve Duke’s 1st Carbon Plan
The North Carolina Utilities Commission approved Duke Energy's first carbon plan to comply with state law calling for carbon neutrality by 2050.
Shutterstock
NJ’s Aggressive Clean Energy Plans Face 2023 Challenges
New Jersey’s far-reaching OSW plans face challenges as the first project undergoes permit scrutiny and the state launches a third coastal wind solicitation.