SPP told stakeholders it will have to make decisions on potential interregional projects in the 2019/20 coordinated system plan before hearing from MISO.
MISO will rely on the same set of futures for the third straight year when it evaluates transmission projects in its 2020 Transmission Expansion Plan.
MISO released draft Tariff language that would allow energy storage resources to compete for projects in the RTO’s annual Transmission Expansion Plan.
MISO plans to revamp its annual MTEP report to emphasize the justifications and analyses behind proposed projects while removing some planning process narratives.
Transmission developers, planners and regulators gathered at the Key Bridge Marriott in Arlington, Va., for Infocast’s annual Transmission Summit East.
In an assessment of this year’s load forecast, MISO told load-serving entities they could do more to support their individual forecasts with documentation.
PJM scheduled two meetings in the coming weeks to discuss rules for removing projects from the Regional Transmission Expansion Plan.
FERC authorized NextEra Energy Transmission Midwest to recover all “prudently incurred” costs related to the Hartburg-Sabine Junction 500-kV project.
SMUD said it is canceling a 500-kV transmission line project it was developing with WAPA because it had proven too expensive and was no longer needed.
State regulators are bringing in the MISO and SPP market monitors to help solve seams issues between the two RTOs.