Transmission Planning
MISO planners emphasized that its hypothetical map of projects is not what a final second portfolio could look like under its long-range transmission planning.
SREA said Duke Carolinas' and TVA's holiday blackouts were likely avoidable had they built robust transmission links and had better access to organized markets.
MISO and SPP said they plan to treat Joint Targeted Interconnection Queue projects as large generator interconnection projects when allocating costs.
MISO remains set on limiting transmission congestion by instituting a lower system impact threshold on interconnecting generation.
Ben Schumin, CC BY-SA-2.0, via Wikimedia
Beacon Wind I drew unanimous public support during public hearings on the transmission line needed for the1,230-MW wind farm planned off the New York coast.
SPP and MISO plan to apply for grants from the Department of Energy to help fund five transmission projects recently identified in their JTIQ work.
NYISO announced that it had completed the final interconnection studies for its Class Year 2021 group of projects.
MISO has kicked off its second request for proposals process coming out of its $10 billion long-range transmission portfolio.
Stakeholders requested MISO take a second look into its recommendation of an expedited transmission project in Michigan.
The energy storage units planned in great number in New York can also serve the state’s grid as transmission assets, a new study finds.
Want more? Advanced Search