The D.C. Circuit Court of Appeals affirmed FERC’s ruling that NextEra Energy is responsible for replacing the circuit breaker at its Seabrook Station nuclear plant to accommodate the interconnection of the New England Clean Energy Connect transmission line.
The D.C. Circuit upheld FERC’s decision to OK PJM’s FTR forfeiture rule without ordering refunds under previous rules implemented without commission approval.
The order complicates ISO New England's capacity auction scheduled for Monday.
The D.C. Circuit Court of Appeals found fault with reviews by FERC on climate and environmental justice issues for planned LNG projects in Texas.