Opinion writer Shahid Mahdi worries about the cybersecurity risks of co-location, and asks if a co-located data center is hit with ransomware, does the nuclear plant have to trip offline?
PJM presented stakeholders with an initial look into the first of a handful of compliance filings it is drafting to define how co-located large loads receive transmission service.
FERC told PJM to change its rules to allow for co-located load at generators, with new transmission services and other tweaks.
Stakeholders urged FERC to consider reliability and consumer costs when weighing approaches to co-located large loads.
In comments on a FERC investigation, PJM said there are several pathways to bolster the ability for large consumers to benefit from co-locating with generators.
FERC voted unanimously to launch a review of data center co-location issues in PJM that will look into whether the RTO’s tariff needs to be revised to ensure grid reliability and fair costs to customers.