Exelon

Alison Williams, B Strategic Solutions
Stakeholder Forum: PJM Is Flailing, but There’s a Solution
Everyone knows we need more electricity, and it’s painfully clear PJM is not capable of responding to increased demand, say energy consultants Brad Viator and Alison Williams.
© RTO Insider LLC
FERC Opens Door for PJM to Refile RTEP Protocol Proposal
FERC opened the door for PJM to resubmit a previously rejected proposal to shift its Regional Transmission Expansion Plan protocol from its operating agreement to its tariff, while dismissing a rehearing request for a connected proposal by the RTO’s transmission owners.
© RTO Insider 
Meeting the Surge in Demand Without Sacrificing Affordability

The Edison Electric Institute’s annual conference and thought leadership forum featured numerous discussions on the industry's ability to meet the explosive demand without sacrificing reliability and affordability.

© RTO Insider 
PJM Stakeholders Reaffirm Board Election Results
The PJM Members Committee voted against reconsidering whether to reelect Terry Blackwell to another term on the Board of Managers.
Peretz Partensky, CC BY 2.0, via Wikimedia Commons
New Jersey Opts to Explore Nuclear Options
Facing a projected energy shortfall, New Jersey is evaluating whether it is feasible to build an additional nuclear generation plant to add to the three that provide about 40% of the state's electricity.
© RTO Insider 
PJM Stakeholders Vote Out 2 Board Members

PJM’s Members Committee voted not to reelect two incumbent members of the RTO’s Board of Managers: Chair Mark Takahashi and Terry Blackwell.

Talen Energy
FERC Approves $180M Annually for RMR Deals with Brandon Shores and Wagner Plants
FERC approved settlements on reliability must run deals that will keep the Brandon Shores Generating Station and the H.A. Wagner Generating Station in Maryland running until May 31, 2029.
© RTO Insider 
Stakeholders, NERC Respond to FERC Large Loads Investigation
Stakeholders urged FERC to consider reliability and consumer costs when weighing approaches to co-located large loads.
Aurora Energy Research
Around the Corner: The Promise, Uncertainty and Unparalleled Risk of Data Center Load
Columnist Peter Kelly-Detwiler writes about the explosion of data center load requests and the enormous risks to utilities and ratepayers of overbuilding assets.
© RTO Insider LLC 
PJM PC/TEAC Briefs: March 4, 2025
PJM presented the Planning Committee with a draft amendment to the Deactivation Enhancement Senior Task Force’s issue charge to add a key work activity focused on creating pro forma language for reliability-must-run agreements with generation owners seeking to deactivate a unit identified as being necessary for reliability.

Want more? Advanced Search