September 29, 2024

Federal Energy Regulatory Commission (FERC)

Entergy
FERC OKs $142M Grand Gulf Settlement with Entergy Arkansas
Entergy will pay its Arkansas affiliate $142.3 million in the latest settlement in the ongoing billing disputes over the utility’s Grand Gulf Nuclear Station.
© RTO Insider LLC
PJM Awaiting FERC Response to Court Rejection of 2024/25 Capacity Auction Parameters
PJM updated stakeholders on how it will proceed in the wake of a 3rd Circuit ruling vacating a FERC order allowing the RTO to revise a parameter after bids had been received for the 2024/25 Base Residual Auction.
Arizona Public Service
FERC Upholds, Clarifies Generator Interconnection Rule
FERC rejected challenges to its new generator interconnection rules under Order 2023, while making minor modifications and extending the compliance date.  
© RTO Insider LLC
MISO Members Mull Full Impact of DER Aggregations in Markets
MISO members pondered at Board Week over how quickly the full impact of Order 2222 will be felt across the footprint.
© RTO Insider LLC
FERC Proposes Restricting Reactive Power Compensation
FERC is seeking comments on a proposal to prohibit including charges associated with reactive power in transmission rates.
FERC, via Hitachi ABB Power Grids Velocity Suite
FERC: Markets Stable in 2023; Gas Continues to Dominate Mix
2023 began with a mild winter, setting the pace for a relatively quiet year in which natural gas and wholesale electricity prices dropped and the U.S. added a net 26 GW in generation capacity.
Sun Valley Solar Solutions
FERC Rejects PURPA Petition in Arizona Solar Case
FERC declined to act on a petition that accused the Salt River Project of violating PURPA with rates that discriminate against customers with rooftop solar.
© RTO Insider LLC
3 FERC Nominees Quizzed by Senators in Hearing Short on Fireworks
The three nominees to be FERC commissioners faced questions from the Senate Energy and Natural Resources Committee in a hearing that was light on fireworks.
© RTO Insider LLC
FERC, State Regulators Renew Collaboration
Nearing completion of its transmission planning rulemaking, FERC said it is forming a new working group with state regulators with a focus on reliability.
NYISO
FERC Accepts NYISO Proposal to Coordinate Queue, Transmission Processes
FERC approved NYISO’s proposed tariff revisions aimed at enhancing the coordination between its interconnection study processes, minimizing redundant study evaluations and streamlining study processes.