generator interconnection agreement (GIA)
A group of utilities have filed for rehearing of a show cause order FERC issued in June that could change the practice of who pays for interconnection lines at four ISO/RTOs.
With FERC’s blessing, MISO will synchronize its generator replacement process with its generation suspension and retirement process to give interconnection customers more flexibility.
MISO plans to revise its rules around commercial operation dates to allow interconnection customers to begin operating about a decade after they first enter the queue.
FERC refused a MISO interconnection agreement for a Michigan solar farm while Commissioner Mark Christie used the order to point out "a defect" in the MISO Tariff.
MISO signaled it's somewhat receptive to stakeholder ideas on loosening its commercial operation date deadlines in its generation interconnection queue.
MISO has compromised with stakeholders on a few details in its proposal to downsize the number of projects allowed in its generator interconnection queue.
MISO’s quarterly Board Week explored the reasons behind its growing number of generation projects that have the stamp of approval to connect to the system but remain unbuilt.
In light of stressed-out supply chains and a bogged-down study process, MISO has agreed to re-evaluate its rules around commercial operation dates in its interconnection queue.
MISO says it will file in October to put stronger obligations and more monetary risk on queue entry to weed out speculative generation projects and take pressure off its overcrowded interconnection queue.
MISO proposes megawatt limits on annual project proposals, tripled entry fees and escalating penalty charges in its quest to oust speculative projects and lighten its gridlocked interconnection queue.