Barbara Tyran, director of ACORE’s Macro Grid Initiative, discusses the issues grid operators and regulators face in ensuring cost-effective, reliable service.
Matthew T. Rader, CC BY-SA 4.0, via Wikimedia Commons
Representatives of FERC, MISO, the Kansas Corporation Commission and Pattern Energy discussed interregional transmission planning at the CLEANPOWER conference.
MISO and SPP said they will likely establish a smaller interregional project type, which could produce the two's first cross-border transmission project.
SPP’s Strategic Planning Committee approved a task force’s recommended framework to manage DC tie revenue-requirement recovery in the proposed RTO West.
Reliability and clean energy related public policies are increasing the need for and benefits of large-scale transmission to avoid increased electricity costs.
A Brattle Group-Grid Strategies study on transmission planning pinpoints inefficiencies that hinder the integration of new renewable resources.
The developer of a proposed 2,100-MW HVDC line escalated its fight with PJM, asking FERC to eliminate capacity rules it says are blocking it from competing.
New York selected the Clean Path and the Champlain Hudson Power Express transmission projects from among seven submitted to the CES Tier 4 solicitation.
MISO and SPP have shared an early concept for cost allocation on joint transmission projects intended to ease the two’s crowded interconnection queues.
SPP released a comprehensive report on the week of February's severe winter storm, calling it the most operationally challenging week in its 80-year history.
Want more? Advanced Search