Xcel Energy is seeking approval for a large load tariff in Colorado that includes an optional clean transition tariff to encourage the development of emerging carbon-free resources.
A delay in the repair of Unit 3 of Xcel Energy’s coal-fired Comanche Generating Station has sparked questions among Colorado regulators about the utility’s ability to meet summer peak demand in 2026.
Colorado regulators approved 3.2 GW of new resources requested by Public Service Company of Colorado under an expedited approval process designed to take advantage of soon-expiring federal tax credits.
Colorado regulators have declined to reconsider their decision finding that it would be in the public interest for Public Service Company of Colorado to join SPP’s Markets+.
Black Hills Colorado Electric has filed an application with Colorado regulators to join SPP's Markets+, saying it has no choice because it is embedded in a balancing authority that will be a Markets+ participant.
With a surge in interconnection requests from large load customers, Public Service Company of Colorado has fallen behind on processing applications, a situation that has sparked concern from state regulators.
The Colorado Public Utilities Commission granted a one-year extension to Unit 2 of the coal-fired Comanche power plant, as uncertainty lingers about the fate of outage-plagued Unit 3.
Public Service Company of Colorado and the Polis administration want to keep Unit 2 of the coal-fired Comanche Generating Station running a year longer than planned.
The Colorado PUC issued a split decision approving Public Service Company of Colorado’s application to join SPP’s Markets+, finding that market participation is in the public interest and will “provide a number of benefits.”
Xcel Energy is fighting two counties that are blocking a segment of the company’s Colorado’s Power Pathway transmission project.