Reliability Pricing Model (RPM)
The PJM MRC endorsed an issue charge to hire a consultant to investigate the pros and cons of a sub-annual capacity market and what designs stakeholders feel would be feasible.
The clearing price is the highest in PJM history and an increase of $59.22 (22%) from last year’s record for the RTO.
Key challenges in the review are tightening supply and demand, the uncertain cost of new capacity and accounting for changes PJM has made to how it identifies reliability risks and determines the capacity value for different resource types.
Anger over a recent dramatic rate hike and fears of energy shortfalls because of a predicted future rise in demand have prompted New Jersey to look anew at whether the state should consider pulling out of PJM.
The PJM Board of Managers is pursuing an approach that would spread the cost of continuing to operate Constellation Energy’s Eddystone Generating Station to all PJM consumers.
PJM's Markets and Reliability Committee discussed a problem statement and issue charge brought by Pennsylvania Gov. Josh Shapiro to open a discussion on establishing a sub-annual capacity market design.
PJM’s Public Interest and Environmental Organization User Group voiced mixed views on the RTO’s policy trajectory, praising advances in generation interconnection over the past year while raising concerns about rising costs and transparency.
The Maryland Office of People’s Counsel filed a complaint alleging the rules used in PJM's 2025/26 Base Residual Auction would require consumers to pay twice for capacity provided by generators operating on RMR agreements.
PJM’s Markets and Reliability Committee endorsed two proposals to revise the RTO’s ELCC formula to add two new generation categories and limit the penalties resources face if their accreditation declines between auctions.
PJM announced it will seek to establish a $325/MW-day price cap on capacity prices and a $175/MW-day floor for the 2026/27 and 2027/28 Base Residual Auctions following discussions with Pennsylvania Gov. Josh Shapiro to resolve a complaint he filed over increased capacity costs.
Want more? Advanced Search