Wisconsin Public Service Commission (WI PSC)
FERC authorized an exception to MISO’s interconnection rights transfer process, allowing two Xcel Energy subsidiaries to cooperate on a replacement of a coal-fired plant with a solar farm.
A court of appeals has toppled Wisconsin’s longstanding ban on aggregators of demand response participating in wholesale markets.
The Public Service Commission of Wisconsin said it’s missing several details from We Energies regarding its multiyear plan to substitute gas for coal at its Oak Creek Power Plant.
The planned 625-MW gas-fired Nemadji Trail Energy Center encountered another hitch after the Superior City Council refused to move ahead on zoning changes necessary for breaking ground.
Outgoing Organization of MISO States Executive Director Marcus Hawkins appeared before the RTO’s Advisory Committee for a final time before taking on a new role as a Wisconsin PSC commissioner.
Wisconsin’s GOP-controlled Senate voted to reject Public Service Commissioner Tyler Huebner’s nomination to the commission — nearly four years into his time there.
The timeline for building the Nemadji Trail Energy Center has been pushed into next year as clean energy groups continue to challenge the need for the planned gas plant.
Cardinal Hickory Creek transmission project overcame another legal hurdle: a Wisconsin county judge found that regulators adequately scrutinized the project.
WEC Energy Group’s first-quarter earnings dipped year-over-year, owing to one of the mildest winters in its service territory in more than a century.
A report examining the use of the interstate system as a corridor for expansion of the nation’s transmission system concluded it can be done relatively quickly.
Want more? Advanced Search