FERC OKs Salt River Project Agreement to Join EIM
FERC approved an agreement between CAISO and the Salt River Project that establishes the rules governing the utility’s participation in the Western EIM.

By Hudson Sangree

FERC last week approved a nonconforming agreement between CAISO and the Salt River Project (SRP) that establishes the rules governing the Arizona utility’s participation in the Western Energy Imbalance Market.

Publicly owned SRP has ownership interests in more than a dozen major natural gas, coal and nuclear generating stations. It plans to begin participating in the EIM in April 2020.

“According to CAISO, the agreement [with SRP] differs from the pro forma EIM Entity Agreement in that it reflects the legal and regulatory issues unique to Salt River as a publicly owned utility under Section 201f of the Federal Power Act,” FERC noted in its order (ER19-539).

Gila River Power Station | SRP

CAISO’s agreement with the Balancing Authority of Northern California (BANC) contained similar nonconforming provisions. (See SMUD Balancing Area Inks Agreement for EIM Membership.) FERC accepted that agreement in October 2018.

The ISO’s agreements with the public entities are different in several respects from its agreements with private companies.

For instance, CAISO’s agreement with SRP clarifies the utility is an exempt entity under FPA Section 201f and that it may terminate the agreement regardless of any action or inaction by FERC with respect to CAISO.

The EIM agreements with SRP and BANC contain identical indemnity and liability provisions.

And the CAISO-SRP agreement includes “language to address state law considerations unique to publicly owned utilities” that are modeled after the SPP Open Access Transmission Tariff, according to FERC.

“Salt River asserts that these negotiated terms were important to its decision to move forward with participating in the EIM because they recognize Salt River’s exempt status under the FPA and provide Salt River with protection important to its ratepayers,” FERC said.

“Salt River also states that the modifications made to section 10.5 of the agreement provide a process for addressing conflicts between Arizona law and the CAISO Tariff, and further notes that the process is modeled after similar processes found in the Southwest Power Pool Inc. and Midcontinent Independent System Operator Inc. tariffs.”

Several entities filed motions to intervene, including the Southwest Public Power Agency (SPPA), which manages resources for 19 utility districts in Arizona. SPPA did not oppose SRP joining the EIM, FERC said, but requested that the commission “further analyze the implications of Salt River’s entry into the EIM to ensure that customers are not negatively affected.”

“SPPA notes that, because Salt River is a public entity, its entry into the EIM will not be analyzed for market power implications, and that this may be the only opportunity the commission has to address issues associated with Salt River’s EIM participation,” FERC wrote.

But the commission rejected SPPA’s comments as beyond the scope of the proceeding because the agency did not oppose SRP’s entry into the EIM or raise concerns regarding its agreement with CAISO.

FERC noted that SRP would still be subject to the EIM Market Power Mitigation Procedures set forth in CAISO’s Tariff and that it is the job of the ISO’s Department of Market Monitoring to catch any market power issues.

“We also note Salt River’s commitment to work with its wholesale energy and transmission service customers to examine current contractual relationships and assess whether they will be affected by Salt River’s anticipated participation in the EIM,” FERC said. “We encourage Salt River to follow through on this commitment and to work with its customers to address any issues that may arise.”

The EIM has been expanding across much of the West.

Its current members include Arizona Public Service, Idaho Power, NV Energy, PacifiCorp, Portland General Electric, Puget Sound Energy and Powerex. The Sacramento Municipal Utility District plans to begin participating in the market in April 2019. The Los Angeles Department of Water and Power and Seattle City Light also are scheduled to go live in April 2020. Public Service Company of New Mexico recently received state regulators’ permission to join the EIM by 2021.

The Bonneville Power Administration remains in discussions with stakeholders about joining the EIM, with a possible activation date in 2022. (See BPA Stays on Track to Join the Western EIM.)

ArizonaEnergy MarketWestern Energy Imbalance Market (WEIM)

Leave a Reply

Your email address will not be published. Required fields are marked *