November 23, 2024
Manual Change: Training and Certification (M40)
The following PJM manual change was approved by the Markets and Reliability Committee on Feb. 28, 2013, effective March 1, 2013. For more information, contac...

The following PJM manual change was approved by the Markets and Reliability Committee on Feb. 28, 2013, effective March 1, 2013. For more information, contact PJM Member Relations.

Manual 40: Training and Certification Requirements – verification of operators performing reliability functions

Reason for Change: FERC Order 742 (issued Nov. 18, 2010) ratified NERC Reliability Standard PER 005 (System Personnel Training) to ensure the qualifications of system operators performing real-time, reliability-related tasks. Most requirements are effective April 1, 2013.

Impact: The changes require that all applicable operators be verified on the reliability-related tasks assigned to them (both common terminal tasks and company-specific functions) before the operator assumes independent shift duties. Creates a Systematic Approach to Training (SAT), as developed by the Dispatcher Training Subcommittee.

  • Operators must be re-verified on any modified tasks within six months of the modifications. Verification may include direct observation in a real-time or simulated environment or completion of relevant training and certification and verbal questioning.
  • All task verifications must be entered into a new Task Tracking Module of the PJM Learning Management System (LMS).
  • The one-year grace period for completion of Initial Training Program was eliminated for TO operators. (A similar provision for certification had already been removed to comply with NERC requirements.) A new initial training program is being created (using SAT). The course can be completed either online or in person.

PJM Contacts: Glen D. Boyle, manager, system operator training; Michael J. Sitarchyk, manager, state and member training.

FERC & FederalPJM Markets and Reliability Committee (MRC)PJM Other Committees & TaskforcesReliability

Leave a Reply

Your email address will not be published. Required fields are marked *