December 25, 2024
Reliability Projects in 2013 RTEP Likely to Exceed $1B
PJM transmission planners identified more than $800 million in reliability upgrades for inclusion in the PJM RTEP for 2013. Costs may exceed $1 billion.

PJM transmission planners have identified more than $800 million in reliability upgrades for inclusion in the Regional Transmission Expansion Plan (RTEP), officials told members last week. Costs are likely to exceed $1 billion once all projects are tallied.

The upgrades, outlined to the Transmission Expansion Advisory Committee Thursday, include 26 projects to address high voltage problems, 10 to fix load deliverability problems and four areas with short circuit problems.

Short Circuit Upgrades

The biggest single reliability project is likely to be one addressing the short circuit problem in the PSE&G transmission zone outside New York City.

The 2012 PJM RTEP identified several buses in the PSEG zone where the fault currents exceed 80 kA. Potential solutions include upgrading stations to 90 kA and installing current limiting reactors.

Another possible solution being reviewed by PJM is to isolate the Hudson 230 kV from the 138 kV at Marion and 345 kV at Farragut. The 138 kV buses and transmission facilities on the path from Linden to Bergen would be converted to double circuit 230 kV or 345 kV lines. The 345 kV proposal is estimated to cost $1.1 billion but eliminates the need for $588 million of approved RTEP projects, resulting in a net cost of $515 million.

Also under consideration is a proposal to build parallel 700 MW high voltage DC converter stations, estimated at $800 million to $1.1 billion.

One member said PJM should open a proposal window to solve the issue. But PJM officials said they were unlikely to do so — meaning PSEG would have the right to construct the solution — because of the urgency of the problem.

“We will be hard pressed to get any solution by 2015,” said Paul McGlynn, general manager of system planning. “It doesn’t really lend itself to a proposal window.”

“The board has been concerned that this [problem] has been hanging on for quite a while,” added Steve Herling, PJM vice president for planning.

PJM staff is refining its cost analyses and performing additional load flow analyses. Any solution will have to accommodate PJM’s contract with NYISO for the so-called Consolidated Edison “wheel.” The wheel funnels 1000 MW from NYISO through PSEG and into New York City.

In addition to the PSEG short circuit project planners also identified “overstressed” circuit breakers in the Duke Energy Ohio and Kentucky (cost to be determined), Duquesne Light (cost TBD) and Jersey Central Power and Light Co. transmission areas (estimated cost $360,000).

High Voltage

Location of High Voltage Problems Identified by PJM (Source: PJM Interconnection, LLC; p. 11, RTEP Reliability Analysis, TEAC 7-10-13)
Location of High Voltage Problems Identified by PJM (Source: PJM Interconnection, LLC; p. 11, RTEP Reliability Analysis, TEAC 7-10-13)

PSEG also figures prominently in upgrades to fix high voltage problems, with 13 projects with a total cost of $122 million. AEP had five projects totaling $17 million while AEC had two projects totaling almost $30 million. PEPCO, PPL, Jersey Central Power and Light, Allegheny Power System and PECO had upgrades ranging from $16 million to $4 million.

PJM’s Board of Managers will be asked to approve the high voltage projects in October, PJM officials said.

Load Deliverability

Twenty-five of 27 Locational Deliverability Areas (LDAs) passed the load deliverability test with no thermal or voltage issues while voltage violations were identified in the Penelec transmission zone resulting from the Penelec and Western MAAC load deliverability tests.

Planners identified 10 projects to solve the problems. One in PPL is estimated at $84.5 million and another in Atlantic City Electric Co. at $11.2 million. Costs of the remaining projects, one in Delmarva Power and Light and seven in PEPCO, have not been estimated. 

PJM Transmission Expansion Advisory Committee (TEAC)ReliabilityTransmission Planning

Leave a Reply

Your email address will not be published. Required fields are marked *