October 4, 2024
FERC Accepts Order 1000 Compliance Filing
FERC accepted NYISO’s fourth Order 1000 compliance filing, rejecting protests from transmission developers.

FERC has accepted NYISO’s fourth Order 1000 compliance filing, turning aside the protests of transmission developers that claimed it unfairly favored incumbent transmission owners (ER13-102-007).

LS Power and NextEra had protested the ISO’s right to terminate development agreements if a force majeure event prevents a non-incumbent developer from completing its project by the in-service date. (See Tx Developers Challenge NYISO, SPP, ISO-NE Order 1000 Filings.)

NYISO and the New York Transmission Owners submitted their fourth Order 1000 compliance filing in May. It included a pro forma development agreement for NYISO’s reliability transmission planning process.

“NYISO argues that it must have the option to terminate the development agreement and identify alternative means of satisfying an identified reliability need if a developer cannot complete its project by the required project in-service date,” FERC wrote on Dec. 23.

The commission cited a similar provision at PJM, ordering NYISO to add comparable language in its development agreements with incumbent transmission owners to prevent discrimination.

In a second order Dec. 23, FERC rejected a NYISO filing that the commission said was unfair to competitive transmission developers (ER15-2059).

FERC said the proposal “subject[s] nonincumbent transmission developers to an interconnection process with different requirements than the interconnection process that applies to incumbent transmission owners.” While all interconnection customers are required to obtain system impact and facility studies, the nonincumbents were required under the proposal to additionally submit a feasibility study and deposits for all three studies.

NYISO had argued the incumbent would have already conducted a feasibility study in its normal planning process, but FERC said that would create two different processes that are not comparable.

— William Opalka

Transmission Planning

Leave a Reply

Your email address will not be published. Required fields are marked *