December 22, 2024
FERC OKs Cost Allocation of PJM Transmission Projects
FERC approved cost allocation responsibility assignments for 39 baseline upgrades recently added to the PJM Regional Transmission Expansion Plan.

By Rory D. Sweeney

FERC last week approved cost responsibility assignments for 39 baseline upgrades recently added to PJM’s Regional Transmission Expansion Plan (ER17-2362).

The allocations were filed on Aug. 25. Thirty-five projects will be allocated to the transmission zone in which they are located, including five projects of less than $5 million each. Two projects will address Form 715 local planning criteria, and 28 involve circuit breakers and associated equipment. The remaining four projects are “lower voltage facilities” that are allocated based on the solution-based distribution factor (DFAX) method.

pjm ferc cost allocation
PJM’s control room | PJM

Old Dominion Electric Cooperative challenged two of the DFAX allocations, saying it was unable to replicate PJM’s analysis. It asked the commission to direct PJM to provide the detailed information “for the sake of transparency” and to determine whether the upgrades are appropriately allocated entirely to the American Electric Power zone. ODEC questioned PJM’s 100% allocation of another project to the American Transmission Systems Inc. zone, arguing that the results of the DFAX analysis produce a 1.32% allocation to ATSI.

FERC accepted PJM’s defense of its allocations. The RTO said because only ATSI had a DFAX percentage greater than 1% for project b2898 — reconductoring the Beaver-Black River 138-kV line — that zone was assigned the entire cost of the $20 million project.

PJM said it used “an appropriate substitute proxy” for the baseline projects, reactive power upgrades that can’t be addressed by DFAX analysis, which measures over transmission lines or transformers. PJM developed an “interface comprised of the lines and transformers that surround the entire AEP system,” a localization method PJM often uses “because the majority of reactive power upgrades are intended to provide local voltage support.”

ODEC has also asked the D.C. Circuit Court of Appeals to overturn FERC’s policy of allocating all costs from Form 715 projects to the zone of the transmission owner whose criteria triggered the upgrades. ODEC said the cost allocation for the two Form 715 projects should be subject to the outcome of its challenge.

PJMTransmission Planning

Leave a Reply

Your email address will not be published. Required fields are marked *