Planning Committee
PJM Presents Quick Fix Proposal on Battery Dispatch Modeling
PJM’s Julia Spatafore presented a quick-fix proposal to model battery storage dispatch in Regional Transmission Expansion Plan base cases. The quick-fix process allows an issue charge and problem statement to be brought alongside a solution.
Battery units are modeled as offline under Manual 14B: PJM Region Transmission Planning Process, which would be revised to allow them to be dispatched in the block dispatch methodology. The resources are already modeled as online in generation deliverability studies, a misalignment Spatafore said would be closed by the proposal. The change would also increase the generation available when planning transmission and support state policies promoting storage.
Transmission Expansion Advisory Committee
Transmission Projects for Large Loads
Dayton Power and Light presented a $246 million transmission project to supply an 800-MW service request of load near the Darby Substation in Marysville, Ohio. A 765/345-kV substation, named Patina, would be cut into the existing 765-kV Marysville-Flatlick line. Two new 5-mile 345-kV lines would connect Patina to a new 345-kV substation, named Weaver, serving the customer. The project has an in-service date of May 1, 2031, and is in the conceptual phase.
Exelon presented a 263.5 million project in the BGE zone to serve an 880-MW customer near the Calvert Cliffs nuclear plant in Maryland. A 500-kV substation, named Camp Canoy, would be constructed with a 175-MVAR, 500-kV capacitor bank. It would be cut into the 500-kV Calvert Cliffs-Waugh Chapel and Calvert Cliffs-Chalk Point lines. The customer is seeking to come online in 2028 with 190 MW before reaching full capacity in 2030. The project is in the engineering phase, with a projected in-service date of March 1, 2028.
Exelon also presented a $245 million project in the ComEd zone to serve a customer seeking to bring 504 MW to the DeKalb, Ill., area. Two 345-kV substations, Charter Grove and Gurler, would be constructed to link the customer to the 345-kV Bryon-Wayne line. Charter Grove would cut into Bryon-Wayne, and a 16-mile 345-kV line would connect it to Gurler. A 1.5-mile 345-kV line would connect Gurler to the Keslinger substation, and two 345-kV lines would link it to the customer. The load is expected to come online in 2029 at 12 MW and ramp to 504 MW in 2033.
A $269 million project in ComEd would serve a 1.8-GW customer near Joliet, Ill., by constructing a new 345-kV substation, named Rowell, featuring two 150-MVAR, 345-kV capacitor banks. It would cut into the 345-kV Elwood-Goodings Grove line and link to four customer-owned substations. The customer is expected to come online in June 2029 with 225 MW and ramp to its full consumption in 2033. The project is in the conceptual phase, with an estimated in-service date of July 1, 2028.
A $145 million ComEd project is planned for a 1,296-MW customer near Coal City, Ill., involving the construction of a 345-kV substation, named after the village, with two 150-MVAR, 345-kV capacitor banks. It would cut into the 345-kV Dresden-Pontiac Midpoint and Lasalle-Braidwood lines. The customer is seeking to bring 216 MW online in June 2029 and grow to its full load in 2034. The project is in the conceptual phase with an estimated in-service date of July 1, 2028.
A $99 million project in ComEd would serve a 1-GW customer near Joliet by constructing a new 345-kV substation, named Hiawatha, with one 150-MVAR, 345-kV capacitor bank. It would cut into the 345-kV Kendall County E.C.-Collins line and feed two customer-owned substations with two 0.7-mile radial lines. The customer is seeking to come online with 30 MW in June 2028 and reach its full load in 2032. The project is in the conceptual phase with an estimated in-service date of June 1, 2028.
PPL presented a $220 million project to serve a customer seeking to service 1 GW of load in Archibald, Pa. A new 500/230-kV Archbald Mountain Switchyard would be constructed, cutting into the 230-kV Callender Gap-Paupack and the 500-kV Lackawanna-Hopatcong lines. Archbald Mountain would be connected to Callender Gap with a new 4.6-mile double-circuit 230-kV line and to the customer substation with a 4-mile single-circuit 230-kV line. The customer is expected to come online with an initial load of 166 MW in 2027 and reach 900 MW by 2030, before reaching 1 GW the following year. The project is in the development phase, with a projected in-service date of May 30, 2028.
Dominion Energy presented three projects to serve data centers in Caroline and Spotsylvania counties and Petersburg, Va. They total $106 million and would serve at least 912 MW.



