Calpine announced a special protection scheme that will allow the outage of the Blooming Grove-Bushkill 230-kV line July 1 to accommodate construction of the Susquehanna-Roseland 500-kV line. According to a presentation to the Operating Committee Tuesday, the SPS also takes into account the expected retirement of the Portland coal units, scheduled for June 1.
The SPS calls for the trip of Unit 8 at Calpine’s Bethlehem station to relieve potential congestion from the loss of either of the two Steel City-Quarryville 230-kV lines. The SPS is expected to end in summer 2015 with the completion of the Susquehanna Roseland 500-kV line.
New Line Designations at Breinigsville
PPL announced new line designations coming out of its new Breinigsville substation. PPL plans to reuse the 5044 designation, currently used for the 500-kV Wescovsville-Alburtis line, for the Wescosville-Breinigsville 500-kV line. It would then christen the Breinigsville-Alburtis 500-kV line as 5058.
The new Breinigsville substation is designed to protect against excess voltage drop on 138-kV lines between Wescosville and Seigfried, excess transformer load at the Wescosville substation, and maximum allowable load drop if the Wescosville-Trexlertown #1 and #2 lines are lost.
The project is expected to be completed in May 2015.