Resource Adequacy
Resource adequacy is the ability of electric grid operators to supply enough electricity at the right locations, using current capacity and reserves, to meet demand. It is expressed as the probability of an outage due to insufficient capacity.
Public Service Company of Colorado and the Polis administration want to keep Unit 2 of the coal-fired Comanche Generating Station running a year longer than planned.
The National Association of Regulatory Utility Commissioners passed a resolution urging FERC to resist the Department of Energy’s push to give itself jurisdiction over large loads interconnecting with the grid.
The Organization of MISO States is warning NERC that its possible new resource adequacy standard would tread on states’ planning authority.
SPP state regulators have approved several motions related to FERC Order 1920’s mandate for long-term, scenario-based planning to ensure the system can meet future needs and be fairly compensated.
Duke Energy expects its new five-year capital plan for 2026 to 2030 to be between $95 billion and $105 billion, up from the $87 billion that was planned for 2025 to 2029.
PJM’s winter outlook found the RTO should have enough resources to meet the forecast peak load of 145,700 MW, although the reserve margin continues to decline as new resource development lags.
FERC can make large load flexibility a reality through the implementation of the Department of Energy’s Advance Notice of Proposed Rulemaking on large load interconnections, according to a new Nicholas Institute policy paper.
Both parties have members working on permitting legislation, but the shutdown and the Trump administration's actions against clean energy projects make actual legislation a tough lift for now.
If just 10% of the land-based renewables in PJM’s generator interconnection queue had been developed, the total cost of the RTO’s 2026/27 capacity auction would have been reduced by $3.5 billion, according to an analysis GridLab commissioned by Aurora Energy Research.
The Western Resource Adequacy Program Day-Ahead Market Task Force held its first meeting after the program’s binding decision deadline, with members exploring how the new participant footprint will impact transmission connectivity and other issues.
Want more? Advanced Search










