October 4, 2024

Resource Adequacy

Resource adequacy is the ability of electric grid operators to supply enough electricity at the right locations, using current capacity and reserves, to meet demand. It is expressed as the probability of an outage due to insufficient capacity.
PJM PC/TEAC Briefs: June 2, 2020
PJM weekday load peaks have come in 10.4% less than than projected before the coronavirus pandemic, the Planning Committee learned.
Heat Counteracts COVID-19 Impact on MISO Load
Unseasonably warm weather has nudged MISO load a little closer to normal this week, though demand is still being compressed by pandemic safety measures.
NYISO Management Committee Briefs: May 27, 2020
NYISO has suspended the sequestration of its control room operators as New York begins its recovery from the coronavirus pandemic.
MISO Utilities Urge Swift Action on Gen Mix
Utility executives urged MISO to prepare for the imminent change sweeping the grid with the increased adoption of renewable and distributed resources.
CAISO Predicts Adequate Summer Capacity
California should have enough capacity to get through this summer’s peak demand but dwindling hydropower and limited imports during late-season heat waves could strain supply, CAISO said.
EDF Sees ERCOT Value in Demand-Side Solutions
The Environmental Defense Fund on released a report on ERCOT‘s competitive energy-only market that concludes it can meet future demand growth, increase grid resilience and keep energy costs down through demand-side solutions.
ERCOT’s Summer Reserve Margin up to 12.6%
ERCOT said it still expects record demand this summer and the potential need for emergency measures, despite a drop in load from the COVID-19 pandemic.
MISO Leans Toward Seasonal RA
MISO is contemplating creating a seasonal design for its resource adequacy construct to manage potential reliability risks outside of the summer months.
PJM Analyzes Potential COVID-19 Generation Losses
PJM could support the loss of up to 40% of capacity this summer in a worst-case scenario situation in which COVID-19 spreads among plant workers.
NWPP Details Proposed Reliability Program
The Northwest Power Pool held a webinar on efforts to create a resource adequacy program, discussing FERC oversight and a need to manage the program.