Advanced Energy United has released a scorecard that ranks the seven domestic ISO/RTOs on their generator interconnection processes, finding room for improvement in every one.
ISO-NE’s compliance proposal for Order 2023 failed to meet the voting threshold to receive support from the NEPOOL Transmission Committee.
ISO-NE told the NEPOOL Markets Committee that it is proposing a major redesign to its capacity market, moving from a three-years-ahead schedule to a prompt and seasonal design.
A new coalition launched to push transmission expansion, while a recent paper put some numbers on how expanding the grid can impact different companies' profits - both positively and negatively.
NERC's Board of Trustees will vote on a set of rule changes to allow the registration of inverter-based resources.
The NEPOOL Transmission Committee will vote on ISO-NE compliance proposal and stakeholder amendments on Feb. 15.
ISO-NE has proposed several deviations from the specific approach detailed in Order 2023, including a 270-day cluster study timeline instead of FERC’s 150-day timeline.
Representatives from states working on the Northeast States Collaborative on Interregional Transmission spoke about the young effort, particularly about offshore wind connections.
Advanced Energy United advocated for ISO-NE to exceed Order 2023's required changes in addressing its interconnection's high costs and long delays.
A range of clean energy stakeholders outlined questions and concerns about the potential changes in ISO-NE's FCA 19.