November 21, 2024

supplemental projects

© RTO Insider LLC
PJM PC/TEAC Briefs: Sept. 12-13, 2024
The PJM PC voted to defer action on three proposals to rework the RTO’s process for transferring capacity interconnection rights from a deactivating generator to a new resource.
© RTO Insider LLC
PJM PC/TEAC Briefs: June 4, 2024
PJM stakeholders received updates on the RTO's plan for long-range transmission planning and utilities' supplemental projects to deal with growing data center load.
Xcel Energy
Pro-competition Group Plans to Sue if FERC Reinstates Federal ROFR
FERC has yet to issue a final rule on transmission planning, but supporters of competition for transmission development have said they will appeal it to court if it reimposes a federal right of first refusal. 
PJM
PJM PC/TEAC Briefs: March 5, 2024
The Planning Committee endorsed PJM’s long-term regional transmission planning proposal, advancing manual revisions that would expand the RTO’s planning horizon to 15 years.
ETCC
Big Savings for Tx Competition Claimed as FERC Considers a New ROFR
The Electricity Transmission Competition Coalition released a report arguing that decreasing competition in transmission development would cost consumers hundreds of billions of dollars. 
PSEG
PJM PC/TEAC Briefs: Oct. 31, 2023
PJM stakeholders OK'd a manual change necessitated by the growth of data centers and heard reviews of multiple supplemental transmission projects.
© RTO Insider LLC
PJM PC/TEAC Briefs: July 11, 2023
PJM's Planning Committee discussed the recommended load model to be used in the 2023 Reserve Requirement Study (RSS), while the TEAC gave an update on the ongoing third window of its 2022 RTEP and the opening of the 2023 RTEP later this month.
© RTO Insider LLC
FERC Urged to Close ‘Regulatory Gap’ on Tx Costs
State regulators and others urged FERC to increase oversight of “local” transmission projects while TOs insisted existing cost controls are sufficient.
© RTO Insider LLC
Appellate Judge Presses FERC on End-of-life Transmission Planning
PJM stakeholders asked the D.C. Circuit Court of Appeals to require the RTO to exercise more oversight over transmission owners’ end-of-life projects.
© RTO Insider LLC
PJM PC/TEAC Briefs: Nov. 1, 2022
The PJM Planning Committee continued fine-tuning the five remaining packages for assigning capacity interconnection rights to ELCC resources.

Want more? Advanced Search