Mass. Picks Avangrid Project as Northern Pass Backup
Eversource, Central Maine Power
Massachusetts has selected Central Maine Power's transmission project as the alternative to Northern Pass for the state’s clean energy solicitation.

By Michael Kuser

Avangrid announced Friday that Massachusetts has selected the transmission project of its subsidiary, Central Maine Power, as the alternative for the state’s 9.45-TWh clean energy solicitation if New Hampshire regulators do not approve the Northern Pass transmission line by March 27.

Massachusetts awarded the contract to Eversource Energy and Hydro-Quebec’s Northern Pass on Jan. 25, only to see the New Hampshire Site Evaluation Committee (SEC) unanimously reject the 1,090-MW transmission project a week later. Eversource appealed the decision, saying in a statement Feb. 16: “We have a strong legal argument for a reconsideration by the SEC.” (See New Hampshire Rejects Permit for Northern Pass.)

Avangrid Northern Pass Hydropower
| Eversource, Central Maine Power

CMP and Hydro-Quebec’s New England Clean Energy Connect (NECEC) transmission project would deliver up to 1,200 MW of Canadian hydropower to the New England grid via a 145-mile transmission line. The partners estimate the project to cost $950 million.

News of the selection drew a protesting tweet from Dan Dolan, president of the New England Power Generators Association: “Massachusetts is now all-in on Hydro-Quebec, going from the fatally flawed Northern Pass to a Maine project that still lacks virtually all its key permits. Hydro-Quebec is asking for Massachusetts consumers to guarantee them revenue through an above-market contract for electricity for the next two decades.”

Avangrid Northern Pass Hydropower
Hydro-Québec Major Facilities | Hydro-Québec

Dolan said existing power plant operators in the region have invested more than $13 billion in their plants without any guarantee of cost recovery or profit.

Beginning Negotiations

CMP submitted applications for state and federal permits for NECEC in mid-2017 and said it expects to receive state approvals later this year and final federal permits in early 2019. The company said it will immediately begin negotiation of long-term contracts with the Massachusetts electric distribution companies to prepare for a submission to the state’s Department of Public Utilities in April 2018.

“Our applications for state and federal permits are moving forward with the strong support of communities and stakeholders in Maine,” CMP CEO Doug Herling said in a statement.

Eversource’s statement said that Friday’s decision “strikes a sensible balance by allowing negotiations with Northern Pass to continue, while establishing a back-up protocol that can be initiated if necessary.”

Avangrid Networks CEO Bob Kump said, “A new transmission link between Maine and Quebec would deliver a reliable, firm supply of clean energy to help dampen seasonal price instability when high demand puts pressure on natural gas supplies.”

Massachusetts issued its MA 83D solicitation for hydro and Class I renewables (wind, solar or energy storage) last July. The selection committee for the clean energy request for proposals issued in July 2017 includes representatives from the state’s Department of Energy Resources and from distribution utilities Eversource, National Grid and Avangrid subsidiary Unitil.

Any contract awarded under the request for proposals must be negotiated by March 27 and submitted to the DPU by April 25.

Other proposals for the RFP included Nova Scotia-based Emera’s Atlantic Link project, a 375-mile submarine HVDC transmission line from New Brunswick to Plymouth, Mass., to deliver 5.69 TWh of clean energy per year. National Grid partnered with Citizens Energy on two transmission projects; one of them, the Granite State Power Link, is a 59-mile HVDC line from northern Vermont to New Hampshire to deliver 1,200 MW of new wind power from Canada.

The state-owned Hydro-Quebec also partnered separately with Transmission Developers Inc. for the RFP and, as with Northern Pass, made two proposals, one pure hydro and one with a wind energy component.