PJM Finalizes Rules for Generators Using Dynamic Transfers
Mar 11, 2014
PJM has finalized rules for establishing dynamic transfers, which allow resources in one balancing authority to be operated as if they were in another BA.
PJM has finalized rules for establishing dynamic transfers, which allow resources in one balancing authority to be operated as if they were in another BA. Dynamic transfers can be accomplished through pseudo ties or dynamic schedules.
The business rules, spelled out in a white paper, are a response to PJM’s proposed capacity import limits (ER14-503). External generators with pseudo ties and confirmed firm transmission could win exemptions from the limits if they also accept a must-offer requirement.