By Michael Brooks
WASHINGTON — New wind generators will be required to provide reactive power following a FERC order last week eliminating their exemption from having to provide the service (RM16-1).
Reactive power, essential for controlling the voltage of the grid, can be measured at three points: the generator itself, the generator substation or the point of interconnection. Synchronous generators’ reactive power is measured at the interconnection point.
The commission’s order revises the commission’s pro forma generator interconnection agreements — both small and large — to require nonsynchronous generators’ reactor power to be measured at the high side of generator substations. In its Notice of Proposed Rulemaking in November, FERC had proposed the interconnection point, but it was persuaded by commenters who said doing so would require additional investment in equipment.
FERC issued the wind exemption in Order 661 in 2005 because it was concerned that the cost of the technology needed to provide reactive power would inhibit the development of the resource. Improvements in that technology since then have made it far less expensive, and FERC said that continuing the exemption could result in insufficient reactive power as wind power grows and traditional synchronous generation retires.
Order 661 did not exempt other types of nonsynchronous generation, such solar, but FERC has been treating them similarly to wind on a case-by-case basis. The commission has sometimes required that balancing authorities demonstrate that the lack of reactive power from a non-wind, nonsynchronous generator would threaten reliability before requiring it to provide the service.
The new requirements apply to all new nonsynchronous generators, regardless of type, that have not executed a facilities study agreement as of 90 days after publication in the Federal Register. They would not apply to existing generators, including those making upgrades that require new interconnection requests. FERC said these provisions would allow generators to complete the interconnection process without delay or extra costs.
FERC approved the new requirements at Thursday’s meeting, which was open to the public again after the commission closed it last month. (See Pipeline Protesters Force FERC to Close Monthly Meeting.) Staff’s presentation of the order was interrupted by two protesters, who urged the commission to halt approval of natural gas pipelines.
“There’s a certain irony here because the protesters interrupted a presentation by staff on commission work that can enable a higher degree of penetration by wind resources while maintaining reliability,” Chairman Norman Bay said in response. “This final rule will ensure comparable and nondiscriminatory treatment of both traditional resources and new resources, such as wind and solar, in the provision of reactive power, while recognizing that some technological differences remain.”
“Today’s rule recognizes that wind and other nonsynchronous generators, which are an increasingly important part of the fleet, now have the technical ability to provide reactive power at reasonable cost, and so they’ll now be required to do so,” Commissioner Cheryl LaFleur said. “I think today’s rule highlights that wind and solar are no longer just niche technologies.”