October 3, 2024
Metcalf Reliability-Must-Run Draws Scrutiny
CAISO will gather feedback on its proposal for reliability payments to keep Calpine’s Metcalf gas-fired plant from retiring.

By Jason Fordney

CAISO this week will gather feedback on its proposal for reliability payments to keep Calpine’s Metcalf gas-fired plant from going offline, a decision drawing scrutiny amid a larger conversation about local resource adequacy (RA) planning.

The ISO relies on reliability-must-run (RMR) contracts to keep resources online that are slated for retirement but are still needed for reliability. It has a stakeholder call scheduled for Sept. 26 to gather feedback on its recent proposal to designate Metcalf as an RMR resource.

CAISO FERC Metcalf substation reliability-must-run agreements
CAISO is Considering an RMR Contract for Calpine’s Metcalf Energy Center | Calpine

The contract is slated for a vote by the CAISO Board of Governors in early November, leading some to complain about a quick decision timeline. The board also faced some scrutiny in March when it designated Calpine’s Yuba City and Feather River gas-fired plants as RMR contractual facilities. (See CAISO RMRs Win Board OK, Stakeholders Critical.)

Calpine in June told CAISO that it intends to take the Metcalf plant offline at the end of this year. The company’s request that the ISO study the reliability impact came back in the plant’s favor. “Analysis has indicated that Metcalf Energy Center is in fact required in order to meet the relevant criteria for reliable system operation,” the ISO said in a notice for the call.

At its most recent meeting Sept. 19, the board voted unanimously to extend the current reliability RMR contract for three 55-MW oil-fired units at Dynegy’s Oakland facility. CAISO says it will not renew a contract with AES for the synchronous condensers at its Huntington Beach plant, and those units are expected to shut down.

At the board meeting, Pacific Gas and Electric Director of ISO Relations Eric Eisenman said “these continuing RMR designations show that the market is changing,” pointing to new solar and other resources. He added that “the RA process, especially the local process, needs improvement.”

The RMR contract for Metcalf will put tens of millions of dollars of costs onto ratepayers, he said, asking the board to work with regulators “to improve the local RA paradigm sooner, not later.” He expects more RMR designations for 2019, which will almost certainly raise customer costs.

Noting that CAISO informed stakeholders of the possible RMR designation for Metcalf in early September ahead of the Nov. 1 vote, he said: “We are feeling kind of jammed when it’s tens of millions of dollars.”

Local RA Adjustments Planned

Part of the problem is the way the RA for load-serving entities is measured, CAISO Vice President of Market and Infrastructure Development Keith Casey said at the meeting. RA is currently measured across a broad area, but individual capacity areas within that territory might have inadequate resources.

“We cannot operate being short in a specific area, and I think Metcalf is probably indicative of that deficiency in design,” Casey said. The ISO is working with the California Public Utilities Commission on the problem, and “I am optimistic we will have a proceeding soon to take on some of the deficiencies around the local RA design.” In a Sept. 12 memorandum to the board, Casey said “reliability-must-run contracts remain an important backstop instrument to ensure reliability when other alternatives are not viable.”

RMR contracts are pursued when an LSE does not purchase sufficient capacity to meet local reliability criteria, or when CAISO needs reliability service such as voltage support, black start or dual-fuel capability. RMR can also be used to address local market power or protect availability of a given resource that could retire in the absence of a contract. LSEs are required to provide the RA showing by Sept. 15 of each year and have until Oct. 31 to submit their final year-ahead RA showings. CAISO must notify a potential RMR unit by Oct. 1 of each year whether it will extend an RMR contract.

The number of facilities under RMR contracts has dropped significantly since the implementation of the RA program and the addition of other types of resources. In 2006, CAISO had 9,963 MW under RMR, which dropped steeply to 3,995 MW in 2007. Today, in addition to the Oakland units under RMR, CAISO has about 1,500 MW under black start contracts and about 160 MW under dual-fuel extension status.

CAISO Says Puente Plant Needed

Reliability needs have also led CAISO to conclude that a new gas-fired plant on the California coast cannot affordably be replaced with other alternatives. CAISO on Aug. 16 released its study on the 260-MW Puente Power Project, but NRG Energy has run into heavy opposition to its proposal to build the plant on an existing site in Oxnard to replace its retiring Mandalay and Ormond Beach plants.

CAISO FERC Metcalf substation reliability-must-run agreements
Puente Power Project viewed from beach | California Energy Commission

The California Public Utilities Commission authorized Southern California Edison to enter into a long-term RA contract with NRG for the plant’s capacity, and the California Energy Commission is reviewing the construction and operating permit for the facility. The project was approved because 2,000 MW of generation in the area is due to retire by 2020 because of once-through-cooling regulations.

As part of its review process, the CEC accepted CAISO’s offer to study whether demand response, energy efficiency, renewable generation and combined heat and power could offset the need for the Puente project. CAISO last month issued its findings in the Moorpark Sub-Area Local Capacity Alternative Study, after gathering comments from market participants.

After examining three scenarios, the ISO concluded that Puente would be the cheapest alternative at a cost of $299 million. The most expensive scenario was “incremental distributed resources plus grid-connected battery storage (if the Ellwood Generating Station is retired)” at $1.1 billion, more than triple the cost of Puente.

CAISO FERC Metcalf substation reliability-must-run agreements
CAISO Determined the Puente natural gas plant was the cheapest option to meet local reliability needs. | CAISO

RMR revenue helps keep natural gas a player in the CAISO market as environmental opposition toward fossil fuels is on the uptick. Gas remains the largest component of CAISO’s fuel mix, making up about 54% of its installed capacity of 71,400 MW, followed by renewables at 29%, large hydro at 12% and nuclear at 3%. Oil, coal and “other” comprise about 2%.

However, conventional generation such as natural gas makes up only 9% of CAISO’s interconnection queue of 325 projects totaling 58,000 MW, while 68% are renewable projects and 20% are energy storage devices.

Aside from RMR, CAISO also has a risk-of-retirement program called the Capacity Procurement Mechanism Risk-of-Retirement Enhancements (CPM ROR) initiative, which is generally regarded as a better alternative to RMR. (See CAISO Finalizes Risk-of-Retirement Program Changes.) That package of market rules is also due for a vote from the board at its November meeting.

CAISO/WEIMCaliforniaReliabilityResource Adequacy