October 5, 2024
SPP Seams Steering Committee Briefs: Sept. 6, 2017
SSC Endorses Doomed Interregional Project
SPP stakeholders endorsed a proposed interregional project to be developed in partnership with MISO, despite the project’s dim prospects.

SPP stakeholders last week endorsed a proposed interregional project to be developed in partnership with MISO, despite the project’s dim prospects.

The Seams Steering Committee unanimously agreed with staff’s recommendation to endorse the $5.2 million Split Rock-Lawrence project in South Dakota, identified through the interregional process. It would have been the RTOs’ first-ever interregional project, but staff told the Planning Advisory Committee last month that it no longer recommended moving forward with the initiative. (See SPP Glum as MISO Axes Last Interregional Project.)

SPP MISO interregional project
| MISO & SPP

MISO said its latest analysis of the project indicates the congestion on the 115-kV line is still manageable and that an alternative project could provide the RTO with at least the same benefit at a lower cost.

“It seems odd to endorse a project when we don’t have a partner,” said Jeff Knottek, director of transmission planning and compliance for City Utilities of Springfield, Mo., during the committee’s Sept. 6 conference call.

“We were aware we could come down on different sides on this,” said Adam Bell, SPP’s interregional coordinator. “We didn’t come to a point knowing MISO’s decision until we were done with a majority of the analysis.”

GridLiance’s Bary Warren, who chaired the meeting, said the RTOs’ coordinated study process identified a good project “from the SPP and MISO perspective.”

“MISO stakeholders don’t agree this is the best solution,” Warren said. “From SPP’s perspective, it appears this is a better solution for both RTOs.”

David Kelley, SPP’s director of interregional relations, said the South Dakota project could surface again in a future study. However, SPP’s Tariff prevents the RTO from approving an alternative interregional project other than the one that advanced from the interregional study out of a regional review.

“We’re recommending to you what we feel we’re obligated to do under the process,” he said.

Staff Prepping Response to AECI Project’s Protests

SPP staff is preparing comments due to FERC on Sept. 12 in response to protests lodged by Xcel Energy Services and Westar Energy over a proposed interregional project with Missouri-based Associated Electric Cooperative Inc. (See “Board Reaffirms Seams Project with AECI,” SPP Board of Directors/Members Committee Briefs: July 25, 2017.)

Last month, the RTO filed with FERC the terms and conditions of a cost-sharing and usage agreement among SPP, AECI and Springfield, as well as Tariff changes that would regionally allocate costs to the RTO’s transmission customers (ER17-2257).

The $13.75 million project involves installing a new 345/161-kV transformer at AECI’s Morgan substation and an uprate of a related 161-kV line, both near Springfield.

Westar asserts a lack of transparency regarding SPP and AECI’s cost-sharing methodology and their negotiations.

Xcel protested the proposed allocation of the Morgan transformer’s costs, noting the project is outside SPP’s footprint and being allocated to members on a regional load-ratio share basis. It also says SPP’s filings do not justify “a departure from the cost allocation methodologies” currently stipulated by the RTO’s Tariff.

SPP Sends MISO $1.2M for M2M Settlements

SPP sent MISO $1.2 million in market-to-market (M2M) payments for June congestion on flowgates along the seam between the two RTOs. The payments reduced the net amount of settlements SPP has collected from MISO to $20.5 million — as of June — since the two began the process in March 2015.

SPP MISO seams interregional project
| SPP

Temporary flowgates accounted for most of the congestion, binding for 214 hours, 32% less than the month before, and resulting in almost $1.2 million in M2M settlement charges to SPP. Permanent flowgates were binding for 27 hours, giving MISO an additional $59,339.

More than half of the M2M settlements came over a MISO flowgate in northwest Iowa near the Nebraska and South Dakota borders. SPP was unable to commit enough generation during low-wind periods to compensate for outages in the area, resulting in 23 hours binding and $676,332 in charges.

— Tom Kleckner

Other SPP CommitteesSPP/WEISTransmission OperationsTransmission Planning

Leave a Reply

Your email address will not be published. Required fields are marked *