Montana Wind Farm Exempted from Frequency Response Rule
FERC ruled that an existing Montana wind farm is exempt from a commission order requiring new generators to provide primary frequency response.

By Amanda Durish Cook

FERC ruled last week that an existing Montana wind farm awaiting a new interconnection is exempt from a recent commission order requiring all new generators to be capable of providing primary frequency response.

The commission’s Nov. 15 ruling said Order 842 does not apply to NaturEner’s Glacier Wind Farm II, which has been in the queue for Enbridge’s Montana-Alberta Tie-Line (MATL) since 2013 and currently the only resource to request to join the 214-mile, 230-kV AC line extending from Lethbridge, Alberta, to Great Falls, Mont. (ER18-1788). The wind farm began operating in SPP in 2009.

Order 842 requires all new generators to be capable of providing primary frequency response as a condition of interconnection. The rule has been in effect since May.

Glacier Wind Farm II
MATL | Enbridge

Enbridge’s U.S. operating subsidiary for the line, MATL LLP, asked the commission to clarify that Order 842 does not apply to the pending interconnection request, saying the wind farm applied for interconnection and was studied before the rule was issued. The company said requiring frequency response service would “cause significant equipment installations and system restudies that would cause unduly burdensome delays and expenditures.” MATL estimated that restudies would cost anywhere from $15,000 to $20,000 and take three to six months.

FERC assured the company that the rule does not apply to the existing generator. The commission pointed out that MATL’s pending request involves a generator that has already been in operation under another interconnection agreement for about nine years and has been lined up for interconnection for five years, well before the issuance of the final rule. FERC also said the wind farm has not taken “any action that requires the submission of a new interconnection request.”

MATL noted that its has nearly completed the associated interconnection studies with NaturEner and expects to proceed with the negotiation of an interconnection agreement in the near future.

Ancillary ServicesGenerationSPP/WEIS

Leave a Reply

Your email address will not be published. Required fields are marked *