PJM Transmission Expansion Advisory Committee (TEAC)

PJM
PJM PC/TEAC Briefs: Oct. 3, 2023
The Planning Committee endorsed the recommended values in the 2023 Reserve Requirement Study, which would increase the amount of reserves that PJM aims to procure for the 2027/28 delivery year.
© RTO Insider LLC
PJM PC/TEAC Briefs: Sept. 5, 2023
PJM brought a quick fix solution before the Planning Committee, seeking to address the frequency and magnitude of load forecast adjustments being requested by electric distribution companies.
PJM
PJM PC/TEAC Briefs: Aug. 8, 2023
PJM stakeholders approved a load model for the 2023 reserve requirement study during the Planning Committee's Aug. 8 meeting.
© RTO Insider LLC
PJM PC/TEAC Briefs: July 11, 2023
PJM's Planning Committee discussed the recommended load model to be used in the 2023 Reserve Requirement Study (RSS), while the TEAC gave an update on the ongoing third window of its 2022 RTEP and the opening of the 2023 RTEP later this month.
Dominion Energy
PJM PC/TEAC Briefs: June 6, 2023
The PJM Planning Committee approved documents to explore possible improvements to transferring capacity interconnection rights.
© RTO Insider LLC
PJM PC/TEAC Briefs: May. 9, 2023
PJM plans to allocate more than 2,000 MW of transmission headroom to generators that requested additional capacity rights under a transitional process.
© RTO Insider LLC
PJM PC/TEAC Briefs: April 11, 2023
State advocates would like to see more details when supplemental transmission projects are proposed to the Transmission Expansion Advisory Committee.
© RTO Insider LLC
PJM PC/TEAC Briefs: Feb. 7, 2023
An error in the power flow case for several generators caused minor impacts to the 2022 annual cost allocations and zonal charges for the units, PJM said.
PJM
Policymakers Working to Meet Spiking Demand of Data Centers in Virginia
Demand growth in Northern Virginia's power-hungry Data Center Alley is accelerating, and policymakers are trying to ensure new demand can be met reliably.
PJM
PJM PC/TEAC Briefs: Jan. 10, 2023
PJM stakeholders approved new generator deliverability tests and learned of a 3rd competitive window to address "unprecedented" data center load in Virginia.

Want more? Advanced Search