PJM Requests 2nd Talen Generator Delay Retirement
A PJM graphic shows the region where voltage concerns were found in the analysis of the deactivation of the H.A. Wagner Generating Station.
A PJM graphic shows the region where voltage concerns were found in the analysis of the deactivation of the H.A. Wagner Generating Station. | PJM
|
PJM has requested that Talen Energy continue operating a portion of its H.A. Wagner Generating Station an additional three years beyond its requested 2025 deactivation date.

PJM has asked Talen Energy to enter into a reliability-must-run (RMR) contract to continue operating its oil-fired H.A. Wagner generator, located outside Baltimore, three years beyond its requested retirement date in 2025. 

In its Oct. 16 deactivation request, Talen asked to take the generator offline on June 1, 2025, citing air quality restrictions that limit its run time and the economics of PJM’s capacity market as prompting the retirement. Wagner is configured with three oil units and one gas-fired combustion turbine; PJM’s request would retain the oil-fired Units 3 and 4, which output 305 and 397 MW, respectively. 

“The Wagner facilities’ [Clean Air Act] Title V air permit limits operation to capacity factors under 15% when operating on oil. … The combination of low margin energy market economics, low capacity prices and significant Capacity Performance penalty risk due to run hour limitations results in the economics being outweighed by the risk associated with continued operation,” Talen said. 

During the Oct. 9 Transmission Expansion Advisory Committee meeting, PJM’s Perry Ng said the RTO’s reliability analysis found that taking the 844-MW generator offline in 2025 would cause voltage and thermal violations throughout the Baltimore Gas and Electric region. The projected issues were identified when the Wagner retirement was combined with the deactivation of Talen’s 1,283-MW Brandon Shores generator, which the company also requested to go offline in 2025 and is adjacent to Wagner. 

By delaying the retirement by three years, Ng said planned transmission upgrades could be completed and resolve the violations without any new Regional Transmission Expansion Plan projects. In particular, he said a component of the $5 billion package of transmission projects that the Board of Managers approved in December would resolve the violations. That component, the construction of the 65-mile, 500-kV North Delta-High Ridge line and upgrades to both substations, is projected to be in service between 2026 and 2028. (See PJM Board Approves $5 Billion Transmission Expansion.) 

PJM has also asked Talen to continue operating Brandon Shores on an RMR contract through 2028, though Senior Manager of Transmission Planning Sami Abdulsalam said the discussions on the contract are still in progress. (See “Brandon Shores Deactivation to Require $786M in Grid Upgrades,” PJM PC/TEAC Briefs: June 6, 2023.) 

Since the start of December, Ng said an additional four generators have requested full or partial deactivation: 

    • Constellation Energy has requested deactivation of Eddystone Units 3 and 4, totaling 760 MW, on May 31, 2025. The generator is a dual-fuel resource located outside Philadelphia. 
    • Archaea Energy requested deactivation of its 11-MW, methane-powered Virginia Beach LF generator on April 1. 
    • GenOn Energy Management requested (here and here) deactivation of four CTs, amounting to 216 MW, at its Morgantown Generating Station near Newburg, Md., on June 1. 
    • Heritage Power requested deactivation of its four dual-fuel CTs at the Sayreville Energy Center, amounting to 217 MW. The company cites a New Jersey Department of Environmental Protection rule limiting emissions effective June 1, which is the date the company requests that the generator goes offline. The notice suggests the possibility the company may make modifications to the site to allow it to resume operations in compliance with the regulations or that it may permanently retire.
Environmental RegulationsFERC & FederalNatural GasNew JerseyPJM Transmission Expansion Advisory Committee (TEAC)ReliabilityResource Adequacy

Leave a Reply

Your email address will not be published. Required fields are marked *