FERC OKs Most of ISO-NE 2nd Storage Compliance

FERC on Tuesday accepted most provisions in ISO-NE’s second compliance filing for Order 841, which requires RTO market participation rules to recognize the unique physical and operational characteristics of storage resources.

The changes become effective Dec. 3, 2019, with a limited number of revisions becoming effective Jan. 1, 2026, subject to further compliance filings (ER19-470-004).

The commission in December found ISO-NE had failed to comply with requirements to account for maximum run time, maximum charge time, state of charge, maximum state of charge and minimum state of charge (collectively, state of charge and duration characteristics) of electric storage resources in the day-ahead market. It required the RTO to modify its participation model through bidding parameters or other means.

FERC in April denied a rehearing request on the same issue. (See ISO-NE Order 841 Rehearing Request Denied.) In Tuesday’s order, the commission accepted most of ISO-NE’s revisions around the issue but found the RTO still didn’t go far enough.

ISO-NE Storage Compliance
Green Mountain Power’s Stafford Hill Solar Farm in Rutland, Vt was the first in the region to use battery storage to reduce peak demand. | UVM

“We find that, while ISO-NE’s proposed revisions state that it will account for such characteristics in the day-ahead market through bidding parameters or other means, ISO-NE has failed to propose any bidding parameters or other means through which it will do so,” the commission said.

“If ISO-NE intends to rely on new bidding parameters, it must define those bidding parameters in its Tariff and explain in its transmittal how those bidding parameters will be incorporated into its day-ahead market engine,” the commission said, directing the RTO to file such revisions within one year.

The commission also rejected ISO-NE’s response to direction that it file Tariff revisions that apply transmission charges to an electric storage resource when that resource is charging for later resale in wholesale markets and is not providing a service, and to include a basic description of ISO-NE’s metering methodology and accounting practices for ESRs.

“We disagree with ISO-NE’s statement that electric storage resources will always be providing a service when charging for later resale in the wholesale markets,” the commission said. “Specifically, we find that ISO-NE has failed to demonstrate that an electric storage resource that is self-scheduled to charge at a fixed MW quantity is providing a service that warrants exempting its full self-scheduled charging MW from transmission charges.”

The commission directed ISO-NE to file within 90 days Tariff revisions specifying that it will not apply transmission charges to ESRs when they are dispatched to withdraw energy to provide voltage support and reactive control, provide operating reserves, provide regulation, balance energy supply and demand on an economic basis or address a reliability concern, but it will apply transmission charges to ESRs when they are not being dispatched to provide one of those tariff-defined services.

The commission also directed the RTO to modify Tariff language that “could effectively allow the host utility to decide whether an electric storage resource may participate in the ISO-NE markets by stating that an electric storage resource cannot qualify to participate if the host utility is unwilling or unable to support the necessary registration, metering and accounting of the electric storage resource. This language may create a barrier to the wholesale participation of electric storage resources and may therefore be inconsistent with Order Nos. 841 and 841-A.”

Senators Press DOE, PJM on Cybersecurity Testing

Expressing concern over the bulk power system’s preparedness for a cyberattack, members of the Senate Energy and Natural Resources Committee on Wednesday pressed representatives from industry and the federal government to strengthen their cooperation.

King Focuses on Testing Gap

Cybersecurity Testing
Senator Angus King (I-ME) | U.S. Senate

Testing utilities’ cybersecurity preparations was a major theme of the hearing, with Sen. Angus King (I-Maine) asking witnesses what work their organizations had done to verify the readiness of utilities’ systems.

“I was very disturbed a year or two ago when we had a hearing on this subject, and I asked the fellow from NERC, ‘Do you red-team, do you [penetration] test,’ and the answer was, ‘I don’t think so,’ or something to that effect,” King said, referring to testing practices where organizations hire professional hackers to try to break into their systems.

While Thomas O’Brien, senior vice president and CIO of PJM, assured King that the RTO frequently conducts penetration testing and red-team exercises, the senator was not so happy with the response of Alexander Gates, who earlier this year was picked to head the Department of Energy’s Office of Cybersecurity, Energy Security and Emergency Response (CESER). (See DOE Names Gates to Head CESER.) Gates said that while DOE conducts red-team exercises on federal property, the office serves a consulting role with regard to private sector organizations.

“Wasn’t CESER designed to protect the grid?” King asked.

Thomas O’Brien, PJM | U.S. Senate

“It’s designed to protect the grid, yes sir, but —”

“Isn’t [part of] protecting the grid determining whether it’s safe?” King broke in.

“We could do more, perhaps we should do more,” Gates admitted. “I don’t know if it gets to the level of pen-testing or red-teaming … but again, right now … with the responsibilities and authorities that we have, and the partnerships, it’s an advisory service that we’re providing at this point.”

King asked Gates to inform the committee if additional authorities would help DOE and CESER to strengthen their testing capability, reiterating that he “[didn’t] see how you can carry out a mission of protecting the grid without testing the grid’s vulnerability.”

Manchin Probes Communication Resiliency

Cybersecurity Testing
Senator Joe Manchin (D-WV) | U.S. Senate

Sen. Joe Manchin (D-W.Va.) also grilled Gates and O’Brien on testing. The ranking member’s questions focused on utilities’ ability to maintain communications during cyber incidents.

Manchin first asked O’Brien whether PJM had any procedures in place for testing whether members have robust mechanisms for keeping essential data flowing to the RTO. Told by O’Brien that “we don’t feel [that] is in our jurisdiction,” Manchin asked Gates if DOE had made any effort to check on communications resiliency.

“If they’re actually not really hardening the systems to protect against the cyberattacks, how are you able to detect that?” Manchin asked. “Do you wait until something happens, or are you all checking to see if they’re doing it?”

“We’re not — there is a reporting mechanism in place —” Gates began.

Cybersecurity Testing
Alexander Gates, Department of Energy | U.S. Senate

“No one’s checking, I can tell right now, no one’s testing to make sure,” Manchin interrupted. “If I wanted to find out if you did what you told me you did, I’d have one of my smart people try to hack in … and see if I showed a fallacy there. So we’re not doing those types of testing.”

Gates observed that the Department of Homeland Security’s Cybersecurity and Infrastructure Security Agency (CISA), along with FERC and NERC, do have “mechanisms to engage” with private utilities, but DOE is limited in its ability to oversee implementation of security guidelines. O’Brien concurred, telling Manchin that “we rely on … NERC compliance” and audits to ensure members are dealing with their vulnerabilities properly.

“Well, we’ll have to check with NERC, then, or check with somebody to see if somebody’s checking anything,” Manchin replied.

No one from NERC participated in the hearing.

Murkowski Urges Aid for Small Utilities

Cybersecurity Testing
Senator Lisa Murkowski (R-AK) | U.S. Senate

Chair Lisa Murkowski (R-Alaska) reminded participants of the role that municipal utilities and rural electric cooperatives play in large parts of the U.S. grid. She asked Gates for an update on CESER’s efforts to help strengthen these smaller entities’ cybersecurity preparedness through grants and information sharing.

Gates did not provide any specific funding figures in response but reassured the committee that CESER is “working very hard” to ensure that small utilities and co-ops have the resources they need.

“The small utilities are … in some respects, the soft underbelly of the grid, and we take great pride in certain research and development programs … that we think are going to be valuable in providing those entities the same level of protection as some of the larger utilities,” Gates said.

Evergy Releases Standalone Plan Details

Evergy confirmed Wednesday that it will remain independent and released details of the standalone plan that helped guide its decision.

CEO Terry Bassham told financial analysts during the company quarterly earnings call that Evergy’s Sustainability Transformation Plan “sets the stage for significant value creation and a strong future for Evergy and our stakeholders.”

The plan follows a “comprehensive, independent review” that began earlier this year and calls for $8.9 billion of capital investments in facility upgrades, grid modernization technologies and clean energy initiatives through 2024 in the company’s Kansas and Missouri service territory.

“Our plan creates a compelling value proposition for shareholders,” Bassham said. “Throughout the review, we were focused on three core objectives: maximizing long-term value for our shareholders, serving the best interests of all Evergy stakeholders, including our customers, employees and communities, and continuing to advance our work to successfully create a forward-thinking sustainable energy company.”

Evergy
Evergy CEO Terry Bassham | Evergy

The Kansas City-based company had explored possible purchases by a number of other companies. It called off the effort to remain a standalone company. (See Report: Evergy Calls Off Sale, Stock Slides.)

Bassham said Evergy considered a potential strategic combination and a “modified, improved” standalone operating plan and strategy. The board of directors and its strategic review committee each retained independent financial advisors and consultants to assist in the review.

Asked by an analyst whether Evergy received any purchase offers, Bassham only said the company did “engage with a number of third parties” during a “robust and comprehensive process.”

“Without getting into a lot of the detail, in the end, the committee and the board both agreed that, based on that work and that review, our standalone plan produced a better long-term shareholder return profile and that was absolutely the best way to move forward,” he said.

Evergy has become the nation’s second-largest generator of wind energy as a percentage of total generation since 2005. The company has added or contracted for more than 4.6 GW of renewables and retired more than 2.4 GW of fossil generation. It said it can reduce CO2 emissions by 85% before 2030, compared with 2005 levels.

The company will benefit from recent Kansas legislation that eliminates the state income tax for public electric utilities, effective Jan. 1. Bassham called the legislation “very positive” for Evergy’s customers and communities.

Evergy reported second-quarter earnings of $133 million ($0.59/share), compared with $140 million ($0.57/share) a year ago. The company’s operating earnings of $0.68/share just missed the Zacks consensus estimate of $0.70/share.

Evergy’s stock price lost 3.38% Wednesday, falling $1.87 before closing at $53.53.

NEPOOL Reviews `Future Grid’ Study Requests

NEPOOL members are trying to cull and combine nine proposals for the Transition to the Future Grid study that ISO-NE has offered to perform.

The New England States Committee on Electricity suggested ISO-NE build on the Pathway Scenario developed by the Northeastern States for Coordinated Air Use Management for achieving economy-wide carbon reductions. | NESCOE

ISO-NE CEO Gordon van Welie announced the initiative in March, saying it will give stakeholders information needed to plan transmission and market designs to achieve decarbonization goals. (See ISO-NE Study to Chart Transition to Future Grid.)

Representatives of each stakeholder group gave brief descriptions of their proposals and answered questions during a joint meeting of the NEPOOL Markets and Reliability committees Aug. 4.

In addition, Ben D’Antonio, counsel for the New England States Committee on Electricity, described NESCOE’s suggestion that ISO-NE build on the Pathway Scenario developed by the Northeastern States for Coordinated Air Use Management (NESCAUM) for achieving economy-wide carbon reductions. It assumes that at least 1,000 MW of clean energy resources will be added annually for the next several decades. NESCOE said the Pathway Scenario could be included in energy market modeling to generate hourly dispatch patterns, examine system operating characteristics and requirements and analyze transmission.

Day Pitney attorney Eric Runge presented a summary of the nine other proposals:

  • Eversource Energy asked for loss-of-load expectations (LOLE) and other reliability metrics, market prices, total cost to load, a description of how the supply mix could develop under current market rules and a qualitative assessment of how likely it is for such a supply mix to develop. It suggested three scenarios for meeting 80% economy-wide emission reductions by 2050: a mixed portfolio, a high offshore wind portfolio and a high solar portfolio. Eversource also made a second request to identify total installed nameplate capacity of a future system where LOLE meets the NPCC standard of one day in 10 years with no renewables built with out-of-market contracts clearing as new in the primary or substitution auctions.
  • National Grid asked how bi-directional controllable transmission with Quebec and other neighbors would impact emissions, LMPs and the use and spillage of intermittent resources. It also wants to identify transmission upgrades needed for a fully decarbonized economy and determine whether markets under high renewable/storage penetration cases would provide sufficient revenues to cover resources’ capital and operations and maintenance (O&M) costs.
  • Energy Market Advisors said the RTO should look at the cost, operational and resource adequacy implications of the two options available to new resources addressing state policy objectives: those using capacity network resource interconnection service (CNRIS) and participating in the capacity, energy and ancillary service markets and those using network resource interconnection service (NRIS) and participating in only the energy and ancillary service markets. If policy resources cannot get a capacity service obligation through the forward capacity auction due to the minimum offer price rule or the Competitive Auctions with Sponsored Policy Resources (CASPR) test price, or if the cost of a CNRIS is too high, EMA said that “NRIS may well become the preferred outcome.”
  • FirstLight Power said that to avoid understating potential reliability problems, the base scenarios should not assume significant new electric storage entry. It would add new electric storage based on as-modelled market prices, considering round-trip efficiency and variable O&M costs.
  • NextEra Energy and Dominion Energy made a joint request to determine how the loss of the NextEra’s Seabrook and Dominion’s Millstone nuclear power plants would impact market prices, system operations and state RPS targets and decarbonization goals.
  • American Petroleum Institute asked for a study on how the future grid will balance policy goals with other reliability, affordability and energy access objectives. API cited previous studies and reports by ISO-NE that it said demonstrate “that natural gas infrastructure can further economic and reliability objectives in the region.”
  • Multi-sector Group A (Acadia Center, Advanced Energy Economy, Brookfield Renewables, Conservation Law Foundation, Energy New England, Natural Resource Defense Council and PowerOptions) asked for an update and extension of the Planning Advisory Committee’s 2016 economic study on regulation, ramping and reserves to assess the impact of ramping, regulation and load-following resources as the system decarbonizes.
  • Multi-sector Group B (Advanced Energy Economy, Borrego Solar, Conservation Law Foundation, Energy New England, ENGIE, Natural Resources Defense Council and PowerOptions) seeks a long-term transmission system assessment to identify new transmission investments that could eliminate obstacles to reaching net zero-carbon and that are more economical than upgrades for near-term transmission needs. They also would like an analysis of whether distribution system generation, mobile and stationary storage, increased energy efficiency or flexible demand could reduce the need for new transmission.
  • Anbaric Development Partners called for identifying an onshore and offshore power system that is carbon-free by 2035, as proposed last month by Democratic Presidential candidate Joe Biden. (See Biden Offers $2 Trillion Climate Plan.)

The proposals called for study time frames of at least 10 years (EMA) to as long as 2050 (Multi-sector Groups A and B and Eversource).

Day Pitney will attempt to identify commonalities among the nine proposals before the committees’ next joint meeting on Sept. 1.

It’s not definite at this point that we’ll be the ones conducting the study,” ISO-NE spokesman Matt Kakley said via email. “We’ve offered to do it if stakeholders want us to [and] we’re able, but it hasn’t yet been decided if that’s the direction stakeholders want to go. It’s still possible that a consultant could be hired for the work. 

E3/EFI Study

The committees also heard a presentation on a study on deep decarbonization by Energy+Environmental Economics (E3) and Energy Futures Initiative (EFI) that was funded by Calpine.

The study projects that electricity demand could nearly double over the next three decades with large additions of renewable generation, particularly solar and offshore wind.

The study included a “High Electrification” case in which 80% of building energy consumption is electricity, with about 230 TWh of annual load in 2050, a 97% increase. It also included a “High Fuels” scenario in which advanced biofuels and hydrogen result in somewhat lower electrification rates and greater reliance on low-carbon fuels, with about 60% of building energy consumption from electricity. It would have a load of 192 TWh by 2050, a 66% increase.

NEPOOL Future Grid Study
Energy+Environmental Economics (E3) and Energy Futures Initiative (EFI) conducted a study that looked at two scenarios for electrification and decarbonization that project electric load will increase by at least 66%. | E3/EFI

The New England electricity system becomes winter-peaking in the 2030s, and the median gross load peak (net of energy efficiency) is expected to increase from 25 GW in 2019 to 42-51 GW by 2050.

The study identifies land and transmission availability as likely constraining factors for new generation development. Its base case estimates that a land area equal to 4% of the region’s farmland will be needed for solar generation and 2% of farm and forest land needed for wind.

E3 and EFI said that New England will require 30-37 GW of thermal capacity through 2050 under all scenarios studied but that its usage will drop over time, with the capacity factors for gas-fired generation dropping to 10% to 15% by 2050. They expect some form of low-carbon fuel will be available to reduce the carbon intensity.

NEPOOL Future Grid Study
The E3/EFI study projected prices increasing by 38% by 2050, mostly due to new generation and transmission. | E3/EFI

The study found that cases with the most available solutions have lower costs and lower technology risks. Increasing the availability of land-based wind and solar also reduces costs.

“Firm, low-carbon technologies such as advanced nuclear, [carbon capture and sequestration] or hydrogen could play a significant role,” E3 and EFI said.

Average electric rates will increase at a compound annual growth rate of 1.3% to 1.5% by 2050 to fund infrastructure additions, including new generation, transmission upgrades and spur line costs, and a slight increase in variable costs. Average prices are forecast to rise from $0.17/kWh in 2025 to $0.23/kWh in 2050 under the high electrification case, an increase of 38%.

NEPOOL Future Grid Study
Mid-century economy-wide GHG emission reduction targets in New England | E3/EFI

Removing all combustion turbines (CTs) and combined cycle plants (CCGTs) increases the cost of achieving a zero-emissions grid by about $19 billion annually relative to a zero-emissions portfolio with zero-carbon fuels (hydrogen or biogas).

In most weeks, wind and solar generation minimizes the need for CTs, CCGTs or steam turbine generation. But when renewable production is low, up to 32 GW of thermal generation could be dispatched for reliability. Building a system with no gas or hydrogen would cause a “significant overbuild” of renewables and storage, resulting in many curtailments during typical weeks, the authors said.

Without upgrades to the region’s 345-kV network, the study found enough “headroom” for a combined 800 MW of renewable generation in New Hampshire and Vermont, and 4 GW each for Connecticut, Massachusetts and Rhode Island. There is no headroom for Maine, which has the best onshore wind potential in the region. Offshore wind headroom is estimated at 8 GW.

Utility-scale solar could increase to 50% of the projected 2050 peak load without upgrades. Reaching 100% would require 115-kV line upgrades.

Brattle Offshore Wind Study

It concluded that the current approach — with OSW developers competing primarily on cost to develop offshore generation and project-specific generator lead lines — would be more expensive than developing transmission independently from generation. “A planned approach is likely to result in lower costs in both the near- and longer-term, by lowering risks and costs of onshore upgrades and increasing competition for both offshore transmission and generation,” the study found.

The study also concluded that a planned approach would make better use of limited onshore points of interconnection, reduce seabed disturbances, increase competition for transmission and generation and reduce transmission upgrade costs.

NEPOOL Future Grid Study
Current generator lead line approach (left) vs. planned offshore-grid approach (right) | The Brattle Group

The study found that the region will need to add more than 1,500 MW of OSW annually to reach the “80% by 2050” decarbonization goals.

NEPOOL Future Grid Study
Comparison of total onshore plus offshore transmission costs in Phase 1 analysis (3,600 MW additional OSW) | The Brattle Group

Phase 1 of the study focused on 3,600 MW of OSW (including authorized procurements of 1,600 MW in Massachusetts and 1,200 in Connecticut). Phase 2 included an additional 4,800 MW, for a total of about 8,400 MW.

It cited as examples of proactive transmission planning Texas’ Competitive Renewable Energy Zones, California’s Tehachapi wind, MISO’s Multi-Value Projects and several European countries.

Brattle said the existing approach for connecting 2,800 MW of OSW already contracted to Cape Cod will require $131 million to $787 million in onshore transmission upgrades. Continuing the current approach in the next 3,600 MW of procurements could cost up to an additional $1.7 billion in onshore upgrades it said.

The planned approach would increase offshore transmission equipment costs by $600 million ($3.3 billion vs $2.7 billion) but reduce costs of onshore upgrades from $1.7 billion to $550 million, a savings of more than $1.1 billion or 10% for Phase 1.

Among other findings, Brattle said the planned approach would result in:

  • A 40% reduction in line losses.
  • Increased competition: It cited studies of offshore transmission costs in the U.K. showing that competition among independent offshore transmission owners reduced costs 20-30% compared with generator-owned transmission.
  • Fewer system overloads: The study said a scenario using the current planning, with 8.1 GW of generation and five points of interconnection, would have many more system overloads — particularly in Connecticut and the Mystic-North Cambridge-Woburn section of Massachusetts — than a planned system that carried 8.6 GW over nine points of interconnection.
  • Lower OSW curtailment: 14% vs. 34% in 2028.
  • Increased production cost savings: $619 million in 2028 vs. $564 million for the current process, a difference of $55 million or almost 10%.
  • Lower LMPs: Some locations in Rhode Island and Southeastern Massachusetts would face significantly higher LMPs by 2028 under the current approach because of transmission congestion.
  • An almost 50% reduction in marine trenching: 831 miles vs. 1,620 miles for Phases 1 and 2.
  • Preservation of the option for networked transmission to improve reliability and reduce curtailments from transmission outages: If three 1,200-MW HVDC converter stations were networked offshore, an outage of one line would still allow full power flow in all hours when total generation is less than 2,400 MW, resulting in only 4% of energy curtailed relative to no outages. “Under the current (non-meshed) gen-tie approach, an outage in any one of three lines would [result in a] 33% reduction in delivered energy to the onshore system, causing significantly more curtailments than under a meshed configuration,” Brattle said.

NERC Reliability Issues Steering Committee Briefs: Aug. 6, 2020

NERC’s Reliability Issues Steering Committee (RISC) is planning to bring forward the release of its next ERO Reliability Risk Priorities Report — traditionally published in November of odd-numbered years — to August 2021. The biennial Reliability Leadership Summit will be held earlier next year as well — in January – rather than its usual time in March.

Presenting the expected publication schedule to RISC members via conference call on Thursday, Thomas Coleman, director of risk issue management at NERC, said an August release seemed more “timely” than the traditional November publication date. Work on the report is expected to begin in the fourth quarter of 2020 with the production of the risk template and the release of the industry survey to “prioritize identified risks as well as to potentially identify new and emerging risks.”

Results of the survey will form the basis of discussions among industry leaders at the Reliability Leadership Summit. The last summit, held in March 2019, involved more than 130 regulators, utility officials, RTO executives and other stakeholders. (See NERC Chief: No ‘Appetite’ for Expanding Authority.) The format of next year’s summit has not been finalized, but Coleman said that “more than likely” the meeting will be held online.

“I think we can really have a very interactive and productive [summit] virtually,” he said. “We’ve all been on so many different variations of virtual calls, [and] we’ve seen some really innovative and creative approaches, so I feel strongly that we can develop a really meaningful and impactful virtual meeting in the beginning of 2021.”

Risk Framework Goes to RSTC Next Month

Reliability Issues Steering Committee
RSTC/RISC coordination within the risk mitigation framework. | NERC

NERC Chief Engineer Mark Lauby updated the committee on NERC’s planned risk mitigation framework, which is currently under development with input from the Reliability and Security Technical Committee (RSTC). The committees hope to finish the framework in time to present it to NERC’s Board of Directors at its November meeting.

Development of the framework began last year in hopes of creating a unified, transparent process to help entities choose the best approach to manage various situations. (See NERC Developing Risk Mitigation Framework.) A preliminary framework was created by the ERO Enterprise with input from the North American Transmission Forum and handed off to RISC for further refinement after the February board meeting.

The latest updates to the framework focus on the relationship between the RSTC and RISC in the risk mitigation process, including a flow diagram that breaks down each committee’s responsibilities at each stage. RISC plans to pass the document to RSTC by Aug. 19 for inclusion in the agenda for its meeting next month. Once RSTC members have provided their input, the committees will finalize the document so that RISC Chair Nelson Peeler and RSTC Chair Greg Ford can present it to the board together.

“What we’d like to do, depending on the views of everyone, is ultimately take this to the board as a joint [proposal], so that it kind of puts a little bit more cement around how we identify and prioritize risks and work on risks in a more formal way,” Lauby said.

RISC Charter Updates Accepted

RISC members also voted to approve proposed changes to the committee’s charter and submit them for acceptance by NERC’s board at its November meeting.

The approved edits are largely cosmetic, aimed at replacing outdated language and aligning the charter with those of other NERC committees. However, Jennifer Sterling of Exelon said she was concerned that the committee would have just one representative from the RSTC, as opposed to one each from the Operating, Planning and Critical Infrastructure Protection Committees that the RSTC replaced earlier this year. (See RSTC Tackles Organization Issues in First Meeting.)

Sterling asked if RISC would be able to achieve the same level of coordination with RSTC as its predecessors with fewer shared members. In response, Peeler said that RISC leadership felt one RSTC representative would be enough to maintain communication, especially since the two committees plan to create more formal bonds going forward.

“The purpose of those committee members being on RISC was for them to maintain alignment and bring issues from their committees, not necessarily to be the technical expert of the committee,” Peeler said. “[But] we’re going to have more coordination between RSTC and RISC formalized … in the framework.”

WECC Seeks Western Bent on Strategy Plan

WECC is soliciting stakeholder comments on a draft strategic plan that seeks to build on NERC’s ERO Enterprise Long-Term Strategy while adding a Western flavor.

WECC strategy plan
| WECC

“WECC took a hard look at the ERO Long-Term Strategy (LTS) and, with input from the board, made some really intentional decisions about what concepts made sense for incorporation and further expansion … to reflect WECC’s unique profile and perspective,” Jordan White, WECC vice president of strategic engagement, told the organization’s Member Advisory Committee Wednesday.

NERC’s Board of Trustees approved a revised ERO Enterprise LTS in December. That plan calls on the regional entities to incorporate four “value drivers” into their practices, including using innovative, risk-based programs; seeking top talent; and balancing industry collaboration with independence and objectivity. (See NERC Plans Review of Supply Chain Standards.)

The NERC LTS also identified five key focus areas for REs in coming years, including expanding its risk-based focus in all areas; taking steps to mitigate emerging reliability and security risks; building a strong Electricity Information Sharing and Analysis Center (E-ISAC); strengthening engagement across North America; and “captur[ing]” continuous improvement opportunities.

WECC’s draft LTS riffs off NERC’s five focus areas with variations of its own:

  • Innovate and expand risk-based focus in all standards, compliance monitoring and enforcement actions. WECC says it will provide leadership and expertise in the development of ERO standards and draw on “rich stakeholder expertise in the West” to evaluate and develop regional reliability standards or variances “to assure they carefully consider the unique characteristics of the Western Interconnection.”
  • Assess and initiate action to mitigate known and emerging risks to the reliability and security of the Western Interconnection. WECC promises continued collaboration with the ERO Enterprise in developing special assessments and studies while ensuring those efforts are informed by Western viewpoints. It will also supplement those assessments with “Western-focused” work when necessary.
  • Strengthen engagement with the reliability and security community in the Western Interconnection. This focus area reflects WECC’s recent push to ramp up its engagement with regional stakeholders through “proactive outreach and communications with key state and provincial regulatory, legislative and policy bodies and associations to identify drivers of change.” WECC will reach out to share relevant reliability impact information with industry decision makers as they “drive change” across the West. It also intends to share the region’s “specialized and localized” point of view on national reliability and security matters.
  • Seize opportunities for effectiveness, efficiency and continuous improvement. WECC will work to ensure it has the budget and staff to follow through on its reliability and security mission. It will also establish annual goals for organizational performance and share progress with stakeholders through a corporate scorecard.
  • Build the capability and culture that enable WECC to deliver on its critical reliability mission. This entails WECC becoming an “employer of choice” that attracts “the right talent to deliver on its performance objectives.” This focus area also emphasizes the importance of WECC’s “invented future,” during which it builds strong relationships to collaborate with industry on implementing risk-based concepts rather than just enforcing compliance with standards. (See WECC Seeks to ‘Invent Future’ with RA Forum.)

WECC will hold an Aug. 11 webinar “where we plan to do a deeper dive into the long-term strategy and get stakeholder input,” White said. Stakeholders are asked to comment on the plan by Aug. 19. WECC management hopes to get board approval for the LTS in September.

“Assuming that the final long-term strategy is approved with all of the stakeholder feedback, et cetera, by the board at the September meeting, we plan to hold an interactive forum at the annual meeting to increase stakeholder engagement and understanding of the long-term strategy,” he said.

WECC will hold its annual meeting virtually this year on Sept. 10-11.

FERC Ends Idaho Power MBRA Probe

FERC on Tuesday found that Idaho Power had satisfied the commission’s standards for market-based rate authority and terminated a Section 206 proceeding it had ordered last September to find out if the utility was exercising market power in its balancing authority area (ER10-2126).

The proceeding was meant to determine if Idaho Power could continue charging market-based rates in its BAA.

The company’s market-power analysis, initially submitted in June 2019, had passed the pivotal supplier and wholesale market share screens in the Avista, Bonneville Power Administration, Nevada Power, NorthWestern Corp., PacifiCorp-East and PacifiCorp-West BAAs and in CAISO’s Energy Imbalance Market. But it failed the wholesale market share indicative screen in one season in its own BAA.

Based on the results, FERC ordered Idaho Power to show cause within 60 days why the commission should not revoke the company’s market-based rate authority in its BAA.

Idaho Power
Lower Salmon Dam | Idaho Power

Responding in November, Idaho Power said its updated market power analysis, which included a delivered price test (DPT), rebutted the presumption of horizontal market power in its BAA.

“As the commission has previously explained, the DPT analysis identifies potential suppliers based on market prices, input costs and transmission availability and calculates each supplier’s economic capacity and available economic capacity for each season/load level,” FERC said. “The results of the DPT are used for pivotal supplier, market share and market concentration analyses.”

The DPT calculates market concentration using the Hirschman-Herfindahl Index (HHI). “An HHI of less than 2,500 in the relevant market for all season/load levels, in combination with a demonstration that the applicants are not pivotal and do not possess more than a 20% market share in any of the season/load levels, would constitute a showing of a lack of horizontal market power, absent compelling contrary evidence from interveners,” FERC explained.

Under the available economic capacity measure, which factors the utility’s own load into the calculation, Idaho Power’s HHI score was less than 2,500 in all 10 season/load levels. But under the economic capacity measure, its HHI exceeded 2,500 in all 10 season/load levels and “thus Idaho Power fails the market concentration test in every season/load level,” FERC said.

However, FERC noted its prior rulings had found that “failure of either the economic capacity or available economic capacity analyses does not result in an automatic failure of the test as a whole. The commission weighs the results of the economic capacity and the available economic capacity analyses and considers the arguments of the parties.”

“As the commission explained in Order No. 697: ‘[I]n markets where utilities retain significant native load obligations, an analysis of available economic capacity may more accurately assess an individual seller’s competitiveness, as well as the overall competitiveness of a market, because available economic capacity recognizes the native load obligations of the sellers,” FERC wrote. “On the other hand, in markets where the sellers have been predominantly relieved of their native load obligations, an analysis of economic capacity may more accurately reflect market conditions and a seller’s relative size in the market.’”

Given Idaho Power’s native load obligations, FERC found the available economic capacity measure — under which its HHI score was consistently less than 2,500 — more accurately reflected conditions in Idaho Power’s BAA.

“Based on the above discussion, there is no further need for the Section 206 proceeding instituted in Docket No. EL19-87-000,” FERC said. “Accordingly, we will terminate this Section 206 proceeding.”

Vistra Q2 Cash Flow Up 30% from 2019

The company formerly known as Vistra Energy — Vistra Corp. as of July 2 — boosted its second-quarter cash flow by 30% over 2019 and told financial analysts Aug. 5 that the best may be yet to come.

Vistra delivered earnings before interest, taxes, depreciation and amortization of (EBITDA) of $929 million, based on net income of $164 million. The company had an EBITDA of $717 million and net income of $354 million during last year’s second quarter.

Vistra uses adjusted EBITDA as a measure of performance, saying it improves visibility to both net income prepared in accordance with GAAP and adjusted EBITDA.

Vistra
Luminant’s Odessa-Ector gas plant stands ready for possible scarcity pricing later this summer. | Luminant

CEO Curt Morgan reminded analysts during a conference call that “much of the Texas summer shows its teeth in August and September.” He noted that while Vistra’s generating subsidiary, Luminant, has not yet been able to take advantage of scarcity prices in the ERCOT market, last August saw 72 15-minute intervals over $1,000/MWh and 12 intervals reaching the $9,000/MWh cap.

“All it takes is one week of hot temperatures and either low wind output or an unplanned outage for scarcity pricing to materialize,” Morgan said.

At the same time, he warned investors about EPA’s recent regulatory revisions for utilities’ disposal of coal ash. (See “EPA Changes Closure Requirements in Coal Ash Rule,” Federal News.)

“Our evaluation suggests there are several coal plants, especially in PJM, that are under pressure due to this rulemaking,” Morgan said.

Vistra’s share price lost 50 cents during the day, closing at $18.26 on the New York Stock Exchange.

OSW Study Sees $166 Billion in Investment by 2035

A new study finds that Bureau of Ocean Energy Management (BOEM) offshore wind area lease auctions over the next two-and-a-half years could initially pump $1.7 billion into the U.S. Treasury while potentially creating 80,000 jobs and $166 billion in capital investment through 2035.

“We’re talking about five lease areas, offshore New York, North Carolina, South Carolina, California and Maine, and these areas could unlock tremendous energy and economic potential,” Erik Milito, president of the National Ocean Industries Association (NOIA), said at a press conference Tuesday.

Offshore wind study
The report shows OSW development supporting approximately 80,000 jobs annually from 2025 to 2035. | Wood Mackenzie

NOIA commissioned the study by research group Wood Mackenzie with three other groups: the American Wind Energy Association (AWEA), the New York Offshore Wind Alliance (NYOWA) and the Special Initiative on Offshore Wind (SIOW) at the University of Delaware.

“From the NOIA perspective … there is a very strong synergy between offshore oil and gas and offshore wind … and the same shipbuilders, heavy lift vessel operators, steel fabricators and other companies who built the Gulf of Mexico oil and gas business stand ready to lend their expertise to the American offshore wind industry,” Milito said.

Feng Zhang, managing consultant for Wood Mackenzie’s power and renewables division, said the study mainly looked at areas from the New York Bight and south, plus California, but that interest was also “very high” in possible call areas in the Gulf of Maine.

“From the study, we found that if the relevant policy can be put in place, if BOEM and other industry parties can act very quickly, then potentially 2 million acres of federal waters in those areas can go to auction as soon as 2021 and 2022,” Zhang said.

Jump Starter

Additionally, the findings indicate that new offshore wind leases could be a short-term way to jump-start recovery from the economic slowdown caused by the coronavirus pandemic, Zhang noted.

The study found that investment in the country’s offshore wind industry will total $17 billion by 2025, $108 billion by 2030 and $166 billion by 2035.

“From 2022 to 2035, capital investment of $42 billion will go to turbine manufacturers and the supply chain, $107 billion will go to the construction industry and $8 billion will go to the transportation industry and ports. Annual capital investment for operations and maintenance activities will increase to $2.4 billion in 2035,” the study said.

Offshore wind study
Historical OSW lease auction winning price and future forecast ($/km2). | Wood Mackenzie

Long-term, new OSW projects will provide 28 GW of new clean energy resources to power 20 million households and support 20,500 jobs annually for decades beyond 2035, the study found.

The other study sponsors issued statements lauding the economic and environmental benefits of OSW development.

“States along the eastern and western seashores have a massive domestic clean energy resource and many states have set ambitious offshore wind goals to reap the economic and environmental benefits that offshore wind offers but cannot achieve those goals with existing leases,” said NYOWA Director Joe Martens. “It’s time for the federal government to act with the same urgency as the states.”

“We’re on the cusp of a rare opportunity, but the U.S. remains far behind other countries in harnessing offshore wind technology,” said Laura Morton, AWEA senior director of offshore wind. “It’s time for us to unleash this abundant domestic energy source that will deliver tens of thousands of new jobs, revitalize coastal ports and expand manufacturing opportunities to reap major economic and environmental benefits.”

“Offshore wind development can be a major part of the solution to our country’s most pressing energy needs and our country’s most immediate economic woes,” said Nancy Sopko, executive director of SIOW. “Unleashing the potential of offshore wind power through immediate and consistent auctioning of new lease areas can help the United States rebound from the greatest economic downturn in our nation’s history.”

Exelon’s Nuclear Units Face Uncertain Future

Exelon CEO Chris Crane on Tuesday apologized for subsidiary Commonwealth Edison’s involvement in a bribery scandal and said he may be forced to shut down the company’s Illinois nuclear plants without favorable state legislation.

In July, ComEd agreed to a $200 million fine with the Illinois U.S attorney’s office to settle allegations it bribed the state House of Representatives’ speaker in return for legislation that increased the company’s earnings and bailed out its money-losing nuclear plants. Under the Deferred Prosecution Agreement, the bribery charge will be deferred for three years and then dismissed, as long as ComEd continues to cooperate with “ongoing investigations of individuals or other entities.” (See ComEd to Pay $200 Million in Bribery Scheme.)

“We’ve taken robust actions to identify and address deficiencies, including enhancing our compliance governance, to prevent this conduct,” Crane said during a conference call with financial analysts. “We apologize for the past conduct, which did not live up to our values. These new policies will ensure it won’t happen again.

“We’re extremely disappointed with the seriousness of the past misconduct,” he said, listlessly reading his prepared comments. “We know many stakeholders understandably feel the same disappointment. We will take every possible step to earn back the confidence and trust we have lost. This will not happen overnight, and it will be a formidable task, but we’re resolved to get there.”

Exelon
Exelon CEO Chris Crane | © RTO Insider

Crane said Chicago-based Exelon must restore the trust that “has been eroded” while, at the same time, working through legislative strategy in Illinois to help its nuclear plants earn capacity market revenue.

“It’s very critical for us to get it done,” he said, noting his “analytic folks” have a “strong sense” that Exelon’s nuclear units will not clear the next PJM Base Residual Auction.

“Some are uneconomic at this point right now, and some may become more uneconomic,” Crane said. “If we can’t find a path to profitability, we’re going to have to shut them down. We will not run plants and lose free cash flow or earnings on assets that are not supporting themselves. … We will not let the balance sheet [be] further [deteriorated] by non-profitable assets.”

Exelon has lost 14.7% of its stock value since the year began.

The company reported a “strong quarter” with earnings of $521 million ($0.53/share). A year ago, the company had earnings of $484 million ($0.50/share).

Exelon’s operating earnings of $0.55/share beat analysts’ expectations of $0.42/share, as gathered by Zacks Investment Research. The stock price gained 76 cents on the NASDAQ, closing at $38.75.