December 25, 2024

MISO Planning Reserve Margin Climbs to 17% for 2018/19

By Amanda Durish Cook

MISO predicts the 2018/19 planning year will require a reserve margin just more than 17%, a figure that’s been steadily increasing over the years.

Based on its annual loss-of-load-expectation (LOLE) analysis, MISO expects the planning period to require a 17.1% reserve margin for installed capacity (ICAP) and 8.4% margin for unforced capacity (UCAP), the latter of which represents ICAP minus forced outage rates. The RTO will use the margins along with the latest load forecasts to create its enforceable planning reserve margin requirement before April’s capacity auction.

MISO LMP EIM governing body Synchronized Reserves
| MISO

Systemwide, MISO predicts it has about 150 GW of ICAP and almost 139 GW of UCAP to meet a nearly 126 GW expected peak demand for the June 2018-May 2019 period. The RTO’s planning reserve margin assumes the inclusion of 4,764 MW of firm UCAP and 2,331 MW non-firm UCAP from external resources.

MISO’s needed reserve margin has been on the rise since 2013. Last year, MISO predicted 15.8% for ICAP and 7.8% UCAP reserve margin for the 2017/18 planning year, up from 2016/17’s 15.2% and 7.6% values. (See MISO 2017/18 Planning Reserve Margin at Nearly 16%.) All local requirements increased from the 2017/18 planning year, the RTO noted.

Speaking during a Nov. 2 Reliability Subcommittee conference call, MISO senior engineer William Buchanan said the increase is primarily driven by an upswing in generation outages and a change in the dispatch model for demand resources, but it was partially offset by reduction in anticipated load growth. The RTO this year added a new modeling step to capture economic load uncertainty that increases the risk associated with high peak loads, also boosting the reserve margins.

Despite the yearly increases, MISO predicts reserve margins will begin to plateau. According to the LOLE analysis, they will largely hold steady because of similar forecasts over the next decade even as peak demand exceeds 129 GW by the 2023/24 planning year. The LOLE analysis found that through 2027, MISO’s ICAP reserve margin will fluctuate between 17.1 and 17.2% while the UCAP reserve margin will oscillate between 8.3 and 8.4%.

Con Edison Q3 Earnings Fall 8%

earnings Con Ed Consolidated Edison Q3

Consolidated Edison’s third-quarter earnings fell 8% to $457 million ($1.48/share), a drop the company attributed to changes in its rate plan and regulatory charges, as well as the impact of weather on steam revenues. The new rate plan includes changes in the timing of recognition of annual revenues between quarters.

earnings Con Ed Consolidated Edison Q3
Con Edison Forecasted Average Rate Base Balances ($ in millions) | ConEd

“This is an exciting time in the energy industry,” CEO John McAvoy said during a Nov. 2 earnings call. “We’re incorporating renewables into the grid at an increasing rate, we’re using data analytics to provide customers with more information about the way they’re using energy and how they can save, and we’re working on programs to increase electric vehicle use and access to charging stations. At the same time, our $1 billion storm hardening program after Superstorm Sandy has made our system more reliable than ever five years later, having already prevented 250,000 power outages due to our investments.”

The company updated its guidance on adjusted earnings per share for 2017 slightly to $4.05 to $4.15/share. The previous range was $4 to $4.15/share.

Con Ed also said it is unable to estimate the amount or range of possible costs related to an April 21 subway power outage in New York City.

earnings Con Ed
ConEd plant on the East River at 15th Street in Manhattan, New York City

After investigating the outage, the New York Public Service Commission in August issued an emergency order requiring the company to inspect electrical equipment serving the Metropolitan Transportation Authority’s system, analyze power supply and power quality events affecting subway signaling services, provide new monitoring and other equipment, and file monthly reports with the commission on all activities related to the subway system. The commission last month approved another order extending the subway outage oversight beyond its original 90-day limit but has not yet issued the second order.

— Michael Kuser

Board Decisions Highlight CAISO Market Problems

By Jason Fordney

FOLSOM, Calif. — In a move that met criticism from some stakeholders, CAISO’s Board of Governors on Thursday approved two measures intended to prevent the early retirement of unprofitable — but needed — generation in California.

The board approved a reliability-must-run (RMR) contract for Calpine’s Metcalf Energy Center, saying it was an undesirable but necessary measure to maintain electric grid reliability in the Silicon Valley.

CAISO Board of Governors reliability-must-run
CAISO on Thursday approved an RMR agreement for Calpine’s Metcalf Energy Center | Calpine

CAISO Board of Governors reliability-must-run
Bhagwat | © RTO Insider

Despite the unanimous vote, the board expressed unhappiness about approving the contract, an out-of-market payment to keep the 605-MW natural gas-fired plant from retiring.

Governor Ashutosh Bhagwat said: “I am going to hold my nose very, very hard.” He added that “I understand the problem, but I think this is going to be a recurring issue and we need to come up with a solution.”

Governor Mark Ferron said he was tempted to vote against the RMR “because I am opposed to the process and the situation we find ourselves in.” But, he added, “to vote against this contract is not a risk that we should play with.”

CAISO DER Coal Plant Retirements Market Monitor
Ferron | © RTO Insider

The Metcalf RMR is the third such contract awarded to a Calpine plant this year, sparking concerns among industry participants that the CAISO market and California’s resource adequacy (RA) process are not supporting generation needed for future reliability. Calpine in June told the ISO it planned to remove the plant from dispatch on Jan. 1, 2018. The RMR contract was developed in a relatively short time frame after the ISO determined Metcalf was needed for local reliability. (See CAISO RMRs Win Board OK, Stakeholders Critical.)

CAISO Board of Governors reliability-must-run
Berberich | © RTO Insider

Representatives from the California Public Utilities Commission, Pacific Gas and Electric and Cogentrix spoke against the agreement at the meeting.

CAISO CEO Steven Berberich told the board that use of RMR “is not at all how we want to handle procurement.” He added that “the RMR is symptomatic of a bigger problem, which is that resource adequacy is no longer able to meet the needs of the system.” He said that the ISO does not want to frequently approve RMR agreements, and that procurement should be done through the RA process.

Board Approves CPM ROR Changes

In addition to the Metcalf RMR, the board approved a separate, broader program that will pay generators to stay in service to meet reliability needs. The Capacity Procurement Mechanism Risk-of-Retirement (CPM ROR) program expands the existing CPM process to include procurement of at-risk capacity needed for the next RA compliance year.

CAISO Board of Governors reliability-must-run
The CAISO Board of Governors issued several decisions at a meeting on Thursday in Folsom | © RTO Insider

The program includes two application windows each year — in April and November — for three types of ROR designations. As the ISO developed the process, some stakeholders — including the PUC — raised concerns that inclusion of the April window gives resources undue insight into price discovery for the commission’s RA program, which occurs in October. The commission was concerned “that moving a CPM ROR determination to a date prior to the conclusion of the year-ahead procurement process will result in front-running the RA bilateral procurement process.” (See CAISO Participants Question Retirement Program.)

CAISO Board of Governors reliability-must-run
Johnson | © RTO Insider

CAISO added the April window based on requests from generation owners, who said they needed the option of a designation earlier in the year for planning reasons. CAISO changed the proposal to require that a resource attest that it “reasonably believes” its annual fixed costs meet or exceed certain price thresholds. Some have criticized that the ISO would accept an attestation in that regard.

CAISO Infrastructure and Regulatory Policy Manager Keith Johnson told the board that the PUC’s 2019 RA proceeding is an opportunity to address the issues that have been identified. The ISO will evaluate potential modifications to the RMR construct to better align with the current environment, he said in a presentation to the board.

No Time for Other Solutions

CAISO Board of Governors reliability-must-run
Casey | © RTO Insider

Keith Casey, CAISO vice president of market and infrastructure development, repeatedly took to the microphone on Thursday to rebut criticisms of both the RMR and CPM ROR. He acknowledged that the state’s RA program and ISO markets need fixes, but there is not enough time to develop them in an adequate time frame.

The ISO would normally let the RA procurement process run its course in October before signing an RMR agreement, but Calpine told it that the normal time frame would not be workable. Calpine also indicated it was not interested in the CPM ROR program, leaving the RMR as the best option, Casey said. “We don’t want to be one wire away from blacking out Silicon Valley,” he added.

“The issue for me is one of timing,” Casey said. Changing the RA construct is going to be a long and difficult process, and with increasing retirements, “we have got to have some tools to ensure that resources that are critical on the system can be retained.”

CAISO Board of Governors meeting underway | © RTO Insider

The board on Thursday also approved modifications to an incentive that is meant to ensure that RA resources can meet their must-offer obligations and provide replacement capacity if the resource has a forced outage. It changes the Resource Adequacy Availability Incentive Mechanism (RAAIM) calculation to separately calculate generic RA used for system load and flexible capacity, among other changes, according to an Oct. 25 letter from Casey to the board.

Lastly, the board voted to increase its retainer compensation to $40,000/year, which CAISO said is well below the retainers paid to the governing boards of the nation’s other RTOs/ISOs.

ISO-NE Bars Invenergy Plant from FCA 12

By Rich Heidorn Jr.

ISO-NE has barred Invenergy’s planned Clear River Energy Center Unit 2 from offering into February’s capacity auction because of permitting delays resulting from local opposition to the natural gas-fired plant in Burrillville, R.I.

ISO-NE FERC Invenergy FCA
Clear River Energy Center project rendering | Invenergy

Invenergy publicized ISO-NE’s decision for Forward Capacity Auction 12 for 2021/22 in a filing Wednesday to the Rhode Island Energy Facility Siting Board.

The board was scheduled to hold its final evidentiary hearings on the $1 billion project this week but postponed them until December after calling for additional public comment hearings on the plant’s water plan. The plant will have two 485-MW natural gas units with fuel oil backup.

In September, the company announced it had reached agreements with the Narragansett Indian Tribe and water trucking company Benn Water & Heavy Transport to serve as supplemental water suppliers for the plant if it needs more than the primary supplier, the Town of Johnston, R.I., can provide. State regulators had required the company to identify the backup suppliers following a lawsuit by the Town of Burrillville and the Conservation Law Foundation challenging the Johnston supply contract.

The company said the plant will need about 15,000 gallons of water daily, which it says is “90% less than similar plants in the region.”

Invenergy said ISO-NE cited the permitting problems and delays in ordering equipment, although the company said the current schedule would still have allowed it to begin operations by 2021.

“Although Invenergy considered appealing this decision to [FERC], Invenergy could not dispute that there have been permitting delays, and as such, the likelihood that the FERC would overturn ISO-NE’s FCA qualification decision was determined to be remote,” the company said.

Jerry Elmer, senior attorney with the Conservation Law Foundation, told the Providence Journal that “this shows that even the ISO agrees that [the plant] is not needed.”

But in its filing with the siting board, Invenergy included an updated report from PA Consulting Group asserting that the need for the plant is unchanged. The company also said the RTO has told it that Unit 2 is eligible to participate in FCA 13 in 2019.

The report, which assumed a one-year delay in Unit 2’s online date to June 1, 2022, said the delay had no impact on the four findings by the Rhode Island Public Utilities Commission indicating need: Unit 1’s clearing of FCA 10; a significant amount of capacity at-risk for retirement; the state’s location in an import-constrained zone; and the need for capacity above the RTO’s net installed capacity requirement.

Unit 1 is scheduled for commercial operation no earlier than June 2020.

GOP Tax Bill Would Trim PTC, Drop Credit for EVs

By Rich Heidorn Jr.

The tax bill introduced by House Republicans on Thursday would trim the wind production tax credit by more than a third and eliminate the credit for electric vehicles while maintaining the tax credit for Southern Co.’s troubled Vogtle nuclear project.

The proposal would repeal the inflation adjustment for the PTC, effectively reducing the PTC from 2.3 cents/kWh in 2016 to 1.5 cents for projects begun after Nov. 2.

PTC AWEA electric vehicles
| AWEA

The American Wind Energy Association complained that the proposed Tax Cuts and Jobs Act “reneges” on the deal Congress made in 2015, which would phase out the PTC completely over five years.

AWEA CEO Tom Kiernan said the bill is “a retroactive tax hike” that would “pull the rug out from under 100,000 U.S. wind workers and 500 American factories, including some of the fastest growing jobs in the country.”

Under the 2015 legislation, wind projects that started construction in 2015 and 2016 receive the full PTC of 2.4 cents/kWh. Projects that begin construction in 2017 receive 80% of the credit, with those beginning in 2018 reduced to 60% and those in 2019 getting 40%. The credit would be eliminated for projects begun in 2020 and beyond.

Eliminating the inflation adjustment would boost tax receipts by $12.3 billion through 2027, according to a summary released by Republicans on the House Ways and Means Committee.

AWEA also said the law would unfairly change what constitutes the start of project construction. “Investors who put billions of dollars into factory orders and construction contracts cannot go back in time to meet the revised requirements,” it said.

Under current rules, a project is deemed to have commenced construction when it has passed a “physical work” test or shown that 5% or more of the total cost of the facility was paid or incurred. The physical work test is met by activities such as the beginning of excavation for turbines’ foundations or work on step-up transformers.

Developers are required to make “continuous progress” toward completion once construction has begun and must complete the project within four calendar years after the year in which it began construction. The new bill would eliminate the 5% “safe harbor,” disqualifying projects “unless there is a continuous program of construction.”

The wind industry is just one of the potential losers in the bill, which also eliminates the $7,500 tax credit for purchasers of electric vehicles. That would be more bad news for Tesla, which on Wednesday reported a $619 million quarterly loss and said it would not meet its goal of producing 5,000 Model 3 cars per week in 2017. Tesla shares dropped 6.8% Thursday.

The bill also would eliminate the permanent 10% investment tax credit for commercial-scale solar and geothermal power.

But there are also some energy winners.

The Treasury Department would forgo $1.2 billion through 2027 by “harmonizing” the expiration dates and phase-out schedules for ITCs on solar, geothermal, fuel cell, microturbines, combined heat and power system and small wind facilities.

In addition, the bill would remove a 2020 deadline for nuclear plants to claim the 1.8 cents/kWh nuclear production tax credit, a change needed to allow Southern’s overbudget and behind-schedule Vogtle Units 3 and 4 to claim it.

The credit applies to the first 6,000 MW of new nuclear capacity. Because the Vogtle project totals 2,200 MW, and South Carolina Electric & Gas’ V.C. Summer Units 2 and 3 have been canceled, it “will leave a significant amount of remaining capacity that future small modular or advanced reactor projects will be able to access,” the Nuclear Energy Institute said.

SPP Regional State Committee Briefs

LITTLE ROCK, Ark. — SPP’s Regional State Committee will later this month begin taking a lead role in Mountain West Transmission Group’s integration into the RTO, with the first of what will likely be many calls and meetings on the subject.

SPP has identified the RSC as one of the key stakeholder groups in Mountain West’s pursuit of membership. The committee has primary responsibility for cost allocation, financial transmission rights, resource adequacy and remote resources planning within the RTO’s current 14-state footprint.

SPP Mountain West Transmission Group William Scherman
The Regional State Committee’s October meeting | © RTO Insider

Staff played up the importance of the RTO’s role during a recent appearance before the Colorado Public Utilities Commission. (See Col. Regulators Talk Governance with SPP, Mountain West.)

“This is a wonderful strategic opportunity for SPP,” CEO Nick Brown told RSC members Oct. 30. “Expanding our market and lowering our administrative rates both carry significant benefits to SPP members and significant benefits to the Mountain West Transmission Group.

“Now’s the time to engage … please stay that way,” Brown implored. “The next couple of months will be critical.”

SPP will use a commissioners’ forum to work through several policy issues as the integration process moves into more open forums. Some work will still take place behind closed doors, with the Strategic Planning Committee holding executive sessions Nov. 21 and Dec. 4. (See SPP, Mountain West Integration Work Goes Public.)

Mountain West has asked SPP to expand the RSC to include a group consisting of just the Western states, resulting in a single committee with two regional divisions. It has also proposed a Westside Transmission Owners Committee that would have decision-making authority over cost allocation, zonal changes and transmission revenue requirements in what would become the west side of the RTO.

Wind Likely to be SPP’s No. 2 Fuel in 2017

SPP Mountain West Transmission Group
SPP’s Bruce Rew updates the RSC on the RTO’s market performance | © RTO Insider

SPP Vice President of Operations Bruce Rew told the RSC that the Integrated Marketplace continues to work “very well,” despite the growing influence of wind energy in the RTO’s footprint.

Rew said wind will likely become the No. 2 fuel source for 2017, behind only coal. Coal has accounted for 46.9% of the RTO’s fuel mix year-to-date, with wind averaging 22.0% and gas 19.4%, respectively.

Almost 16.7 GW of wind energy is installed and operational in SPP, with another 690 MW registered but not yet operational.

Rew said the RTO came close to setting new records for both wind production and summer peak demand during the third quarter. Wind production peaked at 13.32 GW on Sept. 21, just short of the record of 13.34 GW set in April. On Sept. 22, SPP averaged just more than 12 GW of wind energy for the entire day, Rew said.

Wind penetration during the quarter peaked at 49.41% of system load on Sept. 8. SPP’s record is still 54.47% wind penetration, set in April.

Summer demand peaked at 50.57 GW in July, not far off the all-time peak of 50.62 GW set in 2016.

SPP Mountain West Transmission Group William Scherman
| SPP

Rew said 197 market participants are currently active in the markets. Of those, 130 are classified as financial-only and 67 as asset-owning. He said the day-ahead market was delayed from posting once in the last 12 months, and the real-time balancing market has successfully solved 99.87% of all intervals.

Kansas’ Albrecht Elected as RSC’s 2018 President

The RSC unanimously elected the Kansas Corporation Commission’s Shari Feist Albrecht as its president for 2018, replacing Missouri Public Service Commissioner Steve Stoll. Albrecht currently serves as the committee’s vice president.

SPP Mountain West Transmission Group William Scherman
The RSC’s leadership (l-r): South Dakota’s Kristie Fiegen, Missouri’s Steve Stoll, Kansas’ Shari Feist Albrecht | © RTO Insider

South Dakota Public Utilities Commissioner Kristie Fiegen will become the committee’s vice president next year, with Dennis Grennan of the Nebraska Power Review Board replacing Fiegen as the RSC’s secretary and treasurer.

The committee also approved a 2018 budget of $370,500, with the understanding that $50,000 to $150,000 could be allocated for consulting expenses for its Mountain West work.

— Tom Kleckner

PacifiCorp, NV Energy Gain EIM Market-Based Rate Authority

By Robert Mullin

PacifiCorp and NV Energy can sell power into the Western Energy Imbalance Market (EIM) at market-based rates, FERC has ruled, reversing a previous finding that had restricted the companies to submitting only cost-based offers (ER17-2934).

The commission imposed the restrictions in late 2015 after finding the two Berkshire Hathaway Energy affiliates had failed to prove that they wouldn’t exercise horizontal market power within the market. At the time, the EIM comprised only the CAISO, PacifiCorp-East (PACE), PacifiCorp-West (PACW) and NVE balancing authority areas (BAAs). It now includes Arizona Public Service, Puget Sound Energy and Portland General Electric.

EIM FERC PacifiCorp market-based rate authority
FERC’s decision goes a long way in relieving PacifiCorp’s market restrictions in the interior West. The utility can now sell into the PacifiCorp-East and PacifiCorp-West areas at market-based rates, and will be able to do the same in Idaho Power’s territory starting next April when that utility joins the EIM | WECC

In their August joint filing with FERC, PacifiCorp and NVE said that the bidding restrictions were “no longer appropriate” because both companies now meet conditions for EIM participation set out in previous FERC orders. They also contended that reliance on cost-based bids ran “contrary to organized market design” and presented the risk of unrecovered costs during some market intervals. (See Berkshire Companies Request EIM Rate Authority.) The utilities contended that the restrictions have created inefficiencies in how they manage hydroelectric resources and respond to intraday fluctuations in natural gas prices.

The companies also provided FERC with analysis by Charles Rivers Associates (CRA) demonstrating there has been little congestion between EIM BAAs since the entry of NVE into the market, supporting the argument that member BAAs should not be considered submarkets subject to market power — a key concern for FERC.

The CRA analysis examined EIM price data from December 2015 to November 2016 to determine the frequency of price discrepancies between CAISO and other EIM BAAs — an indicator of transmission constraints that could warrant concerns about local market power.

CRA’s conclusion: In the 15-minute market, transmission paths appeared to be congested enough to create price separation only 0.7 to 2.4% of the time depending on the BAA; the five-minute market experienced congestion during 0.3 to 6.2% of all intervals, with the higher percentage representing periods when prices deviated by just 1 cent/MWh, what FERC called a “conservative” threshold to test for price separation.

In its Oct. 30 ruling, FERC said it had corroborated those findings.

“We have reviewed this analysis and determined the methodology to be acceptable for an EIM submarket analysis,” the commission wrote. “The commission has previously found that binding constraints in 2.2% of all study hours during an 18-month study period is insufficient evidence to support the existence of a submarket. The price separation instances in this case, which are used here as an indication of binding constraints, are generally in the 2% range, which would indicate a lack of a submarket.”

The commission additionally determined that, having demonstrated the lack of submarkets in the EIM, the two companies have prepared their pivotal supplier and wholesale market share screens consistent with FERC requirements.

“Accordingly, we find it appropriate to lift the default energy bid restriction and allow the Berkshire EIM sellers to bid into the EIM at market-based rates without restriction,” the commission said.

FERC’s decision should help relieve the two companies’ broader market restrictions in the interior West. Last year, the commission also revoked authorization for 21 BHE affiliates, including PacifiCorp and NVE, to sell power at market-based rates in the PACE, PACW, Idaho Power and NorthWestern Energy BAAs. (See Berkshire Market-Based Sales Restricted in 4 Western BAAs.)

While that order still stands, the two companies will immediately have a freer hand to effectively bid power into PACE and PACW through the EIM, and will gain similar access to Idaho Power’s territory starting next April when that utility joins the market.

McIntyre and Glick Confirmed to FERC

By Peter Key

The Senate on Thursday confirmed Republican Kevin McIntyre and Democrat Richard Glick to FERC, giving the commission a full panel for the first time in two years.

The two were approved on voice votes, putting them in a position to weigh in on Energy Secretary Rick Perry’s controversial proposal to provide price supports to coal and nuclear plants in competitive markets (RM18-1).

Kevin McIntyre Richard Glick FERC
McIntyre (left) and Glick before their confirmation hearing | © RTO Insider

McIntyre, the coleader of the global Energy Practice at the law firm Jones Day, will serve out the rest of a term that ends June 2018, and then serve a full term that ends June 2023. Glick, the general counsel for Democrats on the Senate Energy and Natural Resources Committee, will serve a term that ends in June 2022.

FERC REV Senate Energy and Natural Resources Committee Kevin McIntyre
McIntyre | © RTO Insider

The nominations of McIntyre and Glick were approved by the Senate Energy and Natural Resources Committee in September, but their confirmations were blocked last month by Sen. Jim Inhofe (R-Okla.), who complained Senate Democrats were blocking several of President Trump’s other nominees. (See Senate Panel Clears McIntyre, Glick for FERC.)

The two were among more than two dozen appointees approved Thursday.

Once they are sworn in, FERC will have its full five members for the first time since October 2015, when Republican Philip Moeller left the commission. FERC was without a quorum between February, when former Chairman Norman Bay resigned, and August, when Republicans Neil Chatterjee and Robert Powelson joined Commissioner Cheryl LaFleur on the commission. (See FERC Quorum Restored as Powelson, Chatterjee Confirmed.)

Kevin McIntyre Richard Glick FERC
Glick | © RTO Insider

Chatterjee welcomed the two in a statement released by FERC. “I’ve enjoyed getting to know Kevin through the confirmation process and am eager to start working with him, and it will be great to reunite with Rich Glick, my former Senate colleague,” he said.

The addition of the two ensures, however, that Chatterjee would need to attract at least two votes for a majority in support of the Department of Energy’s Notice of Proposed Rulemaking to provide “full recovery” of nuclear and coal plant costs. (See FERC Chair Praises Perry’s ‘Bold Leadership’ on NOPR.)

Chatterjee said at a luncheon Wednesday that the federal government may “cast a lifeline” to coal and nuclear power plants while it conducts a long-term review of the country’s power grid. Chatterjee said he was worried that short-term market pressures would force the owners of coal and nuclear plants to close them and later on the country would realize it needed the power they produced.

Although DOE put no price tag on its proposal, estimates of its cost range into the billions. (See Cost Estimates on DOE NOPR: $300 million to $32 billion.) In a conference call with Kentucky reporters Thursday, Chatterjee acknowledged that the policy could result in higher electric bills for some customers. Additional revenue to keep struggling coal plants running “would come from customers in that region, who need the reliability,” he said, according to the Courier Journal. “It’s in these customers’ interests to keep these plants open.”

Chatterjee, like his former boss, Senate Majority Leader Mitch McConnell, is from Kentucky.

During his confirmation hearing, McIntyre said, “FERC is not an entity whose role includes choosing fuels for the generation of electricity.” (See McIntyre to Senate: ‘FERC does not Pick Fuels’.)

MISO: Tx Link from Ontario to Mich. UP not Cost Effective

By Amanda Durish Cook

MISO has concluded there’s little economic benefit to new transmission connecting Michigan’s Upper Peninsula to Ontario.

Reporting on the results of a study requested by the state, MISO officials told a Nov. 1 Economic Planning Users Group call that none of several potential new lines through the twin Sault Ste. Marie cities on the U.S.-Canada border produces benefits commensurate with their costs over a 20-year span.

“Due to the relatively low transfer capability and relatively high construction cost, none of those transmission ideas provided enough benefit to cover its cost,” said MISO Manager of Economic Studies Zheng Zhou.

Currently there’s no transmission connection between Ontario and the UP, although the Lower Peninsula has connections to the province’s hydropower system. Michigan Gov. Rick Snyder requested the study last August in search of solutions to alleviate persistently high power costs in the UP. (See Michigan Asks MISO to Study Tx Links to Ontario.)

MISO michigan ontario transmission study
Lower voltage options examined under MISO’s UP to Ontario transmission study | MISO

MISO worked on the study with Ontario’s Independent Electricity System Operator (IESO), which found it could reliably transfer a maximum of 125 MW to the peninsula. Beyond that amount, “significant reliability upgrades would be needed on both systems to increase that transfer capability,” Zhou said.

‎Economic Studies Senior Engineer Tim Kopp said MISO studied 16 potential new lines, including 161-kV, 230-kV, 345-kV and DC options. It also found that the benefits of a new 400-MW combined cycle plant in Kalkaska County or a 100-MW plant at the nearby Pine River substation would not outweigh their costs either.

MISO did identify benefits over 20 years if a sub-345-kV transmission line allowed 400-MW transfers, but the scenarios showed the local 115-kV system couldn’t reliably support that amount in its current state and would need expensive upgrades.

Final public results of the study will be posted in mid-December, Zhou said.

Customized Energy Solutions’ Ginger Hodge asked if study results would be included in this year’s MISO Transmission Expansion Plan. Zhou said the study was considered ad hoc and not an MTEP study.

Zhou agreed to a request by Michigan Public Service Commission staffer Bonnie Janssen to present the study’s findings at the MISO Board of Directors’ December meeting.

MISO’s study results arrived a week after the PSC approved Upper Michigan Energy Resources Corp.’s $277 million plan to build two reciprocating internal combustion engine stations in the UP in spring (U-18224). Chairman Sally Talberg said the plants will result in a “more reliable and affordable” electric supply for UP customers, including the Tilden Mining operation. Tilden will cover 50% of the capital costs of the plants along with fixed operations and maintenance expenses.

The plants will replace the costly system support resource agreement that keeps the Presque Isle Power Plant running. In October, FERC ruled that ratepayers were overcharged by nearly $23 million for continued Presque Isle operations. (See $23 Million Owed to Ratepayers in Presque Isle SSR Case.)

MISO, PJM Respond to FERC’s Pseudo-Tie Questions

By Amanda Durish Cook

MISO and PJM have responded to a FERC deficiency letter with a defense and clarification of their proposal to impose stricter rules on pseudo-ties.

In early August, the two RTOs filed identical proposals to permit them to terminate or suspend pseudo-ties that don’t acquire transmission service or follow modeling rules by providing real-time data. The proposals would also allow a balancing authority the ability to redirect pseudo-tie output to avoid exceeding NERC operating limits.

In late September, FERC sent a deficiency letter asking how a native reliability coordinator would commit, de-commit or redispatch pseudo-tied generation to avoid operating limits. The commission also asked the RTOs to clarify rules for suspending terminating pseudo-ties. (See 2nd Deficiency Notice Issued for MISO-PJM Pseudo-Tie Effort.)

In filings Oct. 30, the RTOs defended their proposals, with PJM saying redispatch and recommitment of pseudo-tied generation is essential to maintaining operating limits during localized thermal issues, voltage issues or islanding situations (ER17-2218). MISO also said a redispatch option is crucial during planned transmission outages, forced transmission outages or during periods of heavy system transfers (ER17-2220). PJM added that there would be no limit to the number of times a pseudo-tied generator could be recommitted or redispatched. MISO said pseudo-tied resources would still be eligible to provide reactive supply and voltage control service, a point PJM did not address.

PJM said its 42-month notice to terminate a pseudo-tie is rooted in its three-year advance capacity auction and would give “planning engineers sufficient time to take into consideration the impact of the termination” and pointed out that it is “consistent with the notice requirement that a capacity market seller must give to PJM when it intends to deactivate a generator.”

PJM MISO pseudo-tie parameter rules
| MISO, PJM

MISO and PJM said they would only terminate a pseudo-tie under the circumstances described in their respective Tariffs and both would generally try to impose a suspension period first, during which the resource is decommitted or manually dispatched. PJM said termination conditions are “for the most part … tied to a situation in which a pseudo-tie is causing instability on the bulk power system or raising or causing reliability concerns.”

In identical language, MISO and PJM also said they would use a case-specific approach to termination, and would work with generators to address problems and avoid terminations, which they called a “last resort.”

The RTOs have said that they would suspend a pseudo-tie when they are “reasonably” found to pose a reliability risk or don’t follow the rules of their attaining balancing authority. PJM added that the RTOs “expect suspensions to be very exceptional events.”

MISO and PJM proposed that suspensions occur without FERC approval, and that a contested suspension remain in force pending a commission decision.

Meanwhile, MISO is still awaiting final word on its pro forma pseudo-tie agreement for PJM. The agreement was conditionally approved by FERC staff in August before the commission regained its quorum (ER17-1061). The proposal also was the subject of a deficiency notice in the spring. (See FERC Conditionally OKs MISO’s Pseudo-tie Pro Forma.)