November 9, 2024

FERC Blocks MISO Plan to Shorten Queue Negotiations

By Amanda Durish Cook

FERC has rejected a MISO plan to shorten the number of days allowed to customers negotiating a generator interconnection agreement during the interconnection queue process.

The commission on Thursday ruled that MISO did not provide “sufficient support” for Tariff revisions that would have required that GIAs be negotiated and executed within 90 days, down from the current 150 days (ER17-1728). Negotiation and execution represent the last steps in the RTO’s interconnection queue process, occurring after impact and feasibility studies have been completed.

FERC said MISO failed to demonstrate that the shorter agreement process would give interconnection customers sufficient time to sort out final details on new generation projects.

In its filing with FERC, MISO said that, after the commission’s January acceptance of a leaner 460-day interconnection queue (ER17-156), the RTO realized that it also must “proportionally” reduce the amount of time allotted to crafting and signing GIAs — or risk exceeding the new queue timeline by about two months.

“Without reducing this piece of the timeline, the [generator interconnection process] will last for 520 days instead of 460,” MISO claimed.

MISO FERC generator interconnection agreement
| © RTO Insider

The RTO had sought approval to pare down all three queue stages, with negotiation cut from 60 days to 45; execution of a customer agreement reduced from 60 days to 30; and transmission owners given 15 days to sign off on an agreement instead of 30 days.

MISO had argued that the 460-day timeline approved by FERC “specifically contemplated a reduction in the [agreement] negotiation and execution timeline from 150 days to 90 days.”

The commission responded that a diagram proposing a general, 90-day agreement process was only attached to testimony in the queue reform changes, and not reflected in MISO’s Tariff changes. FERC also said its approval of the new queue process hinged on shortening the definitive planning phase of the queue — where restudies most often occur — and did not focus on altering the interconnection agreement process.

MISO’s filing framed the changes as “limited revisions … to improve and clarify the language implementing the commission’s recently approved interconnection queue reforms.” But FERC responded that the RTO’s characterization of the filing as merely a “cleanup” filing to reflect Tariff revisions was incorrect.

Several MISO members — including multiple wind developers — protested the shorter deadlines, arguing that the RTO was attempting to put the entire onus of a shorter queue on interconnection customers while making no sacrifices itself. Those members pointed out that they have already agreed to increased financial milestones and shorter time frames to review the results of system impact studies, and that MISO should now focus on shortening the timeline it gives itself to conduct studies during the definitive planning phase. The wind developers also said MISO is already failing to implement the more streamlined queue, with a backlog similar to that which dogged the old queue process now threatening the 2020 commercial operation deadline imposed on developers seeking the production tax credit.

Other members said the back-to-back 60-day negotiation and execution periods are crucial because that’s when facility costs are finalized and the companies obtain board approval of the project.

MISO last month told stakeholders to prepare for imminent delays while it studies an unprecedented influx of prospective projects that last year entered the queue. (See FERC Accepts MISO’s 2nd Try on Queue Reform.)

MISO also asked FERC for permission to give interconnection customers fewer days in which to modify their selected level of network resource interconnection service so that any change did not occur after the conclusion of the final system impact study. FERC did not address the proposed change in its decision to reject the RTO’s broader proposal.

EKPC Gets PURPA Exemption; Still on Hook for 2 QFs

By Rory D. Sweeney

FERC last week granted East Kentucky Power Cooperative an exemption from being required to purchase power from Public Utility Regulatory Policies Act qualifying facilities larger than 20 MW — but not in time for the cooperative to avoid such purchases from two solar projects within its territory.

The 1978 federal law requires that utilities — including municipals and cooperatives — purchase electricity from QFs at the utility’s “avoided cost.” QFs were defined as cogenerating plants and small power producers under 80 MW. FERC Order 688, issued in October 2006, granted utilities the ability to disregard the requirement for QFs over 20 MW if they can prove the facilities have nondiscriminatory access to the wholesale markets. As a PJM member, EKPC argued that QFs in its territory have that access.

east kentucky power cooperative EKPC FERC PURPA
EKPC CEO Tony Campbell speaks in May at the ground-breaking for a 60-acre solar farm on EKPC’s headquarters property in Winchester | EKPC

FERC agreed, but it declined to backdate the approval far enough for EKPC to avoid contracting with two solar projects.

“Until a utility applies for termination of the PURPA mandatory purchase obligation, and the commission grants such application, a QF has the statutory right to pursue a contract or other legally enforceable obligation with that utility,” FERC said.

The 80-MW Bluebird Solar and 60-MW Blue Jay Solar projects notified EKPC in December and March, respectively, of their intention to sell their entire output to the cooperative at the avoided cost rate.

EKPC argued that it first requested an exemption from the PURPA rules last November, which would have relieved the cooperative of any responsibility to buy from the solar projects. However, the commission’s lack of a quorum earlier this year caused the request to languish and eventually be denied by FERC staff once its 90-day time frame for action had passed.

The cooperative refiled the request on June 9, arguing that the effective date for the exemption should start from the November filing because it was reasonable to believe that FERC would have approved it with a quorum.

The commission rejected EKPC’s argument and set the effective date for June 9.

NYISO Stakeholders Talk Details of Carbon Charge

By Michael Kuser

ALBANY, N.Y. — NYISO stakeholders on Wednesday offered broad support for incorporating a $40/ton carbon charge into the ISO’s markets, but some expressed concern over how the costs of New York’s decarbonization effort would be allocated.

NYISO FERC carbon charge
Rhodes | © RTO Insider

The comments came at a Sept. 6 public hearing jointly run by NYISO and the New York Department of Public Service (DPS).

Both New York Public Service Commission Chair John Rhodes and NYISO CEO Brad Jones, who opened the hearing, signed off last month on a much-anticipated Brattle Group report on pricing carbon into generation offers and energy clearing prices. (See NYISO Study Sees Little Cost Impact from Carbon Charge.)

NYISO FERC carbon emissions Clinton nuclear plant
Jones | © RTO Insider

Brattle’s Sam Newell presented a summary of the report, saying more than 90% of the increased energy costs could be offset through carbon rebates to customers, reduced prices for renewable energy credits and zero-emission credits (ZECs), and improved investment signals. The report predicts the net impact on customer electric bills will be between a 1% reduction and a 2% increase.

Steps Forward

NYISO FERC carbon charge
Weiner | © RTO Insider

Scott Weiner, DPS deputy for markets and innovation, said the plan being developed by his agency, the ISO and the New York Energy Research and Development Authority envisions fossil fuel generators incurring a penalty based on carbon emissions levels. The carbon adder idea was prompted by the PSC’s decision to subsidize the state’s nuclear plants through ZECs.

Jones noted that New York hopes to implement the plan in the markets within three years, a time frame that Weiner called reasonable. Weiner said officials will have a clearer picture in January, after additional outreach.

As first steps, Weiner said, the DPS would seek stakeholders’ comments on, and alternatives to, Brattle’s proposal by Nov. 1. NYISO and the department will hold a series of technical conferences on the issue, with the first likely to be held around Thanksgiving, he said.

“The exact format has yet to be determined, but we have zeroed in on two topics. One is the issue of borders and seams … and the second topic is revenue allocation,” Weiner said.

Underselling Offsets?

NYISO FERC carbon emissions Clinton nuclear plant
Younger | © RTO Insider

During the hearing, Mark Younger of Hudson Energy Economics contended that the Brattle report understated the volume of expected offsets. Brattle did not account for the New York Power Authority, “which has a lot of green resources also [selling] a fair amount of generation at market prices,” he said.

The Brattle report concluded that a $40/ton carbon charge would raise energy prices by approximately $19/MWh on a load-weighted average basis, but that after accounting for static energy price offsets, net customer costs would rise only $6/MWh.

NYISO
| The Brattle Group

“And so, this is a source of revenues, certainly to the state, that could be used either to reduce taxes or to be rebating people, but that’s not included anywhere in [the report’s] estimate of savings and offsets against this $19/MWh cost,” Younger said.

“As we get rid of net metering, we end up with a value stack, and part of the stack is a credit for CO2 savings,” he said. “And obviously the more the market represents the CO2 savings, the less you have to essentially subsidize this behind-the-meter stuff, and that would be another savings because that would bring an out-of-market payment more directly into the market, and that’s not captured anywhere.”

While Newell conceded Younger’s “good point,” he said Brattle’s goal was to make reasonable assumptions in the middle of the range of predicted outcomes.

NYISO carbon charge
| The Brattle Group

Kelli Joseph, director of New York market and regulatory affairs for NRG Energy, pointed to the major challenge of the state trying to achieve a variety of goals through different methods. Among them: RECs, ZECs, the Clean Energy Standard and Reforming the Energy Vision.

“And is the $40 price sufficient to not only handle ZEC, but get 50% renewable and achieve whatever the REV goals are?” she asked.

Informing FERC

NYISO FERC carbon emissions Clinton nuclear plant
Schwall | © RTO Insider

Matthew Schwall, director of market policy and regulatory affairs for the Independent Power Producers of New York, referred to FERC’s interest in price formation, a subject brought up at a May technical conference on harmonizing public policy with wholesale markets. (See NYISO Sees Carbon Adder as Way to Link ZECs to Markets.)

“FERC is looking for guidance,” Schwall said. “Would it be possible for NYISO to work through its stakeholder process to come up with a conceptual filing to submit to FERC — prior to any Tariff filing, prior to coming to a complete market design — in order to get some guidance from FERC?”

NYISO Chief Information Officer Rich Dewey responded that in May the commission said that any proposal would require “a great deal of stakeholder support” to be successful.

nyiso carbon charge ferc
Dewey (left) and The Brattle Group’s Sam Newell

“And we want to have the most thoroughly vetted design before we go down to FERC,” he said.

Weiner added, “Importantly, nobody should assume that FERC is not aware of what we are doing here today and going forward. The DPS staff and NYISO staff have ongoing conversations with FERC staff, so they’re well aware of this process, and I think it’s fair to say they’re encouraged by it.”

Reconciling Competing Interests

NYISO FERC carbon emissions Clinton nuclear plant
Clarke | © RTO Insider

David Clarke, director of wholesale market policy for the Long Island Power Authority (LIPA), questioned the allocation of carbon costs, saying they might be disproportionately borne by consumers in southeastern New York.

“Right now, everyone has a pro rata share of REC requirements,” Clarke said. “LIPA takes on a proportional share of those renewable energy requirements. … Those collections are going down because the costs of the RECS are going down, but the collections from locational-based marginal prices are going up because you’re [reducing] carbon. Those effects are not remaining in the same proportion and they have different effects for downstate New York than for upstate.”

Newell said New York may want to consider allocating carbon revenues evenly to make up for the non-proportional impacts.

“The total wholesale cost, if it goes up about $20/MWh times about 150 TWh, that’s about $3 billion in total wholesale costs, and then the carbon fund is about half of that, or about $1.5 billion,” Newell said. “The incidence of who’s seeing prices increase more or less is not even, and that is why you might want to consider [proportional rebates],” Newell said.

NYISO FERC carbon charge
NYISO and NY PSC Public Hearing on Carbon Charges underway | © RTO Insider

Weiner said the topic of revenue allocation is key. “How do you divide it up? Is there a way to reconcile these competing interests? The status quo is the status quo, but maybe that’s not the best way, either.”

Reliability is Job One

NYISO FERC carbon charge
Nachmias | © RTO Insider

Stuart Nachmias, Consolidated Edison’s vice president for energy policy and regulatory affairs, said “markets have worked well in meeting the reliability needs of customers in the state but haven’t yet incorporated clean energy goals.”

The capacity markets address reliability, and Con Ed spends a lot of time trying to figure out how the energy market price impacts the capacity market, Nachmias explained. “And more importantly, how does that affect the resources we need for reliability to manage a variable future?” he said.

Dewey said reliability is always the grid operator’s first concern.

“The reality is there’s a lot more renewables coming onto our system, so we need to look at what changes might be necessitated in our existing market products and our existing capacity markets, energy markets or ancillary services to be able to accommodate that grid in the future,” he said.

Nuclear Power not ‘Clean’

Manna Jo Greene, environmental action director for Hudson River Sloop Clearwater, said, “I implore you not to use the word ‘clean’ when talking about nuclear energy. I ask you to think about the communities who had the benefit of the goose that laid the golden egg for so many years and are now faced with massive amounts of high-level radioactive waste.”

NYISO FERC carbon charge
Azulay | © RTO Insider

Jessica Azulay, program director at Alliance for a Green Economy, echoed Greene’s view and suggested that the DPS and NYISO consider a charge on other greenhouse gases, such as methane.

Erin Hogan, of the New York Department of State’s Utility Intervention Unit, asked if Brattle could share the study’s spreadsheet model, which might help the formation of independent proposals. Weiner said he didn’t want to put Newell “on the spot … but I think that’s a very good point.”

Hogan said she knew people had different perspectives: “Those who don’t want combined cycle, those who don’t want nuke, and there’s those who don’t want transmission, but they want the emissions to go down. The reality is … the most challenging part is to maintain reliability, and the other part is to achieve the environmental goals, and the third part is trying to do this in the most cost-effective way possible. … I’m asking people to come at it with a pragmatic perspective. Often people look at it as if we’re going to optimize to achieve the perfect evolved frame. I think what we really do is choose the least imperfect solution.”

Post-‘Wheel’ Changes Spark PJM Member Concerns

By Rory D. Sweeney

When Consolidated Edison last year canceled a decades-old arrangement with Public Service Electric and Gas to wheel 1,000 MW of power from upstate New York to New York City via northern New Jersey, the move appeared to free up transmission capacity in the northeast corner of PJM. (See NYISO Members OK End to Con Ed-PSEG Wheel.)

PJM stakeholders are finding out that’s not so.

The cancellation forced operational changes that caused PJM to remodel phase-angle regulator (PAR) flows along the New York-New Jersey border — and along the PJM-NYISO seam — that will reduce transmission limits and increase the region’s LMPs. (See “‘Wheel’ Replacement Reduces Transmission Limits,” PJM PC/TEAC Briefs: Aug. 10, 2017.)

The modeling changes eliminate non-firm transmission service from the capacity emergency transfer limit (CETL) calculation and specify that adjacent non-PJM areas are not available to supply non-firm energy. In practice, the changes only affect operations along the NYISO interface, PJM’s Mike Herman acknowledged. PJM’s recent analyses as part of its Regional Transmission Expansion Plan have not indicated that external support is needed in any other region within its footprint, he said.

Con Ed subsidiary Rockland Electric objected to the revisions during an Aug. 30 educational session hosted by PJM. Rockland serves about 61,000 customers in northern New Jersey as part of Con Ed’s Orange and Rockland Utilities subsidiary just across the New York border.

“It’s very understandable that you wouldn’t want to over-rely on [the PARs] to the extent that you had under the status quo,” Con Ed’s Diana Barsotti said. “We still oppose the deletion of language [in the manual] that has to do with modeling such support that may be reasonably expected in the future.”

Barsotti requested a manual revision that provides a link to information about firm service interchanges.

Stakeholders had been confused by PJM’s changes to CETL values posted in February and had asked the RTO to explain what alterations it made beyond eliminating non-firm imports.

PJM’s Jonathan Kern acknowledged stakeholder concerns but said he was confident the “more conservative” recent assumptions are the most reasonable and don’t depend on the same “extreme mathematical optimization” that the February numbers do. The new calculations also account for resource diversity, resource retirements and PAR-adjustment coordination.

“We’ve been planning the system for decades using a certain set of assumptions and it’s taken us six months to hone in on what we feel is the best approach, so there were some growing pains,” Kern said. “We decided it would be more realistic, practical and conservative from a PAR perspective to more closely align with how New York is planning their system and PJM is operating our system.”

“There must be some number that can come in [through the PARs] in an emergency,” said Dean Bickerstaff of Hartree Partners. “Even though I know you don’t want to count on New York from a planning perspective, the real world would suggest there is some. … The market isn’t just retiring resources up there [in New York]; it’s adding resources as well. So to the extent that we would be good neighbors to them, I’m sure they would be good neighbors to us.”

Herman clarified that PJM isn’t planning to remove non-firm service from its capacity import limit (CIL) calculations.

“The inclusion of non-firm service is intrinsic to the CIL calculations,” he said. “Utilizing a combination of firm transmission service as well as the non-firm energy purchase allows the CIL test to properly identify physical system limits. In PJM’s analysis and experience, firm transmission service alone may not be enough megawatts to hit a physical limit. The purpose of this test is to identify what that physical transmission limitation is.”

McIntyre to Senate: ‘FERC does not Pick Fuels’

By Michael Brooks

WASHINGTON — President Trump’s nominee for FERC chair brought little comfort to Republican senators seeking assurances that, under his leadership, the commission would look into shoring up uneconomic coal plants.

“FERC is not an entity whose role includes choosing fuels for the generation of electricity,” Kevin McIntyre, cohead of law firm Jones Day’s global energy practice, said at his Senate Energy and Natural Resources Committee confirmation hearing Thursday. “FERC’s role, rather, is to ensure that the markets for the electricity generated by those facilities proceed in accordance with law.”

FERC McIntyre President Trump Baseload Generation
McIntyre | © RTO Insider

McIntyre was responding to a question from Sen. John Barrasso (R-Wyo.), who asked if he agreed with acting Chair Neil Chatterjee’s belief that so-called baseload power — coal and nuclear plants — needed to be “properly compensated” to recognize their value to “reliability and resilience.” (See Coal Seeks ‘Resiliency’ Premium; FERC ‘Fuel Wars’ Coming?)

“I think, overall, the FERC’s role should be to take a hard look at these very important questions and determine where FERC’s jurisdiction actually gives it a role in making decisions that could ensure that there’s a proper attention to the reliability and resilience impacts of what is traditionally thought of as baseload generation,” he said.

Later, Sen. Angus King (I-Maine) urged McIntyre to “just go with the science” when it came to baseload generation, expressing concern that the term had become politicized.

“FERC does not pick fuels among different generating resources,” McIntyre responded. “And so it’s important that it be open to, as you say, the science, which I would expand somewhat also to include the characteristics of reliability and the characteristics of economics.”

FERC CAISO Kevin McIntyre Baseload Generation
Glick (left) and McIntyre are sworn in at their confirmation hearing before the Senate Energy amd Natural Resources Committee | © RTO Insider

The other nominee being considered for the commission, Richard Glick, echoed McIntyre’s position. He told Barrasso that a recent U.S. Energy Department study of the electric grid determined that the loss of baseload generation had not impacted reliability, “but they also suggested it was something to keep an eye on and look for in the future.”

FERC CAISO Kevin McIntyre Baseload Generation
Glick | © RTO Insider

“So I think both FERC and the Department of Energy need to keep an eye on it and continue to study the matter,” said Glick, currently general counsel for the Democrats on the Senate committee.

The committee devoted less than half of the two-hour hearing to McIntyre and Glick, as it also considered two nominations to the Interior Department: Ryan Nelson to be solicitor, and Joseph Balash to be assistant secretary for land and minerals management. The committee’s senators — some hailing from states with large swaths of federally owned land and sizable Native American populations, such as Alaska, Arizona, Nevada and New Mexico — had plenty of questions for the two Interior nominees about policies important to their constituents.

The two FERC nominees, on the other hand, found themselves declining to provide specific answers to many questions, citing ongoing proceedings and Notices of Proposed Rulemaking before the commission. Those questions covered issues such as price formation in energy markets, and eliminating barriers to distributed energy resources and energy storage.

Several Democratic senators asked the nominees about states’ rights in enacting renewable portfolio standards. After discussions with the Interior nominees about her home state, Sen. Catherine Cortez Masto (D-Nev.) asked McIntyre and Glick for quick, yes-or-no answers to her questions.

“Do you agree that states have the authority to establish the resource mix that best serves their customers?” she asked, to which the nominees responded in the affirmative.

She also asked if they agreed that renewable resources can be reliably integrated. Glick noted that several states get at least half of their electricity renewables and that none have had any problems.

“In part due to actions taken by the FERC, renewable energy resources are making their way reliably to our grid,” answered McIntyre.

Noting her state’s adoption of a zero-emission credit program, Sen. Tammy Duckworth (D-Ill.) asked if they agreed that states were “the appropriate place for these types of policies to be decided.”

“We do have a federal system of law,” McIntyre responded. “FERC has its role and the states have theirs, and there’s no question that the states have the absolute right to implement these renewable portfolio standards.”

Committee members refrained from addressing some of the more controversial issues brought up during the May confirmation hearing for Chatterjee and Commissioner Robert Powelson — such as climate change and the Public Utility Regulatory Policies Act. (See No Fireworks for FERC Nominees at Senate Hearing.)

Duckworth did ask about FERC’s role in securing a cleaner environment. Both nominees asserted that FERC is not an environmental regulator, while also noting that the commission ensures that clean resources have nondiscriminatory access to the markets and that it is seeking to better integrate DER, storage and demand response.

FERC CAISO Kevin McIntyre Baseload Generation
McIntyre (left) and Glick chat before the hearing. | © RTO Insider

Committee Chair Lisa Murkowski (R-Alaska) told reporters after the hearing that she hopes to advance McIntyre and Glick to the full Senate “late next week.” Their confirmation would restore FERC to a full, five-member slate — which it has been without since the departure of Philip Moeller on Oct. 30, 2015.

Bankruptcy Court Advances Sempra Bid for Oncor

By Rory D. Sweeney

WILMINGTON, Del. — Sempra Energy moved a step closer to acquiring Texas utility Oncor after a U.S. bankruptcy judge on Wednesday approved the $9.45 billion agreement (14-10979).

The deal would give Sempra an 80% stake in the rate-regulated operations of the largest transmission and distribution utility in Texas. The deal must still be approved by the Public Utility Commission of Texas.

The utility has been the subject of a series of failed takeover bids since parent Energy Future Holdings, saddled with almost $50 billion in debt after poor bets on energy prices, declared bankruptcy in April 2014.

EFH announced the deal with Sempra three weeks ago in the same Delaware courtroom, after hedge fund Elliott Capital Management — the largest holder of EFH bonds — opposed as too low a $9 billion all-cash offer by Berkshire Hathaway Energy. Including debt, Berkshire’s bid valued Oncor at $18 billion, while Sempra’s values the utility at $18.8 billion. (See Sempra Outmuscles Berkshire for Oncor.)

‘Largely Consensual’

“Unlike any proposal we’ve had in the past, this proposal has the support of one of the debtors’ largest and most active creditors,” Chad Husnick, an attorney representing EFH, told Judge Christopher Sontchi. “The Sempra transaction is the highest and best available transaction.”

Husnick said the Sempra deal was “largely consensual” and prompted just one objection regarding how creditors would be compensated, a consideration that Sontchi said should be reserved for a confirmation hearing. That hearing would take place after the PUCT approves the deal.

“We’ll try it again,” Sontchi said in approving the documents, drawing laughter from the courtroom.

Sempra said it is committed to ensuring that Oncor remains independent, financially strong and based in Dallas with local management.

“Oncor is a well-managed, top-tier utility, operating in one of the strongest U.S. growth markets. We believe it will be an excellent strategic fit with our portfolio of utility and energy infrastructure businesses, while opening up a new avenue for our long-term growth,” Sempra CEO Debra Reed said in a statement after the hearing.

The acquisition would allow Sempra to regain a foothold in Texas, where it once owned and operated 10 power plants and still maintains a 200-person Houston office to support marketing and development activities. (See Sempra Begins ‘Listening Tour’ of Key Stakeholders.)

FERC REV Oncor bankruptcy
| Sempra Energy

With the approval in hand, EFH set an Oct. 30 voting deadline for its plan. EFH approved the deal in part because Sempra was willing to accept ring-fencing of Oncor — giving it independence from its corporate parent — and no assurance that it will get control of the 20% of Oncor now owned by Texas Transmission Holdings Corp.

Sempra is the fourth would-be suitor for Oncor. Dallas’ Hunt Consolidated and Florida-based NextEra Energy saw separate bids fall apart in the face of the Texas PUC’s calls for strict ring-fencing measures and a requirement that Oncor be run by a “truly independent” board with control over decisions on capital expenditures and operating expenses.

NextEra Termination Fee Battle

Wednesday’s hearing also addressed EFH’s upcoming legal battle with NextEra, which had offered $18.7 billion for Oncor but failed to win approval for the deal from the PUCT. EFH accused NextEra of failing to do its best to receive approval and sued the former suitor earlier this year to prevent any attempt by NextEra to claim the deal’s $275 million termination fee. The trial is set to begin next April.

EFH filed for Chapter 11 protection in 2014 with roughly $42 billion in debt, which was then the eighth-largest bankruptcy in U.S. history. About $25 billion of the debt has been restructured by spinning off subsidiary Texas Competitive Electric Holdings, which split the company in half.

MISO Makes Case for $130M Market Platform Upgrade

By Amanda Durish Cook

CARMEL, Ind. — ‎MISO’s proposed multimillion-dollar spend to upgrade — and then replace — its market platform will yield a nearly threefold return within 12 years, stakeholders heard this week.

MISO market platform
Ramey | © RTO Insider

The $130 million invested to extend the current system and implement a new platform would reap $341 million in net benefits by 2030, MISO Vice President of System Operations Todd Ramey said during a Sept. 6 workshop in which RTO officials laid out the business case for replacing the system.

MISO’s Board of Directors in June approved the first phase of the upgrade, enabling the RTO to commit $65 million to lengthen the life of its current market platform by at least five years. Another $65 million will be needed to create a new, modular market platform, the final design for which is slated to emerge in 2019. (See MISO Sets Target for Market Platform Upgrade Decision.)

Countdown to Obsolescence

Since 2005, MISO has spent about $350 million to develop and expand its market system, which was built using technology from the 1990s. The RTO predicts it has five to seven years before evolving cybersecurity standards and increasing market complexity render the system obsolete, no longer able to clear the day-ahead market. Current vendor General Electric also plans to end support for the existing platform around that time.

MISO market platform
Bladen | © RTO Insider

Early-stage prototypes of the new computer system will be released in 2018 and 2019 for stakeholder scrutiny, said MISO Executive Director of Market Design Jeff Bladen. The RTO will begin to swap out market components by 2020 and fully migrate to the new modular computer system by 2023, he said.

“The goal is for a modular system … that is much less brittle than the existing system,” Bladen said, adding that the new system will shed the “hub and spoke” software format of the current system in favor of a “data integration layer” that can run several applications simultaneously while isolating the impacts of market changes so other programs are not affected.

Bladen said MISO’s current system cannot accommodate the “plausible” scenario in which hundreds of storage assets begin participating in the market over the next few years. It’s also unable to manage the “added scale and added scope of the existing market, let alone the security posture we would like to have as we look over the horizon,” he said.

The current system also cannot support some planned market enhancements — such as a price spread product, which will have to wait for the future platform, Ramey said. MISO expects the need for new ancillary services — including the recent additions of enhanced combined cycle modeling, a ramp capability product and extended locational marginal pricing — to only increase in the future.

“In a world where resources will continue to multiply and resource size will continue to decrease, the ability to handle more of them and in a more automated fashion” is a must, Bladen said.

Big Effort

Bladen said MISO is currently assembling a team of employees led by Ramey to oversee the replacement.

“This is going to be at least as big an effort as the original market roll-out,” he said.

MISO plans to issue a request for proposals for a system replacement this month. The RTO is looking for a resilient platform that can handle an evolving energy portfolio with increased energy storage and distributed energy resources, possible footprint expansion and future market products — and include security that can stand up to cyber threats, according to Bladen.

MISO market platform
| MISO

Under the near-term preserve-and-protect plan, MISO “is going to wring the very last degrees of usefulness out of the current system,” Bladen said.

Indiana Utility Regulatory Commission staffer Dave Johnston asked if the platform changeover would require MISO’s Independent Market Monitor to upgrade its own software. The Monitor has functions that run alongside MISO’s day-ahead market to enforce market mitigation when necessary.

Bladen conceded the possible need for an upgrade in order to ensure the IMM’s continued operation. And although “it’s very early in the process,” the Monitor’s IT staff may begin to work with MISO staff on the issue, he said.

MISO will convene another stakeholder workshop in late October to discuss how RTO members’ current software might interact with a new market platform, Bladen added.

Customized Energy Solutions’ David Sapper urged MISO to share regular updates with the stakeholder-led Finance Subcommittee. “They’ve all signed nondisclosure agreements, and MISO can be candid with them,” Sapper said.

MISO would consider that option, along with possibly providing updates to the Market Subcommittee, Bladen said.

RTO officials will also later this month provide the board with a project status report during a board meeting in St. Paul, Minn.

“We’re going to have an ongoing conversation going forward,” Bladen said. “We will take any feedback you have on the work we’ve done so far.”

Critics Protest PJM Dynamic Transfers Plan

By Rory D. Sweeney

PJM’s proposal to create standardized contracts for establishing dynamic transfers with other balancing authority areas has provoked opposition from market participants, a neighboring ISO and the Independent Market Monitors for both PJM and MISO.

Critics of the proposed pro forma agreements for pseudo-tied resources filed protests with FERC over the past week — each with a different complaint (ER17-2291).

PJM and MISO both received stakeholder endorsement for their plan to establish agreements that would impose standard requirements on external units seeking to deliver power into PJM. The grid operators filed relevant revisions to their joint operating agreement on Aug. 1 (ER17-2218, ER17-2220).

MISO received conditional approval of its agreement from FERC on Aug. 9, although the plan has since been protested by American Municipal Power. PJM’s proposal includes separate agreements for pseudo-ties and dynamic schedules and was filed with FERC on Aug. 11. (See MISO-PJM Markets Meeting Addresses Seams Issues.)

‘Adverse’ Impacts

In its protest, NYISO said it “is prepared to work with PJM to develop a mutually acceptable alternative,” arguing that the current proposal “will likely cause adverse reliability impacts” and “exacerbate interregional seams.” It said PJM’s proposed pseudo-tie rules, which would require all dispatch control to be transferred to PJM from the RTO or ISO where the unit is located, “are fundamentally incompatible” with several NYISO practices, including financial transmission reservations, generator scheduling market rules and reliability operating standards. The rules would also conflict with the grid operators’ interregional agreement and NYISO’s Tariff, the ISO said.

The New York grid operator said PJM shouldn’t be allowed to standardize pseudo-tie requirements. Any agreement should be “sufficiently flexible to accommodate regional differences at its borders” and require approval from the native balancing authority, it said. Under PJM’s current plan, the native BA would only have to acknowledge awareness of the agreement between PJM and the unit but wouldn’t have to be a party to it.

At recent stakeholder meetings, PJM staff have said they attempted to develop the agreements with input and endorsement from NYISO, but that the neighboring ISO refused to cooperate. Staff decided to move forward without NYISO’s involvement.

IMMs Weigh In

PJM FERC dynamic transfers
Patton | © RTO Insider

While recognizing that PJM has attempted to address previous concerns, MISO Monitor David Patton contended that the plan still creates “substantial economic and reliability harm to the customers in [MISO and PJM] areas and [provides] no countervailing benefit that cannot be achieved by other means.”

PJM’s requirement of operational control creates a problem, he said, because the BA “most impacted by the generator and responsible for the generator interconnection and local impacts loses control of commitment and dispatch.”

PJM FERC dynamic transfers requests for proposals
Bowring | © RTO Insider

PJM Monitor Joe Bowring also filed comments opposing PJM’s plan for operational control — but for the opposite reasons. He called the proposal “an improvement over the existing rules” but said it “needs to be substantially strengthened” because issues the Monitor has pointed out before “remain and are amplified.”

Bowring reiterated an argument he’s brought up repeatedly at stakeholder meetings: that the rules should be designed so that pseudo-tied units can serve as “complete substitutes” for capacity resources within the RTO’s footprint. As such, he argued, the native BA should not be able to recall the unit. Otherwise, pseudo-tied units shouldn’t be eligible to be capacity resources. The agreement would allow native BAs to supersede PJM’s control during two emergency conditions.

Bowring’s filing requests removal of that exemption, along with allowances for suspension or termination of a pseudo-tie.

The provisions create “substantial uncertainty as to whether a pseudo-tied external capacity resource can be available and under the dispatch control of PJM when needed. As a result, pseudo-tied external capacity resources cannot be considered a complete substitute for internal capacity resources,” he said. “If external capacity resources cannot be full substitutes for internal capacity resources, they are inferior products and should not be permitted in the PJM capacity market because they will suppress the price for internal resources and result in an inefficient market outcome.”

Other Protests

Several municipal power organizations, cooperatives and transmission companies also filed protests. Like Bowring, Cogentrix Energy Power Management supports standardizing pseudo-tie rules but opposed the suspension and termination provisions.

“PJM should not be permitted to suspend or terminate a pseudo-tie on any lesser basis than it may suspend or terminate an internal generator’s interconnection rights,” Cogentrix wrote.

The generator, which owns a pseudo-tied unit in Tilton, Ill., also took issue with what it believes is an insufficient transition period and argued that a pseudo-tie should have just one comprehensive agreement among RTOs. PJM’s proposal — which stemmed from the inability for PJM and MISO to agree on terms — would require a unit to obtain separate agreements with each grid operator for the same pseudo-tie.

The Illinois Municipal Electric Agency argued that the proposal is the most recent in a series of changes that has made it “increasingly more difficult and more costly” for IMEA to use its generation units in MISO to self-supply its customers in PJM. The border situation developed in 2004 when Commonwealth Edison migrated from MISO to PJM.

“Like erosion at a beach caused by a succession of waves, each new set of restrictions imposed by PJM, culminating with the current pseudo-tie ‘wave,’ contributes to the erosion of IMEA’s statutory protections,” IMEA staff wrote.

IMEA also contended that its type of pre-existing exception should be grandfathered.

The Northern Illinois Municipal Power Agency said that units with existing pseudo-ties shouldn’t be subject to PJM’s proposed administrative fees in signing the standardized agreement. The agency serves load in PJM but has an ownership stake in a generation resource in MISO that is partially pseudo-tied.

AMP’s protest acknowledged that it endorsed a previous version of the proposal, but that the filed version doesn’t resolve all pseudo-tie issues as it purports to. The utility criticized the filing as “one more piecemeal effort to address these issues” and requested several changes on indemnification, agreement termination and authority to determine payments.

North Carolina Electric Membership Corp. took issue with PJM “unmooring” the agreement from the RTO’s Tariff definition of long-term firm point-to-point transmission service. PJM has previously attempted to impose a five-year service requirement for pseudo-tied units that goes beyond the one-year requirement in the Tariff, and the co-op expressed concerns the RTO might use the agreement to lengthen the requirement if it is not linked to the Tariff definition.

Several intervenors urged deferring a decision on the agreements until other dockets focused on pseudo-ties have been addressed. Patton estimated there are “at least” 10 such proceedings and seconded MISO’s request for a technical conference on the issue.

“Determinations by the commission in those other dockets will invariably affect evaluation of the changes proposed in this proceeding,” he wrote.

Several of those dockets are complaints regarding double assessment of congestion management charges (EL16-108, EL17-29, EL17-31). PJM and MISO have developed a solution that they believe addresses the problem and will be seeking stakeholder endorsement in two phases.

ISO-NE Files Cluster Study Rules; Window to Open in Nov.

By Rich Heidorn Jr. and Michael Kuser

ISO-NE hopes to open a window in November for Maine wind generators interested in joining a cluster interconnection system impact study. The RTO filed its proposed clustering methodology for FERC approval on Sept. 1, requesting approval by Nov. 1 (ER17-2421).

The filing culminates an 18-month effort to assess new 345-kV AC transmission circuits that could connect to areas in northern and western Maine with the largest number of requested new generation interconnections. (See ISO-NE to Offer Clustered Interconnection Requests in Maine.)

System Planning Director Al McBride presented a description of the filing and the study plans at Wednesday’s Planning Advisory Committee meeting.

The clustering approach will involve two phases: a regional planning study, followed by a cluster system impact study of multiple projects that will share the costs for common upgrades.

The Maine Resource Integration Study will be used as the regional study for the first two clusters being considered for development:

  • A radial double-circuit 345-kV AC line between the Maine Yankee generating plant to a new substation at Pittsfield, with a new 345-kV line and three additional substations north of Pittsfield and ending near the Canada border. The estimated cost is $1.31 billion.
  • A radial 345-kV AC line north of the Larrabee Road substation to near the New Hampshire border at an estimated cost of almost $521 million.

The estimates include a shared cost of $108 million for a new 345-kV line from Coopers Mills to Maine Yankee (line 392) that is needed by both radials. Costs would be allocated using the distribution factor methodology or the late-comer cost allocation rules.

ISO-NE wind system impact study
ISO-NE plans to study two clusters of transmission upgrades to enable the connection of more wind generation in western and northern Maine. | ISO-NE

The latecomer provision was developed to prevent free-riders with later interconnections from making use of the clustering upgrades. It would require interconnection customers that connect within 10 years of the cluster upgrade’s in-service date to share in the cost of the upgrades.

Planners estimate the combined clusters could accommodate about 1,900 MW of generation with a maximum of about 1,200 MW on either radial.

The northern cluster projects could accommodate up to 350 MW of additional generation without any new lines south of Pittsfield, assuming the Surowiec-South line remains at 1,600 MW. The maximum is limited by N-1 and N-1-1 violations on lines south from Orrington. Doing the project without the double circuit while increasing Surowiec-South to 2,200 MW would permit 675 MW in additional generation.

The clustering methodology received support from 95% of the Participants Committee in February.

Generators joining the study will be required to post a “very significant financial commitment” — the lesser of $1 million or 5% of the customer’s estimated costs for the upgrade, McBride said.

If either cluster is less than fully subscribed, the RTO will allow resources to withdraw to avoid a higher cost allocation.

“If the cluster doesn’t fill … we’re going to be continuing coming back to the PAC” for other solutions, including a potential HVDC project, said McBride.

The RTO also could open a second cluster window next year following the award of contracts in Massachusetts’ solicitation for 9.45 TWh a year of Class I renewables (wind, solar, hydro or energy storage). The winning projects are scheduled to be chosen by Jan. 25, with contracts completed and sent for state regulators’ review by April 25. (See Hydro-Québec Dominates Mass. Clean Energy Bids.)

McBride said ISO-NE doesn’t want to delay the first study window until after the solicitation because of the number of Maine wind generators ineligible for the cluster study whose interconnection costs might be affected by the cluster projects. “Their studies shouldn’t be held up any further,” he said.

FERC Orders Tech Conference on Algonquin No-Notice Changes

By Michael Kuser

Responding to protests by National Grid, energy shippers and local distribution companies in New England, FERC on Friday ordered a technical conference on Algonquin Gas Transmission’s proposal to change the terms of its no-notice services (RP17-808).

In June, Algonquin asked the commission to approve an update its no-notice services, last changed in 1993, to reflect its “current practices and operational requirements” and eliminate requirements the company said have become outdated with automation and faster forms of communication.

The changes would clarify that customers under Algonquin’s AFT-E and AFT-ES rate schedules seeking no-notice service must have nominated and scheduled an equal quantity of gas on a pipeline upstream of Algonquin for that day.

It also would specify that the right to change primary delivery points under AFT-E/ES only applies to temporary capacity releases.

On July 27, commission staff issued a delegated order accepting Algonquin’s filing but suspending the changes until Jan. 1, 2018, subject to refund and further commission order.

Janice K. Devers, Algonquin’s director of tariffs, told RTO Insider that “the commission’s directive to convene a technical conference was not a surprise. There is a probably a desire on their part to get clarification on the issues prior to the end of the suspension period on Jann. 1, 2018.”

FERC Algonquin no-notice changes
| Spectra Energy

Energy shippers Direct Energy Business Marketing and Shell Energy North America claimed the revisions to rate schedules AFT- E and AFT-ES would unnecessarily limit the availability of no-notice service by implementing more restrictive eligibility criteria, undercutting the commission’s policy of providing shippers with greater scheduling flexibility.

National Grid asserted that Algonquin had failed to show that the proposed tariff changes are just and reasonable. The company also said that it relies on the right to call on reserved capacity on an intraday basis without needing to submit nominations prior to the start of the gas day. The company said that helps it meet shifting daily demand from its predominately low-load-factor residential and small commercial customers.

Sprague Operating Resources, which operates refined products and materials handling terminals, filed a letter in support of the protests.

In its Sept. 1 order, the commission said it lacked enough information to determine whether Algonquin’s proposed tariff changes are just and reasonable. The commission said that discussion at the conference would not be limited to the issues identified in the order.