October 30, 2024

MISO to Release Competitive Tx Project Cost Guide

By Amanda Durish Cook

CARMEL, Ind. — MISO will publish a guide describing its cost estimation process for competitive transmission projects by August, according to RTO staff.

“We’re going to really document how we create our cost estimates,” Alex Monn, MISO senior substation design engineer, said during a June 13 Planning Subcommittee meeting.

The RTO has also changed some aspects of its original cost estimation proposal based on stakeholder input.

With the emergence of competition to build transmission under FERC Order 1000, MISO had to begin providing cost estimates for competitive projects in order to protect the confidentiality of developers’ bids. The RTO wants to put a more transparent process in place before the next competitive project is opened to bidding. (See “MISO Seeks to Improve Tx Cost Estimates,” MISO Planning Subcommittee Briefs.)

miso cost allocation
| © RTO Insider

MISO plans to release both a planning-level cost estimate process and a more final scoping-level one. Stakeholders will review the RTO’s procedures on an annual basis, with the first review scheduled for January 2018.

“We’re going to make this a yearly cycle,” Monn said.

Stakeholders generally agreed on MISO’s new 20% project cost contingency allotment, up from an earlier 15% allowance: “Twenty percent is where everyone landed, so that seems like a good estimate for us,” Monn said.

However, MISO will keep overhead project cost allocation at 10% of the total project cost despite some stakeholder discord.

“In talking to stakeholders, everyone had a different basket of overhead costs,” Monn said. He said MISO staff still believe 10% is the most reasonable figure.

MISO transmission design engineer Devang Joshi said the RTO has increased its planning-level cost estimate for transmission line length to the straight distance between substations plus an additional 30% of the length. Stakeholders asked for more leeway after the RTO originally proposed a straight-line length plus a 20% adder. For scoping-level cost estimates, MISO will create a “reasonable proxy route for the purposes of determining a line length.”

The RTO has also simplified terrain and grading project cost impacts into three categories apiece. Terrain types include flat lands with light vegetation, forested areas and wetlands, with each represented by cost per acre and mile instead of MISO’s originally proposed terrain multiplier. Grading types are identified as “typical” (with the land being less than 30% sloped), “rough” (30 to 50% slopes) or “mountainous” (greater than 50% slopes).

At stakeholder request, the RTO has also added a cost estimate for constructing access roads to substation construction sites, but it reduced transformer cost to a simple unit cost of the transformer instead of a “turnkey” cost that would have provided for other construction materials.

NYISO Management Committee Briefs

BOLTON LANDING, N.Y. — NYISO said Tuesday that it declared a major emergency on May 21 during the hour beginning 5 p.m. after the loss of 1,000 MW of generation in ISO-NE caused the Central East interface flow to exceed its voltage collapse limit.

It was the second major emergency declaration in a month after one in April, also stemming from interface flow problems. NYISO had last declared a major emergency in July 2016.

Wes Yeomans, NYISO vice president of operations, presented the ISO’s May 2017 operations report during a June 13 Management Committee. The report showed that last month’s peak load of 25,578 MW occurred May 18 and that the month saw more than nine hours of thunderstorm alerts.

The grid operator reported that Lower Hudson Valley installed capacity (ICAP) prices for June fell by 27 cents month over month to $10.01/kW-month, while New York City was down by 33 cents to $10.24. Both declines stemmed from increases in generator unforced capacity available and a decrease in unoffered megawatts. The New York Control Area ICAP price meanwhile increased by $2.17 to $3.89, primarily because of reduced imports and increased exports.

Natural Gas down a Penny from April, up 76% from 2016

In his CEO/COO report to the Management Committee, NYISO COO Rick Gonzales noted that the ISO’s May average year-to-date monthly energy cost of $36.54/MWh represented a 22% increase from May 2016. The average locational-based marginal price for May was $31.74/MWh, compared with $23.31/MWh a year earlier.

NYSIO management committee
| NYISO

May natural gas prices on the Transco Z6 pipeline serving New York City were down a penny from the prior month to $2.80/MMBtu but up 76.5% year over year. The grid operator’s average daily sendout was 383 GWh/day in May, compared with 377 in April and 397 in May 2016.

May distillate prices were down compared to the previous month but up 7.4% year on year. Total uplift costs were higher than in April, while costs per megawatt-hour fell. The local reliability share for uplift was 24 cents/MWh, up from 20 cents/MWh in April, and the statewide share was -13 cents/MWh, down from -8 cents/MWh.

New Testing Requirement for Automatic Swap Dual-Fuel Units

The Management Committee approved revisions to NYISO’s Market Services Tariff as described in the “Zone J Dual Fuel Testing Tariff Revisions” and recommended that the Board of Directors authorize filing the revisions under Section 205 of the Federal Power Act.

The New York State Reliability Council Rule G2 R4 requires combined cycle units in Zone J (New York City) that can automatically swap fuel type to test that capability during each capability period. NYISO is updating its Services Tariff Section 4.1.9 and Ancillary Services Manual Section 8 to comply with the rule.

Michael Kuser

ERCOT Board Approves West Texas Transmission Project

By Tom Kleckner

AUSTIN, Texas — ERCOT’s Board of Directors on Tuesday approved the Far West Texas transmission project, which will result in the construction of two 345-kV lines southwest of Odessa, Texas.

The project would have received unanimous approval but for the abstention of American Electric Power, which will build the project, along with Oncor and Lower Colorado River Authority Transmission. The ISO’s Technical Advisory Committee unanimously approved the project in May. (See “Far West Texas Project Gets TAC’s OK,” ERCOT Technical Advisory Committee Briefs.)

ERCOT board far west texas project
| ERCOT

The $336 million project is designed to address the region’s continued load growth, which has averaged 8% since 2010. Increased oil and natural gas exploration in the Permian Basin and a jump in generation projects — mostly solar — are behind the numbers. ERCOT said peak electricity demand in the area has jumped from 22 MW in 2010 to more than 200 MW in 2016 and is projected to exceed 500 MW by 2021.

ERCOT board far west texas project
Billo | © RTO Insider

“We continue to see a tremendous amount of load growth in West Texas,” said Jeff Billo, ERCOT’s senior manager of transmission planning.

One 85-mile line would run between the Riverton and Moss switching stations, with a second circuit added to the existing 16-mile 345-kV line between Moss and the Odessa line. A second 68-mile 345-kV line will connect the Solstice and Bakersfield substations.

The project is expected to be completed within five years, pending approval from the Public Utility Commission of Texas.

Oncor and AEP initially proposed the project to ERCOT’s Regional Planning Group in April 2016. Staff reviewed 40 different alternatives and lowered the cost to $336 million after settling on the most cost-effective of four options: two separate double-circuit 345-kV lines — each with one circuit in place, substation expansions and other transmission elements. ERCOT concluded the upgrades “meet the reliability criteria in the most cost-effective manner and have multiple expansion paths to accommodate future load growth.”

UPDATE: Capacity Survey Shows MISO in the Black

By Amanda Durish Cook

In a departure from previous years, the 2017 Organization of MISO States-MISO resource adequacy survey suggests the RTO will have sufficient capacity to meet near-term planning requirements.

The annual results show the RTO will have 2.7 to 4.8 GW of excess resources from 2018 to 2022, translating into a 16 to 22% reserve margin — “sufficiently” above the 15.8% planning reserve margin requirement, according to MISO.

“The MISO region will have ample electricity-generating resources to meet expected demand while also maintaining an adequate supply of reserves for the next five years,” the RTO said in a statement. “The results show an improved resource adequacy outlook compared to last year.”

MISO Executive Director of Strategy Shawn McFarlane said this year’s range represents a 2 GW increase over the range predicted by last year’s survey.

“For the first time in the survey, we show adequate capacity resources,” he said during a special June 16 conference call to discuss results.

More than 96% of MISO’s load responded to the survey, according to the RTO. “We’re glad to see another high participation rate,” said OMS president and Indiana Utility Regulatory Commissioner Angela Weber.

The rosier results can be attributed to lower demand forecasts and a lukewarm growth rate of 0.5%, down from 0.8% in 2016, the RTO said. Its forecasted 2018 summer peak of 125.1 GW is down 2.5 GW from predictions made earlier in the year, it said. (See MISO Slims Summer Reserve Prediction.)

Changes to the way the RTO counts megawatts available as capacity might have also boosted the results. Weighted averages in this year’s survey included a 35% share of projects in the definitive planning phase of the interconnection queue, a change made to address stakeholder concerns that the survey was producing overly conservative capacity forecasts. (See OMS-MISO Survey Moves Ahead with New Calculation.)

Weber said the process of the survey and results continue to improve.

“Capturing resource adequacy for a moment in time remains an important tool,” she added.

Last year’s survey forecasted that the RTO would exceed its then-projected 15.2% reserve requirement by 0.9 GW — or 0.7% above the 2017 requirement — and that it could face a capacity shortfall by 2018 under a worst-case scenario. (See OMS-MISO Survey: Generation Shortfall Possible.) The 2015 survey concluded that a shortfall could occur by 2020.

resource adequacy survey OMS MISO
| 2017 OMS MISO Survey Results

This year’s results show that two zones still face capacity shortfalls in 2018, but MISO said that “load-serving entities in these areas should be able to reliably acquire capacity from outside their zones to meet these needs.” Zone 5 in Missouri is expected to have a 0.3-GW shortfall, while Zone 7 in Lower Michigan could come up short by 0.7 to 1 GW. Shortfalls in both areas are predicted to persist into 2022. All other local resource zones are expected to have surpluses ranging anywhere from 0.4 to 1.6 GW in 2018 and 0.2 to 1.5 GW by 2022, except Indiana and Kentucky’s Zone 6, which has the potential for either a 0.7 surplus or a 0.4 shortfall by 2022.

Zone 4 in Southern Illinois showed the greatest improvement: Its 1.6-GW forecasted deficit became a 0.7-GW surplus in this year’s survey after MISO reduced load, added 0.4 GW of new resources and factored in the increased availability of existing resources in the zone.

“Several units at 1.8 GW that were previously expected to retire were determined to serve MISO load at the committed level,” McFarlane said of Zone 4.

Minnesota, Wisconsin and the Dakotas’ Zone 1 was limited to 600 MW in exports in 2018 due to a capacity export limit. Exports from MISO South’s Zones 8, 9 and 10 were limited to 1.2 GW because of the continued MISO South-to-Midwest constraint from the use of SPP’s transmission.

Some stakeholders asked how MISO predicted capacity import and export limits, given that the RTO does not calculate limits more than a year in advance. Laura Rauch, MISO manager of resource adequacy coordination, responded that MISO does estimate out-year import and export limits, but added that export limits only have a “minimal” impact on survey results.

MISO predicts when new transmission will relieve constraints, and the Zone 1 transmission constraint that limits exports to 600 MW is expected to disappear by 2022, Rauch said.

Xcel Energy’s Randy Oye asked MISO to provide more detail about how it determines future export limits and transmission constraints, a subject McFarlane said would be discussed at a July 12 Resource Adequacy Subcommittee meeting addressing the zonal breakdown of survey results.

An unforeseen demand increase could affect survey results “unless balanced by policy or market forces.” He warned that results are “highly sensitive” to the same load forecasts  largely responsible for the excesses shown in the survey.

“We appreciate continued collaboration with the Organization of MISO States to provide this outlook on supply and demand in the MISO region,” CEO John Bear said. “This forward-looking view informs and enables collective actions by states and MISO members to ensure continued resource adequacy.”

PJM Monitor Rejects Fuel-Cost Policies for 11% of Units

By Rory D. Sweeney

PJM’s Independent Market Monitor said last week that it has rejected fuel-cost policies for 11% of generating units for the review period ending May 15.

The Monitor said 22 of the 479 power supplier fuel-cost policies it evaluated — less than 5% of the policies, but representing 11% of units — failed to meet its standards for being algorithmic, verifiable and systematic.

Sellers must go through the process again starting June 15, when PJM’s annual review period begins. The annual review runs through Nov. 1.

The policies are important because sellers will be penalized if they choose to offer into PJM’s markets without them.

PJM Joe Bowring fuel-cost policies
Schmitt | © RTO Insider

“Before you put an offer into Market Gateway, you need to have an approved fuel-cost policy,” PJM’s Jeff Schmitt said.

‘Ask Bob’

The initial review was the culmination of a long and often contentious coordination between the RTO and Monitor to get every market seller who must source fuel to submit a policy explaining how it developed the fuel costs included in its cost-based offers. PJM approved all offers submitted.

“We don’t actually agree with PJM that all of the policies that PJM agreed to were consistent with the Tariff,” Bowring said. There were several of the issues that caused his team to fail policies, including submission of unsupported cost adders and reliance on internal estimates.

“That’s what we refer to as ‘Ask Bob.’ So you go down the hall and ask your trader,” Bowring said, noting that the “probably 80%” of gas-fired units that used that method two years ago was “reduced dramatically.”

Some of the explanations shocked stakeholders.

“Someone for real submitted a gas hub that was not in any way, shape or form physically related to the unit that they were submitting it for and didn’t give an explanation as to why?” EnerNOC’s Katie Guerry asked. “You’re saying that someone submitted it without any sort of attempt at explaining it to you, knowing who you are?”

“Precisely,” Bowring responded. “Believe me, we understand all the nuance and subtleties about how it could be.”

PJM Joe Bowring fuel-cost policies
Borgatti | © RTO Insider

Fatigue Among Stakeholders

The ongoing fuel-cost policy requirements have created fatigue among some stakeholders. During last week’s Market Implementation Committee meeting, Gabel Associates’ Mike Borgatti reconstructed the timeline.

“By May 15, we had to get our fuel-cost policies approved to resubmit them by June 15 to maybe get them approved again by Nov. 1, right?” he asked.

Sellers are required by June 15 to submit updated policies to PJM or confirm that their current policies remain compliant. The Monitor will make its determination on policy reviews by Aug. 1, which is also the deadline for sellers to provide policies and sample emissions, variable operations and maintenance calculations to PJM. The Monitor plans to have a fuel-cost policy template incorporating hourly offers available this week, and PJM expects to have its templates ready June 30.

PJM will make its determination on polices by Nov. 1. Schmitt said that review will capture any changes to ensure the policies allow for intraday offers.

“It’s not that we’re trying to recreate work. We just want to make sure that we’re good to go going forward for the winter,” he explained.

With the implementation of FERC Order 825, sellers will be able to update offers hourly to adjust for changing market and supply conditions.

PJM Joe Bowring fuel-cost policies
Bowring | © RTO Insider

“We know this process is not easy,” said Joel Romero Luna, who is part of Bowring’s team at Monitoring Analytics. “I’ll be surprised if anyone submits by June 15 a policy that captures hourly offers, so it’s my expectation that we’ll work through it, and hopefully we’ll get something acceptable by Nov. 1.”

Online Systems

Going forward, PJM and the Monitor will be using online systems for the process. The Monitor will require all market participants to use a new section on its Member Information Reporting Application (MIRA) for reporting cost-based offer data as of June 30.

The new “Cost Offer Assumptions” module was brought online June 12 with the expectation of having all market sellers transitioned by the end of June. The Monitor uses the inputs to verify sellers’ cost-based offers. Participants will need to verify that the data is correct because “incorrect or incomplete data in MIRA may trigger an evaluation of cost-based offers for potential penalties under Schedule 2 of the Operating Agreement,” the Monitor said.

PJM will also be using “a tool” to track policies, which Schmitt said could be MIRA — although that isn’t assured.

Bowring said one of his frustrations is securing PJM’s commitment on the topic.

“My read of what PJM has been telling us is that they don’t intend to rely on MIRA, but I’m not quite sure why. It’s going to cost them at least millions of dollars in order to replace it on their side,” he said. “Until PJM tells us they’re going to rely on it, we’re not making changes to make it work more smoothly for PJM.”

CAISO Finalizes Rules for DR, Distributed Generation

By Jason Fordney

CAISO finalized a set of updates to its proposed policies on demand response and distributed generation, saying there is strong stakeholder support for the new rules to be presented to the Board of Governors in July.

The grid operator has been working on three related but distinct proposals regarding DR, non-generator resources and multiple-use applications. (See CAISO Proposes Rules for Distributed Resources, Storage.)

An incremental approach would be best as CAISO learns from the changes stemming from the policies and their influence on generation resources and grid operations, the ISO said in a draft final proposal on “Energy Storage and Distributed Energy Resources (ESDER) Phase 2.”

“The ISO will continue collaborating with stakeholders on the remaining ESDER 2 topics in a phased policy approach that is appropriate in a rapidly evolving market environment that currently does not have a clear end state,” CAISO said.

The board next month will review finalized proposals for alternative baselines, distinguishing between charging power and station power for energy storage resources, and changes to the threshold price for DR, among others.

For DR, a baseline analysis working group developed enhancements to the method whereby proxy DR resources are evaluated. The ISO has finalized the alternative baselines, which are designed to improve the accuracy of DR performance calculations. CAISO said there has been “overwhelming” support for the alternative baseline proposal.

CAISO demand response distributed generation
| CAISO

The ISO currently relies on a “10-in-10” baseline methodology that works well for many large commercial and industrial customers but not for all customer types, leading to the development of a new approach.

Using the 10-in-10 methodology, the ISO calculates a baseline by examining the 45 days prior to a trade date and finding 10 “like” days in which no DR was required. It then uses hourly average meter data to create a baseline representing a typical load profile, and the resource is paid for reducing usage below the baseline.

Under the new proposal, baselines for residential resources would be based on a four-day weather match that estimates what electricity use would have been in the absence of DR dispatch under similar weather and on similar days, using a control group of similar users.

Commercial baselines would be based on the 10-in-10 method with a 20% adjustment cap, an average of the previous five days and a control group. Baselines are adjusted using actual load data in the hours preceding a DR event to better reflect variables that might not appear in the historical data.

The stakeholder process showed that station power is a retail issue, CAISO said, and listing specific functions for wholesale and retail functions is not the best approach.

“The CAISO believes that it is prudent to simplify the definition of station power to energy for operating the electrical equipment of an energy resource subject to a retail tariff, as defined by the local regulatory authority,” CAISO said. This definition would be consistent across regulatory authorities and avoid conflicts if the California Public Utilities Commission changed its definition of station power.

The ISO is also proposing to expand the list of gas price indices available for use in the calculation of DR benefits. This allows the DR “net benefits test” to recognize Energy Imbalance Market (EIM) entities outside of the state that want to participate as DR in the CAISO market.

The policy issues discovered in the process will affect the EIM if DR or distributed energy resources are used. The EIM Governing Body will review the proposal on July 13 in its advisory role.

New England Seeks to Harmonize Markets, Renewables

By Michael Kuser

CARROLL, N.H. — New England regulators and market participants expressed optimism last week that they will find a way for wholesale markets to coexist with state energy policies, warning of dire consequences if they fail.

In a discussion Monday at the 70th Annual Symposium of the New England Conference of Public Utilities Commissioners (NECPUC), panelists discussed the proposals that have arisen from the New England Power Pool’s Integrating Markets and Public Policy Process (IMAPP).

Angela O’Connor, chair of the Massachusetts Department of Public Utilities, said IMAPP has been successful, although it has not yet resulted in a solution. At the FERC technical conference in May, she said, “New England appeared well ahead of other parts of the country in looking at solutions and trying to understand each other’s priorities.”

New England states are set to procure more than 3,600 MW of nameplate renewable generation, including Massachusetts’ requirement that its electric distribution companies solicit long-term contracts for approximately 1,200 MW of clean energy generation and 1,600 MW of offshore wind.

“The bottom line is, if New England does not find a way to harmonize markets and the requirements of state laws, it creates the risk that consumers will have to pay twice for resources — once through the regional markets, and again as the result of the requirements of the state laws,” O’Connor said. “For those who go to work every day thinking about consumers, that outcome is absolutely unacceptable and would most likely lead to the end of the competitive markets as we know them today.”

New England NEPUC Wholesale Markets Renewables
Panel left to right: Robert Stoddard, consultant; Gordon Van Welie, ISO-NE President and CEO; Mark Vannoy, Chair, Maine PUC; Angela O’Connor, Chair, Massachusetts Department of Public Utilities; and William Fowler of Sigma Consultants, Chair of NEPOOL’s IMAPP | © RTO Insider

Tom Kaslow, chair of NEPOOL’s Participants Committee, said “collaboration is the cornerstone” of the power pool, adding that he hoped New England would develop a solution rather than leaving it “to be solved by the courts.”

“We are all in this together,” he said during lunch remarks Tuesday. “We either make this market work together or we don’t succeed.”

Although it is the Participants Committee that will ultimately determine whether to support proposals brought before it, Kaslow stressed his personal commitment to the regional efforts. “I will not accept failure, at least during my tenure as chair.”

In the ‘Urgent’ Camp

Gordon van Welie, CEO ISO-NE  | © RTO Insider

ISO-NE CEO Gordon van Welie said the RTO is working overtime on the issue in order to reach agreement on a proposal that could be submitted to FERC in time for the February 2019 capacity auction.

“We definitely put ourselves in the ‘urgent’ camp,” he said. “These contracts that the states are intending to sign are probably going to happen during the next 12 months or so. In 2018, we expect resources that are winning these [requests for proposals] are going to want to enter the capacity market in the following cycle. And the qualification process for that 2019 auction will commence in 2018. And so we ideally would like to have a rule set that can deal with that prior to the start of qualification in 2018.”

Because of the RTO’s minimum offer price rule (MOPR), resources receiving a power purchase agreement may have their prices reset to a higher level in the capacity auction, with the result that they likely would not clear. “And so that has an unfortunate consequence if the states are going to go ahead and contract for these resources anyway, which is you ultimately end up overbuilding the system,” van Welie said.

But allowing subsidized resources to participate in the auction without mitigation would drive capacity prices down, he said.

“I often get a lot of eye-rolling back at the ISO when I go back to the market design people and say we need a design that will make six states happy [along with] 460 market participants and it needs to be approved by the FERC,” van Welie said. “If we did nothing and we just rely on the status quo to exist, I think we’d end up creating investor uncertainty in the market because of the litigation that will result,” he continued. “It’s a very fragile premise, an investment incentive, and it can unwind extremely quickly. So we believe it is important for us to have a solution in place that will give the marketplace confidence that we can deal with this.”

Two Leading Proposals

The NECPUC panel focused on the same two proposals that were highlighted at the FERC technical conference. (See ISO-NE Two-Tier Auction Proposal Gets FERC Airing.)

The Competitive Auctions with Subsidized Policy Resources (CASPR) proposal, developed by the RTO and Market Monitor David Patton, would provide financial incentives for existing, high-cost capacity resources to transfer their capacity obligations to subsidized new resources and permanently exit the capacity market. It would involve a two-stage, two-settlement process with a substitution auction occurring immediately after the primary auction.

New England NEPUC Wholesale Markets Renewables
Robert Stoddard | © RTO Insider

The plan would “accommodate the subsidized resources into the capacity market over time and also preserve competitive capacity pricing for unsubsidized resources,” van Welie said. “The key idea here is to coordinate the entry of subsidized capacity resources with the exit of unsubsidized resources … over time.”

A second proposal, a “Dynamic Clean Energy Market” backed by the Conservation Law Foundation, NextEra Energy Resources and Brookfield Renewable, would use forward capacity auctions to procure clean energy attributes unbundled from energy. Charles River Associates consultant Robert Stoddard briefed NECPUC on the proposal, which he helped design.

ISO-NE says CASPR falls into the “accommodation” category as a project that can be implemented relatively quickly. The Clean Energy Market is an “achieve” proposal that attempts to incorporate state policy into wholesale markets; it will take more time to evaluate to determine how it would work with the Forward Capacity Market and the MOPR, the RTO says.

‘Intriguing’ Proposals

“Both proposals are intriguing,” O’Connor said. “You’ll not be surprised that I have more questions than answers at this point.”

O’Connor said she was concerned that the RTO’s proposal would eliminate the annual 200-MW MOPR exemption for renewable resources. She noted the exemption has been supported by the six New England states and the RTO and approved by FERC despite opposition by some conventional generators. “I do question the notion of eliminating the one mechanism that gives me the certainty I need,” she said. “That said … CASPR has some tremendous advantages. We all know there are tradeoffs in these sorts of discussions.”

She suggested combining CASPR and the exemption might “increase the likelihood that CASPR will actually meet its objectives and really give the states the certainty … that we’re going to need.”

O’Connor also said she liked that the Clean Energy Market proposal “seeks to be mindful of the fact that states are responsible for executing their state laws.”

“The CLF, NextEra and Brookfield proposal, like many of the longer-term ‘achieve-style’ proposals are complex and raise questions for states about authority and other matters. They also require a significant investment of time and money to develop and implement.”

She said the New England States Committee on Electricity (NESCOE) is conducting analyses of the proposals, which will be released this fall.

IMAPP Chair William Fowler, president of Sigma Consultants, told NECPUC that 100 to 150 people attended each of the nine IMAPP meetings thus far. He said the next meeting of the group will be in September.

Stoddard and Mark Vannoy, chair of the Maine Public Utilities Commission, said integrated resource planning has moved from public utility commissions to legislatures.

“When legislators say now we want some biomass, or now we want some Massachusetts solar, they’re really getting back into integrated resource planning, so there’s tension about economic efficiency and other priorities,” Stoddard said.

Maine’s Concerns

“That’s the reality of the political economy in which we live,” agreed Vannoy. “There’s this insatiable appetite and I don’t expect that to change at the legislatures. The technology will change, but the desire to direct outcomes is not going to change. When we come to a multistate RTO, that’s where it becomes difficult because we have multiple states looking at a whole new set of complexities.”

New England NEPUC Wholesale Markets Renewables
Mark Vannoy, Chair, Maine PUC (left) and Angela O’Connor, Chair, Massachusetts Department of Public Utilities | © RTO Insider

The use of tailored mitigation strategies has been only partially successful in preventing the socialization of other states’ public policy decisions, Vannoy said. “It’s not an effective long-term approach … because it doesn’t provide regulatory certainty for market participants.”

Vannoy also expressed concern about the CLF proposal, saying incorporating incentives for clean energy into the RTO Tariff “might be a jurisdictional bridge too far.”

Environmental legislation in New England is often the result of compromises between policy goals of reducing greenhouse gasses and economic goals of creating and retaining jobs, he noted.

For example, Maine legislators last year approved spending $13.4 million in taxpayer funds to supplement the price that in-state biomass generators get from selling their power in the wholesale market, a subsidy projected to save almost 300 jobs. The legislation was coupled with the idea of “keeping people cutting wood, and is being judged on the basis of an economic result, while Vermont Tier II [distributed renewable generation] talks about connecting generation facilities of 5 MW or less to sub-transmission or distribution systems.”

Noting that Maine is the only New England state whose manufacturing load is greater than its residential demand, Vannoy said a carbon adder would make the state less competitive than other regions. Owners of large manufacturing operations such as Bath Iron Works and Texas Instruments have complained about the state’s high rates. Any rate increase would raise the risk of manufacturers of moving their operations to a Southern or Western state with cheaper power and higher carbon intensity, he said. “You’re not going to solve the carbon issue by shifting [manufacturing] to other parts of the country.”

Fuel Security

Van Welie also addressed concerns over fuel security, acknowledging that the CASPR proposal could accelerate the retirement of 6,000 MW of older, at-risk steam generators. The RTO needs about 22,000 MW to meet its winter peak, but its dependence on gas-fired generation is limited by pipeline constraints.

“When you look at what’s actually running those winter days, it’s a lot of oil, and historically we’ve had a lot of coal we used to use for winter reliability,” he said. “And so that begs the question: Where’s the energy going to come from in the future to maintain reliability in the winter?”

Van Welie said the RTO is seeking to quantify the risk through analyses that model what the system will look like in 2025 under sensitivities that consider higher and lower levels of retirements, LNG imports and renewables. (See Study: New Resources Could ‘Crowd Out’ Old in ISO-NE.)

Van Welie noted that the RTO’s out-of-market winter reliability program will end in winter 2017/18, with the region relying on its Pay-for-Performance initiative in the future.

“The question is, will the Pay-for-Performance mechanism, together with the stop-loss provisions inherent in that mechanism, be sufficient to drive the level of forward fuel arrangements that we require to get through winter with the pipeline constraints?”

Storage Technology Still Outracing RTO Metrics, Rules

By Michael Kuser

CARROLL, N.H. — Energy storage technology is still moving faster than state regulators and the markets can accommodate, speakers told the 70th Annual Symposium of the New England Conference of Public Utilities Commissioners (NECPUC) on Tuesday.

Fioravanti | © RTO Insider

“Markets are moving at the pace of entrepreneurs, while states are moving at the pace of bureaucracy,” said Richard Fioravanti of energy consultancy Exponent.

The technology is changing so fast that CAISO recently had trouble qualifying a new lithium-ion battery storage project for California’s ancillary services market.

“You may think of some complicated reason why, but it was actually very simple,” said Jason Allen, vice president of operations and power for AltaGas Services U.S. The company’s 20-MW, 80-MWh facility in Pomona, Calif., holds 12,240 lithium-ion batteries. “We were ramping so fast they couldn’t” get an accurate data reading.

Allen | © RTO Insider

CAISO needs three data points to qualify a project during an ancillary services test: a starting point, one point on the ramp portion of the curve and an end-point.

“I can go from 20-MW charge and 20-MW discharge every 100 milliseconds, or 10 times a second,” said Allen. “It took [almost] two months working with them to get that simple issue worked out. And instead of the 10,000-MW/minute ramp rate, we actually detuned the system to 100 MW/minute and qualified for 36 MW [per minute], which is physically where we’re sitting right now in the market.”

Allen emphasized that his dealings with CAISO were not adversarial. “They have worked very closely with us to resolve the issues,” he said.

Speed isn’t Everything

Kaslow | © RTO Insider

“If you can ramp to your full load in much quicker than five minutes, it’s interesting but not necessarily valued,” said the director of market design and policy at FirstLight Power Resources, Tom Kaslow, who also serves as chair of the New England Power Pool’s Participants Committee. “As a practical matter, participation in the energy market, it really matters what you can do in five minutes — and if you can do it consistently, when the system operator needs it.”

There is a disconnect between the performance capability of new technologies and the market need for that level of performance, Kaslow said. “As a practical matter, while some of these new technologies bring a really interesting résumé to the table, their capabilities may actually exceed their ability to be valued, at least in the wholesale ISO market.”

Bartlett | © RTO Insider

Kaslow said battery storage can also present a challenge to RTOs’ operation of regulation markets. “I was on a panel last week where [PJM officials] were indicating that they [were] having problems, because achieving the neutral state of charge while on regulation is actually yielding periods where the charging is working in the opposite direction of their actual regulation needs in that particular interval. So there are things that need to be dealt with in respect to that much smaller market.”

He explained afterward that PJM had implemented a solution in January: PJM is placing a limit on the charging function when the regulating capability is needed to manage the area control error in a direction opposite to charging. Kaslow said it is unclear whether New England will face a similar problem.

Moderator Ned Bartlett, Massachusetts undersecretary of energy and environmental affairs, said storage is a small portion of the Massachusetts electric supply compared to other commodity supply chains. Storage of “food, water, gasoline, even oil [and] natural gas distillates [is] often close to 10%” of the daily consumption of each of these commodities, he said. “In Massachusetts right now … approximately 1% of our electricity used on a daily basis [is] in a storage capacity.”

Cheap and Cheaper

Jenkins | © RTO Insider

Jesse Jenkins, a Ph.D. candidate at the Massachusetts Institute of Technology, said his research indicates energy storage costs must fall 60 to 85% to be competitive with gas peaking plants and that the value of storage drops with its volume.

“The first gigawatt of storage that you might stick in the New England system has a very high value. It displaces our most costly resources that are used most infrequently,” Jenkins said. “And as we deploy more and more storage, the challenge of displacing additional capacity increases and the marginal value steadily falls.”

But assessing the total value of storage means looking at the long-term value of the assets, according to Allen, who explained the economics of the Pomona storage facility.

“Yes, the up-front cost is more, but you look at the operating costs,” Allen said. “Right now it’s about $5/kWh on an ongoing [operations and maintenance] basis. There’s no fuel, very little maintenance. Our technicians who used to [work] 24/7, for now they’re on day shift to do minor maintenance. … You also need to consider what it’s doing to your other assets. I’ve got a couple [cogeneration] units that I use right now that are dispatched for about 300 starts a year. We are just destroying those units; maintenance has gone through the roof. Getting the storage in place can really help dampen those curves and control our costs.”

More Interest Pushes Grid and Regulators

energy storage necpuc
Parent | © RTO Insider

Christopher Parent, ISO-NE director of market development, said the RTO is seeing increasing interest by storage developers. “The market is maybe starting to support [storage], and people are starting to look out at what the future is and the revenue opportunities and that in certain cases, now it is economic,” he said.

The message for policymakers? “For most storage stakeholders, what they really want to see is just the markets opening up, access opening up,” Fioravanti said. “Don’t try to predict where the business cases are going, where the technologies are going. Let the markets drive that.”

Why is storage complicated? he asked. Why all the questions when there is increasing deployment, with about 2.6 GW predicted to come online by 2022?

“The reason is because … it can go everywhere and do many things,” Fioravanti said. “This becomes problematic when people look to make policy off it because … we have it on the transmission side, it works on the distribution side, we’re putting it on the customer side. All of these create issues.”

Electric Utilities and More

The Pomona storage site, formerly a paper mill, illustrates the fast changes taking place in the storage business, according to Allen. Gas-fired boilers served the paper mill, he said. “In the early ‘80s they put in a cogen unit; they innovated lower cost electric. Paper mill went away, that got torn down; the cogen unit went into the deregulated California market. We now built this battery storage facility inside the warehouse that was there. The cogen unit is still there, still in the market [but] hasn’t run for a year.”

The storage facility won a contract in the request for proposals issued in mid-2016 to counter the potential loss of the Aliso Canyon storage facility.

“The big concern there was the potential loss of gas, loss of [natural gas supply for] peaking units,” Allen said. “The mandate of that arm of the [power purchase agreement] was that we could provide four hours of [reliability assurance] service with the battery, hence the 80-MWh structure. We were awarded this in June, actually started construction in early August and it went online on Dec. 31, 2016. [Southern California Edison] said it was the fastest generating asset they’ve ever had go from groundbreaking to in-service.”

energy storage necpuc
Panelists: left to right: Tom Kaslow, Director, Market Design & Policy, FirstLight Power Resources; Christopher Parent, ISO-NE Director of Market Development; Jason Allen, VP of Operations and Power for AltaGas Services U.S.; Richard Fioravanti of energy consultancy Exponent; Jesse Jenkins, PhD candidate, Massachusetts Institute of Technology; and moderator Ned Bartlett, Undersecretary of Energy and Environmental Affairs, Massachusetts Executive Office of Energy and Environmental Affairs | © RTO Insider

Fioravanti reminded the audience of the ubiquity of batteries, saying the industry now manufactures about 5 billion a year of the type that most people have in their laptops.

“That’s going to go up, probably double, when the [Tesla] Gigafactory fully comes online,” Fioravanti said. “Of all the batteries out there — how [storage] has penetrated into our vehicle, transportation world, our aircraft world, our shipping world and all of our everyday devices — to think that we’re going to draw the line at the utility world and say it’s going to stop here, I think can be almost a little silly.”

PJM OC Briefs

VALLEY FORGE, Pa. — PJM will release a request for proposals next January for new black start units intended to begin operation in 2020.

PJM Operating Committee black tie
Schweizer | © RTO Insider

PJM’s David Schweizer said the process is the second iteration of a five-year cycle that began in 2013. (See “New Black Start Units Will Have New Annual Revenue Requirements,” PJM Markets and Reliability Committee Briefs.)

“The purpose of the RTO-wide black start RFP is to look at the system every five years and essentially reoptimize the effectiveness of the cranking paths,” Schweizer said. “What really does drive the amount of black start megawatts and units needed is the critical load amount and the need to serve critical load across cranking paths.”

Existing black start units are expected to remain in service and are not required to respond to the RFP, Schweizer said. However, an approved black start unit could be issued a one-year termination notice if system changes mean that it is no longer serving critical load. The critical-load analysis is being done this year, he said, so “we should have a good idea by the time that RFP is issued what the critical load will be.”

“Even if we don’t have a shortage, the RFP gives us an opportunity to reoptimize the process,” he said.

Seiler Takes the Reins of the OC

PJM Operating Committee black tie
Seiler | © RTO Insider

Ken Seiler, PJM’s executive director of system operations, has assumed the chairmanship of the Operating Committee as of June. He succeeds Mike Bryson, who remains vice president of operations.

Seiler brings 17 years of PJM experience to the position. Prior to PJM, he worked at General Public Utilities for 14 years as a field engineer building substations and transmission lines before moving into other positions, such as managing transmission engineering, construction management and distribution system operations.

Seiler expects the committee to focus on “the evolving resource mix and its subsequent impact on how we operate the system today and in the future, along with the resilience of the power grid.”

Stakeholders Challenge PJM Decisions on Reserve-Shortage Identification

Ciabattoni | © RTO Insider

PJM’s Joe Ciabattoni said PJM’s new shortage pricing algorithm hasn’t identified any shortages, despite complaints from stakeholders that data available online appear to show shortages. (See “Shortage Rule Takes Effect amid FERC Silence,” PJM Market Implementation Committee Briefs.)

Citigroup Energy’s Barry Trayers asked what it takes to create a shortage case.

“You’d look at all your resources, all your ramp rates, and if you’re short of your reserve requires, you’d trigger shortage,” Ciabattoni said.

Tom Hyzinski of GT Power Group asked if there have been shortage cases that system operators haven’t approved, or if there just have not been any shortages yet.

Dispatchers have to “sanity-check” cases and approve them, Ciabattoni said, but situations haven’t warranted a shortage case.

“The cases are the cases,” he said. Dispatchers “won’t go in and play with the numbers in cases.”

However, Calpine’s David “Scarp” Scarpignato argued that PJM’s publicly available data show that several situations have shortage pricing under its new rules related to FERC Order 825. PJM staff argued that they don’t have to implement shortage pricing if the units already dispatched are ramping up to meet the increased reserve requirement, but Scarp said the wording of the order clearly states that the RTO must implement shortage pricing as the units ramp up.

Staff said part of the issue is that units aren’t following their dispatch signals, but Scarp said that’s no justification for not declaring a shortage.

Order 825 “says quite the opposite,” he said. “It says: ‘regardless of cause.’ … It’s black and white.”

Staff suggested that an operator might purposefully disobey the signals to induce shortage pricing. Scarp also dismissed that, saying such action is so egregious that the actor would “probably end up in FERC jail.”

Seiler attempted to quell the argument by saying that it’s a new procedure that will likely require ongoing adjustments.

“We’re not going to settle it here,” he said.

“There’s nothing to settle,” Scarp shot back. He asked to convene a discussion between attorneys for each side.

Staff agreed to develop a report of security constrained economic dispatch cases that were not approved by dispatchers but would have resulted in shortage pricing.

OC to Add Report on DER

Bencheck | © RTO Insider

PJM plans to produce a monthly report on its progress developing distributed energy resource rules, PJM staff said.

FirstEnergy’s Jim Benchek urged all stakeholders involved with DER to contribute to the process so they can “know what’s coming and be able to impact what’s coming.”

“When you’re talking about DER, it’s really who the DER is connected to,” he said. “If you have the potential to have DERs connected to your system, get engaged.”

PJM to Expand Data Capabilities, Discontinue Flat-File Support

Zadlo | © RTO Insider

The capabilities of Data Miner 2 are being expanded, PJM’s Thomas Zadlo explained, which means companies have a year to upgrade their internal systems before the flat files many member systems rely upon disappear.

“Data Miner 2 will become the central source for PJM public data,” Zadlo said.

The expanded database will go live in August and flat file postings will be retired in August 2018. Zadlo urged all stakeholders to send representatives to PJM’s Tech Change Forum to stay informed and be prepared.

Bryson Leads on Next Steps for Fuel Resiliency

Bryson | © RTO Insider

PJM’s Bryson laid out a roadmap through 2018 to increase grid resiliency, focusing on short-term risks — such as assuring black start service — and gradually extending the perspective to discuss long-term goals such as enhanced dispatching and strategic islanding for critical infrastructure.

The roadmap comes a little more than a month after Bryson led PJM’s publicity campaign on its recently released resiliency whitepaper. (See PJM: Increased Gas Won’t Hurt Reliability, Too Much Solar Will.)

The paper found no point at which the percentage of gas-fired units caused reliability threats, but that a capacity mix of more than 20% of solar would threaten reliability. It was narrowly focused and purposely didn’t address other topics, such as environmental issues or whether natural gas infrastructure could keep pace with the high percentage of gas-fired generators PJM’s analysis said the fleet could handle.

– Rory D. Sweeney

Regulators, Utilities See New Roles in Shifting Industry

By Michael Kuser

CARROLL, N.H. — Residential customers installing behind-the-meter generation are just the latest factor stretching electric power utilities far beyond their original role as vertically integrated monopolies, speakers said Tuesday at the 70th Annual Symposium of the New England Conference of Public Utilities Commissioners (NECPUC).

“The most intermittent resource could be the customer,” said Barbara Tyran of the Electric Power Research Institute, part of a panel that explored the future of regulation and utilities by looking at parallels between the telecom and electric sectors.

necpuc behind-the-meter generation
Janet Besser, Northeast Clean Energy Council (left) and Kathryn Bailey, Commissioner, New Hampshire Public Utilities Commission | © RTO Insider

Tyran said the electric industry’s data analytics are not sufficient for the changes coming. “It’s almost like we’re on a freeway driving 55 mph, but we’re only allowed to open our eyes once every 15 seconds,” she said. “That’s how much situational awareness is occurring. We need sensors throughout that system; we need to understand what that data is generating and what the value of it is and how to use it to improve the system performance, enhance the customer experience and also create new efficiencies.”

“Over the past 30 years, we as a region have shifted away from vertically integrated, economically regulated utilities, the ones that were envisioned by the foundational regulatory standards of just and reasonable rates for monopolistic utilities,” said New Hampshire Public Utilities Commissioner Kathryn Bailey, who moderated the panel. “However, I think in New England, we haven’t gone as far with the transformation of the electric industry as we have with the telecom industry.”

Janet Gail Besser, executive vice president of the Northeast Clean Energy Council and former chair of the Massachusetts Department of Public Utilities, said customer adoption of solar and other distributed technologies is the latest step in a process that began with competition in the generation sector following the 1978 Public Utility Regulatory Policies Act and grew with restructuring in the 1990s and the adoption of energy efficiency. She also pointed out that further changes are coming with the electrification of transportation and buildings.

Restructuring and Social Policy

One cause of the restructuring of the electric industry was the disparity between retail and the wholesale prices, according to consultant Louise McCarren, former chair of the Vermont Public Service Board and former commissioner of the state Department of Public Service.

“State regulators thought they could load anything onto” retail prices, McCarren said. “Social programs, conservation programs, you name it. And that price went up, way above the wholesale price.”

Nonetheless, McCarren said that her experience in Vermont has shown that regulatory frameworks can provide valuable public benefits, such as increased rural access to broadband service.

NECPUC behind-the-meter generation
Lorraine Akiba, Commissioner, Hawaii PUC | © RTO Insider

Hawaii Public Utilities Commissioner Lorraine Akiba said that “in the distributed energy resources paradigm shift of the future, we’ll actually be able to [support rural populations] more cost effectively because microgrids, and putting generation closer to the load saves all that transmission expense. In our jurisdiction, we require you to at least look at non-transmission alternatives.”

NECPUC Behind-the-meter generation
ISO-NE Board Member Kathleen Abernathy | © RTO Insider

Regulators need not only to look at what markets can do, but also at what they can’t do, such as addressing social policy needs, said ISO-NE Director Kathleen Abernathy, a former Federal Communications Commissioner. “But don’t decide not to do something because it’s too expensive for low-income customers … you can fix that later or provide the necessary supports,” she said.

Competition forces companies to do things that might not be in their own economic interest but that benefit the public, said Abernathy, who cited unlimited cellphone minutes as an example. “Way back when in the wireless world, we used to pay per call,” she said. “It was only when the FCC allocated additional wireless licenses that all of a sudden you got unlimited minutes. That never would have been mandated by regulators; that happened in the market place. So embrace this kind of disruption and go with the flow on it.”

As with the telecom industry, technology preceded regulation, Besser said, giving customers an alternative to using incumbents’ landline phones. One question is whether some entity other than electric distribution companies will find ways to provide customer and system data to customers, third parties and the EDCs themselves, she said.

Electric Utilities Need to Add Value

“If you shift the risk away from the customer and to the utility, in theory you should shift the reward structure,” McCarren said. “And that is really hard to do, because when the wheels come off you still have to provide adequate and reliable services to all your citizens.”

In 1970s Vermont, hot water heaters were radio controlled in an effort to smooth the load curve. “The only problem was when you had an outage and you had to go reset them. But that was load control,” McCarren said. “Now the customer can do that, so if the utility wants to stay relevant, they have to add value.

“It’s Darwinian. If [companies] can’t change, they’re going to be roadkill,” she continued. “Is it your job as a regulator to create incentives or disincentives that encourage them to participate, or is [it] their job to figure it out?”

Akiba and others highlighted the importance of utilities’ ability to use big data analytics to operate the energy networks of the future.

“I feel sometimes we’re like the Oracle, that very sage character” in the 1999 movie “The Matrix,” Akiba said. “She has to make correct decisions, and she gives cryptic advice to Neo as he navigates the Matrix. … But we do have to keep our eye on the future trends and actions transforming the energy industry.”

NECPUC behind-the-meter generation
Regulation Innovation Panel left to right: Barbara Tyran, Electric Power Research Institute; Louise McCarren, consultant; Lorraine Akiba, Commissioner, Hawaii Public Utilities Commission; Kathleen Abernathy, Board Member, ISO-NE; Janet Besser, Northeast Clean Energy Council; and moderator Kathryn Bailey, Commissioner, New Hampshire Public Utilities Commission | © RTO Insider

Abernathy said that “sometimes a corporation’s addiction to a framework that guarantees certain revenue flows actually prohibits the kind of risk-taking that is essential for survival. … There’s no question that traditional regulatory frameworks actually prevent creativity and innovation, and people who are creative and innovative, they leave those companies for other ones who are doing more interesting work.”

McCarren said the regulatory solution “isn’t just one-size-fits-all, but going back to consumerization, localized solutions and keeping very flexible. … A very simple but effective rate design, that may or not require smart meters, can get you really far. The issue now is will we have to increase the charge to cover this fixed cost. … As long as it’s adequate, efficient and fair, it’ll work.”