November 1, 2024

SPP Seeks Feedback on Transmission Studies at Engineering Summit

By Tom Kleckner

LITTLE ROCK, Ark. — SPP’s engineering staff updated members on the RTO’s current regional and interregional transmission planning studies during an engineering summit last week.

spp engineering summit transmission studies
Freitas © RTO Insider

In return, the engineers asked for stakeholders’ input.

“It was very important that we are able to get in the feedback at the front end of the process,” SPP Director of Transmission Planning Antoine Lucas told members, who spent much of the day delving deep into the 2017 Integrated Transmission Planning’s 10-Year Assessment (ITP10). “Most of you will be pleased with” the process.

“As soon as you guys can provide feedback, please do it,” requested SPP’s Juliano Freitas, manager of economic planning.

ITP10

SPP plans to present its final 2017 ITP10 to the Markets and Operations Policy Committee in December.

Staff is using three futures for the study: regional compliance with EPA’s Clean Power Plan; state-level CPP compliance; and a reference case that assumes the CPP will not be implemented.

The two CPP studies will eventually be combined into a single portfolio, with the reference case also moving forward for additional benefit calculations, using multiple model years and costs derived from the RTO’s annual transmission revenue requirement formulas.

Transmission projects would be deemed to satisfy economic needs by meeting up to 25 constraints with greater than $50,000 in annual congestion costs.

SPP will also produce a near-term reliability assessment early next year. Staff is currently working on a needs assessment but doesn’t expect to produce a final portfolio recommendation and report until March.

Interregional Studies

SPP engineering summit transmission studies
SPP Senior Engineer Kirk Hall presents at the Engineering Summit. © RTO Insider

Adam Bell, SPP’s interregional coordinator, updated members on the status of SPP’s work with three of its interregional partners: MISO, Associated Electric Cooperatives Inc. (AECI) and Southeastern Regional Transmission Planning (SERTP).

SPP and MISO have both voted to pursue a joint study this year, using their regional planning as a starting point. Bell told members they would be able to propose solutions for the final set of needs, currently being developed.

spp engineering summit transmission studies
Bell © RTO Insider

The RTOs are scheduled to meet again Sept. 7. “We want to get this scope approved so we can get this study done,” Bell said.

SPP and AECI are determining the scope of a study of five target areas: potential overloads and voltage issues in northeast Oklahoma and Brookline, Kan.; potential low voltage issues in mid-Missouri and east of Kansas City; and potential upgrades in Wheaton, Kan. They expect to produce a final report and recommendations in January.

Bell said SPP had its annual meeting with SERTP representatives in June. The staffs reviewed their regional plans to “see if anything made sense,” Bell said, adding later, “it’s more coordination than joint planning or joint study.”

“There could be potential here as we move forward,” he said.

Upper Peninsula Ratepayers to Seek FERC Probe of Billing Fraud

By Amanda Durish Cook

A group of Upper Peninsula electric users plans to ask FERC to investigate Wisconsin Electric Power Co. for allegedly falsifying records to increase its revenues under the Presque Isle power plant system support resource agreement.

“The numbers presented by MISO and WEPCo going back to 2014 were inflated, and part of that was falsifying documents,” Todd Chapman, spokesman for Cloverland Electric Cooperative, said Monday.

Chapman said that the organization expects to file a brief later this week or next week detailing the allegations, which were included in Administrative Law Judge Michael Haubner’s initial decision last month saying WEPCo had overcharged ratepayers by $17 million over the SSR (ER14-1242-006, et al.).

Last week, meanwhile, FERC approved nine out of ten SSR process revisions proposed by MISO.

Consulting Contract Allegedly Backdated

Haubner said WEPCo changed the dates on a $1.4 million consulting services invoice relating to upgrades for EPA’s Mercury and Air Toxics Standards at the 61-year-old coal plant. (See ATC Plan Could Eliminate White Pine SSR; Refunds Coming on Presque Isle?)

“Evidence shows that the invoice for services was originally executed and sent to WEPCo on Oct. 9, 2014. Then, a WEPCo employee requested the consultant resubmit the invoice with a later date, Oct. 16, 2014,” Haubner said.

ferc, miso, presque isle
Presque Isle Power Plant Source: WEPCo

According to Haubner, the invoice dates were changed after WEPCo learned that a new version of its SSR agreement with MISO would cover costs incurred from MATS upgrades under a revised fixed-cost component. MATS upgrades were ineligible for recovery under the previous SSR agreement.

“This evidence demonstrates that WEPCo changed the date on the consulting services invoice to one day after the replacement SSR agreement became effective. It appears this manipulation was done by WEPCo to include these costs under the later agreement,” Haubner concluded.

WEPCo issued a statement insisting the company was not seeking to recover MATS compliance costs through the SSR payments. “Beyond that, the company will not comment on cases currently being litigated. The issues that are in contention in the initial ALJ decision, including this issue, will be addressed by our future filings in this case,” it said.

Chapman said the $1.4 million worth of back-dated invoices was “carved out” in the judge’s estimated refunds and contributed to Cloverland lowering its expected amount owed to MISO for the Presque Isle SSR to “the neighborhood of $9.8 million,” instead of the original $11.7 million, for 2014.

Chapman said Cloverland is waiting on a larger decision from FERC in order to verify the $9.8 million figure.

Cloverland will be joined in its request for an investigation by mining company Cliffs Natural Resources, Upper Peninsula Power Co., paper producer Verso Corp., the City of Mackinac Island and the Sault Ste. Marie Tribe of Chippewa Indians, Chapman said.

If FERC decides to investigate, a probe from its Office of Enforcement could take years, Chapman said.

“None of that is going to wipe it all out and completely dismiss the amount we owe,” Chapman said, adding that the outcome of a possible investigation “probably” wouldn’t further reduce the amount owed. “If FERC agrees that it was fraudulent, then we’re back to the same lower number,” he said.

MISO Confused by Refund

Meanwhile, MISO complained in an Aug. 16 brief that Haubner’s ruling was inconsistent and confusing.

MISO said Haubner used two “inconsistent” methods to determine variable compensation under the two separate Presque Isle SSR agreements. The RTO also said the judge at times mixed up fixed compensation and clawback values. Finally, MISO said Haubner did not outline a procedure for calculating the total amount owed to ratepayers.

“MISO is unable to determine the amount of refund that should be made by the Wisconsin Electric Power Co.,” the RTO wrote to FERC. It also said it “hoped for an initial decision that would contain internally consistent findings that MISO could implement in its role as Tariff administrator.”

FERC Accepts Changes to MISO SSR Process

In a related order on Aug. 19 (ER16-1758), FERC accepted nine out of ten SSR process revisions proposed by MISO, which affect the execution, filing and compensation of SSR units.

MISO proposed that while it would still file SSR agreement terms and conditions, SSR owners in “all cases” would make separate filings for compensation. MISO previously only had SSR members resort to a FERC filing when it couldn’t agree on compensation.

FERC agreed. “Given that many recent SSR filings have set compensation issues for settlement and hearing procedures, the advantage of requiring that MISO and the market participant undergo preliminary compensation negotiations prior to executing an SSR agreement is limited and outweighed by the administrative burden of conducting such negotiations,” the commission said.

The Michigan Public Service Commission supported MISO’s proposal, saying it would allow customers and regulators to offer input before MISO and SSR owners reach an agreement.

Chapman said it was better that MISO not take generators’ cost numbers at face value. “I think MISO will learn their lesson, but not before this happens again,” he said, referring to future coal plant retirements.

Inappropriate Limit

The order also allows MISO to enforce a 30-day notice period before retirement on forced outage units and units that are pseudo-tied out of the RTO. Pseudo-tied units now also have a 36-month maximum suspension period in a five-year time frame before their interconnection service is pulled. Black start-designated units must now fill out an Attachment Y notice, which triggers a reliability study, before retiring. Finally, all retirements can be made public by MISO once their retirement date passes.

However, FERC rejected MISO’s proposal that a return to service on a retired former SSR would be defined at the point that the unit re-enters the interconnection queue, saying it would “inappropriately limit” situations where a generator would have to refund certain costs. FERC called MISO’s existing Tariff language on refunds “appropriately broad.”

Cliffs-WEC Deal

Chapman blames a Michigan exemption that allows mining companies to choose electricity suppliers for the creation of the disputed SSR. Mining company Cliffs Natural Resources took advantage of the exemption, leaving Presque Isle for an estimated $20 million to $30 million annual savings.

“Nobody thought anything of the exemption at first. At the time, it protected the mines, and Cliffs is the largest employer in Marquette,” he said.

Cloverland now has a new concern, spawned by Cliffs’ announcement last week that it has entered a 20-year power purchase agreement with WEC Energy Group to power its Tilden mine. The contract would result in the construction of two natural gas-fired plants on the Upper Peninsula totaling 170 MW.

He said Upper Peninsula ratepayers would be on the hook if Cliffs should go out of business, as the Upper Peninsula’s transmission network isn’t able to reliably export power to Wisconsin and the Lower Peninsula.

Cliffs CEO Lourenco Goncalves said the new generators are a “strategic energy solution for the Upper Peninsula [that] optimizes affordability and improves reliability for all ratepayers for decades to come.”

The $255 million plan will need to be approved by the Michigan PSC.

Marketers Seek Rehearing on NY Low-Income Moratorium

By William Opalka

The National Energy Marketers Association has asked for a rehearing of New York regulators’ moratorium on the enrollment of low-income customers by energy service companies (98-M-0667).

The New York Public Service Commission last month imposed the moratorium because stakeholders were unable to reach a consensus on reforms. (See NYPSC Declares Moratorium on Low-Income Sign-ups.)

In a petition filed Aug. 15, NEM said regulators violated stakeholders’ due process rights by adopting the moratorium without notice, violated state law and made other procedural errors.

State law “does not grant the commission authority to institute a moratorium on ESCO service to low-income customers,” the petition states.

NEM cites the same procedural mistakes the commission made in its February order attempting to revamp ESCO practices for customers not receiving public assistance. A state Supreme Court justice ruled that the PSC failed to give adequate notice. (See New York ESCO Order Vacated by Court.)

“The July order erroneously concludes that low-income consumers should not be permitted to make their own energy purchasing decisions,” the petition says, calling the PSC’s action “unfounded and [a] paternalistic view of low-income consumers’” shopping decisions.

The petition also asks for a clarification of the order, saying it fails to address how and under what circumstances the moratorium would be lifted.

“Despite the intention expressed that the moratorium be temporary in nature, the order itself provides no detail of the circumstances or timeline under which it will be lifted. NEM recognizes that the resolution of other related proceedings potentially impacts the duration of any moratorium,” NEM wrote. “However, ESCOs should be provided with some guidance and regulatory certainty about the potential duration of the moratorium in order to properly inform their decisions about serving New York state customers.”

Panelists Envision Low-Carbon Future at MISO Symposium

By Amanda Durish Cook

INDIANAPOLIS — MISO used its first-ever Market Symposium last week to ask industry leaders how a low-carbon environment will influence the electricity market.

Although the discussions produced few specific suggestions on what new rules should be proposed, there was wide agreement that the markets need to become more flexible to accommodate the increase in renewables and distributed resources. The Department of Energy’s Advanced Research Projects Agency-Energy (ARPA-E) partnered with the RTO in the sold-out event Aug. 18-19.

Curran © RTO Insider miso low carbon future
Curran © RTO Insider

“We’re basically heading off to a situation where there’s no trail, and we’re going to have to cut through the wilderness for a while,” said Michael J. Curran, chairman of the Markets Committee of the Board of Directors. “This [symposium] is a coming together of the community where we’re going to have to share ideas. … I look forward to cutting the trail together.”

“We have people saying the system cannot do this; the system was not designed for this,” said CEO John Bear, commenting on incorporating distributed resources. “That reminds me of what people used to say about wind. … We can solve these problems. We can look at what we’re doing in the control room.”

MISO’s wind generation has grown exponentially since 2005, when it totaled only 500 MW. A decade-plus later, the RTO has 15 GW of wind.

Gas the ‘New Coal’

Tom Doughty, vice president of customer and state affairs at CAISO, spoke about the challenge of meeting California’s mandate of 50% renewables by 2030.

Doughty said wind and solar will be a “massive element” by then. He also said natural gas has become the “new coal” in California.

“We’re in a race now to meet the mandates and accomplish our state’s objectives,” he said. “But that race must be run carefully to avoid placing additional costs on consumers.”

miso low carbon future
Left to right: Tom Doughty, CAISO; Scott Harvey, FTI Consulting; Paul Mitchell, Energy Systems Network; Cathy Woollums, Berkshire Hathaway Energy © RTO Insider

Eric Schubert, regulatory affairs advisor at BP Energy, said the growing role of natural gas will require investments in firm transport, storage and long-term contracts.

With gas-fired generation having to manage peak loads in the morning before the sun rises high and in the evening before the wind picks up, measures are needed to optimize the use of intermittent resources throughout the day, said Scott Harvey of FTI Consulting.

But time-of-use pricing is not the answer, said Cathy Woollums, senior vice president and chief environmental counsel at Berkshire Hathaway Energy. “How are you going to tell someone not to do their laundry at 10 in the morning or they’re going to pay more?” she said. “We can’t switch overnight to looking at something brand new.”

Paul Mitchell, CEO of Energy Systems Network, said the transition could be eased by Internet-connected devices, which can receive signals to temper energy use when demand is high.

Roles for Energy Storage

Mitchell also touted the “endless” applications of energy storage, which can be integrated into the grid “at all different layers and levels.”

“The markets are going to have to realize that energy storage is not a renewable-based asset like wind and solar,” Mitchell said.

Panel2-(RTO-Insider)
Left to right: moderator Melissa Seymour, MISO; Michael Milligan, NREL; Eric Schubert, BP Energy; Richard Tabors, MIT © RTO Insider

Richard Tabors, co-director of the Massachusetts Institute of Technology’s Utility of the Future Project, said markets will have to be value-driven instead of cost-driven, so that 200 MW in storage will be compensated based on the energy price when it’s consumed. “We’re not quite there yet,” he said.

“I think the trick for storage and renewables is to have really good forecasting in place so you know when to fill the storage and empty the storage,” said Michael Milligan, principal researcher at the National Renewable Energy Laboratory.

Milligan said for wind and solar to be integrated, systems have to be geographically large with very responsive markets — a recognition that has resulted in CAISO expanding beyond state borders with its Energy Imbalance Market.

“It’s my sumo wrestler theory of wind and solar integration,” Milligan said. “You have to be big and you have to be fast.”

‘Unguided Missile’

miso low carbon future
Bear © RTO Insider

Doughty said consumer participation in the grid will continue to rise, and CAISO has responded by rolling out two products allowing consumers to enter their solar generation into the market through aggregators.

“On our … 70,000-MW grid, we have 5,000 MW of solar that’s invisible to us and undispatchable,” he said. “We are very, very much bullish about involving the consumer. Because if we don’t involve them, they can become an unguided missile.

“My electric bill last month was $800,” Doughty continued. “And I don’t have a large home. In California, [highest electric rates are more than] $0.40/kWh. There’s a huge opening for solar. We have a tremendous responsibility to inform customers about their ability to participate in markets.”

BP’s Schubert said as more wind and solar are added, reserves need to be priced efficiently, or else MISO could find itself in a “binary position” where the marginal cost of wind will be $0/MWh then jump to an offer cap once the breeze stops.

“The beauty of pricing is if you price it right, it will all fall into place because everyone has an incentive,” Schubert said.

Research and Development

Sun © RTO Insider miso low carbon future
Sun © RTO Insider

Several speakers talked about the need to increase research and development.

“The RTO creates value,” said David Sun, chief scientist at The Glarus Group. “It’s an economic platform that allows us to do things we previously could not. But that platform needs to change. It will do well in the future,” but “today we’re not doing enough innovative research. We’re doing embarrassingly little.”

Tim Heidel, program director at ARPA-E, called for a “no-regrets” approach to research and development, in which even failures are celebrated.

“One of the tough technical questions is how do we do that aggregation while respecting the constraints of the market. I think we’ll solve that and I think it’ll work, but there’s a possibility that we uncover another showstopper,” Heidel said. He predicted optimization algorithms will be a large part of distributed resource research.

Terry Oliver, chief technology innovation officer at Bonneville Power Administration, said he does not recommend MISO conduct basic research, but it could use its members to collaborate on narrower research topics. He also said the RTO should “free the data” to researchers and pointed out other sources of harvestable data, such as Nest thermostats.

Panel3-(RTO-Insider) miso low carbon future
Left to right: Terry Oliver, BPA; Tim Heidel, ARPA-E; Joe Schatz, Southern Company; moderator Jeff Bladen, MISO © RTO Insider

Mitchell said the regulatory structure needs to expand to reflect the electrification of transportation and the role of microgrids and distributed resources. “Industry needs to be defined far more broadly than just RTOs and utilities,” he said.

Heidel said the scale of change in the electric system is going to be “huge,” pointing out how quickly the industry grew after Thomas Edison built the first central power plant on New York City’s Pearl Street in 1882.

“We’re going through that magnitude of change again,” he said. “Climate change is going to accelerate the rate of this change, and we’re going to be playing catch up for years. We’re going to get our feet wet in R&D again.”

11 Developers Vie for MISO Duff-Coleman Project

By Amanda Durish Cook

Eleven respondents have submitted proposals for MISO’s Duff-Coleman transmission project, the RTO’s first competitive project under FERC Order 1000.

MISO said Friday that all 11 proposals were judged complete.

“Now that we have finalized our review of the proposals for purposes of completeness, we will begin evaluating the proposals based on the criteria set forth in the MISO Tariff and our Business Practices Manual,” said Priti Patel, MISO North regional executive and executive director of the RTO’s competitive transmission administration.

miso duff-coleman project

MISO identified the developers as:

  • Ameren Transmission Company of Illinois and PPL TransLink;
  • Duke-American Transmission Co.;
  • Edison Transmission;
  • GridAmerica Holdings;
  • ITC Midcontinent Development;
  • Midcontinent MCN, with the Missouri Joint Municipal Electric Utility Commission;
  • NextEra Energy Transmission Midwest;
  • Republic Transmission, a subsidiary of LS Power Transmission, with Big Rivers Electric;
  • Vectren Energy Delivery of Indiana, a unit of Southern Indiana Gas and Electric, and Public Service Enterprise Group;
  • Transource Energy, a partnership between American Electric Power and Great Plains Energy, with subsidiaries Transource Indiana and Transource Kentucky; and
  • Xcel Energy Transmission Development.

The request for proposals window on the project opened in January and closed early last month. (See MISO Duff-Coleman RFP Deadline Passes; RTO Reviewing Bids.) The $67.4 million project was approved by the MISO Board of Directors as part of the 2015 MISO Transmission Expansion Plan.

MISO expects to announce its selection no later than Dec. 30. Construction on the pair of substations and the 28.5-mile 345-kV connecting line in Southern Indiana and Western Kentucky is expected to last through 2020, with the line in service by the beginning of 2021.

PJM’s Grid 20/20 Ponders Mixing Public Policy, Competitive Markets

By Suzanne Herel

VALLEY FORGE, Pa. — After PJM’s Craig Glazer started with the food analogies, speakers at Thursday’s Grid 20/20 symposium couldn’t resist serving up a smorgasbord of edible metaphors.

Glazer, vice president of federal government policy, kicked off the conference, “Focus on Public Policy Goals and Market Efficiency,” talking about apples as a stand-in for power. To the laughter of the overflow audience, a slide depicted a grocery store display pricing the fruit to reflect subsidies (49 cents), subject to partial FRR adjustments (58 cents), MOPR’D per PJM rules (60 cents) and cleansed of all subsidies (65 cents).

apples-(PJM) public policy competitive markets
PJM’s Craig Glazer likened the pricing of apples to MW at Grid 20/20. Image source: PJM

Currently, the recipe for competitive markets doesn’t call for carbon reduction, the preservation of jobs and tax bases, or the retention of uneconomic plants, he said. But these are among the public policy goals that some states are looking to achieve.

“A state could say, ‘Just add my one little ingredient,’” Glazer said. “The result isn’t just the most efficient solution for state A. Everybody gets it. How do we not force it on states B and C, who haven’t authorized us to put that ingredient into the blender?”

Symposium Follows PJM Study

The topic for the confab grew out of a controversial white paper PJM published in May, “Resource Investment in Competitive Markets.” (See PJM Study Defends Markets, Warns State Policies can Harm Competition.)

Penned amid efforts by money-losing coal-fired generators in Ohio and nuclear generators in Illinois to win state-backed subsidies, the report concluded that PJM’s markets efficiently manage the entry and exit of capacity resources, but they could be hamstrung by policies to protect social, economic or political interests.

Subsidized-Supply-Offers-and-Equivalent-Demand-Removed-(PJM)-web public policy competitive markets

The study drew a volley of critical correspondence to the Board of Managers from generators who said it presented a skewed view of the risks and benefits associated with competitive markets as compared with the traditional regulated model. (See Generators Rebut PJM Study on Investment in Competitive Markets.)

The subject incited just as lively of a debate at last week’s forum, which consisted of three panels: defining the problem, discussing traditional responses and studying alternative solutions.

Tony Clark: ‘A Real Challenge’

Cragi Glazer PJM Grid 20-20 (RTO-Insider) PJM’s Grid 20/20 Ponders Mixing Public Policy, Competitive Markets
Glazer © RTO Insider

FERC Commissioner Tony Clark, who will be leaving his post next month, delivered the opening remarks. Clark said that integrating public policies into competitive markets has become an increasing challenge for regulators.

“It’s going to be at the core and heart of what FERC is doing over the next several years and what states are going to be doing,” he said. “It’s going to last long past the next six weeks of my tenure, I can guarantee that.”

Although FERC’s job is not “passing philosophical judgement” on state policies, he said, those policies impact the commission’s jurisdiction over wholesale markets.

“We have the responsibility for just and reasonable rates,” he said. “There may be an iterative process where we try to set the boundaries and bumpers around what is permissible and what is not. But it’s not going to be an easy process.”

Even states that share a goal — such as the nine in the Regional Greenhouse Gas Initiative — can have differing ideas of how to reach the objective, said Marc Montalvo, president of Daymark Energy Advisors, who spoke with Glazer on the first panel.

State policies also can have unintended consequences, he said, citing the challenges faced by California and Hawaii, which are chasing ambitious renewable power goals.

“Every last region inside of the country is wrestling with the same issues. We want to make sure we’re doing smart investments, protecting consumers, respecting competitiveness,” he said. “All of us who are working in the markets are trying to figure a way to mix that batter up to make a delicious pancake.”

How Can PJM Markets Change?

The second panel was led by Hung-po Chao, senior director of economics for PJM. Panelists were Independent Market Monitor Joe Bowring; Steve Schleimer, senior vice president of government and regulatory affairs for Calpine; Susan Bruce, an attorney representing the PJM Industrial Customer Coalition; Jim Wilson of Wilson Energy Economics; and Lisa McAlister, deputy general counsel for American Municipal Power.

PJM-Grid-20-20-Panel-2-(RTO-Insider)
Left to right: Hung-po Chao, PJM; Lisa McAlister, AMP; James Wilson, Wilson Energy Economics; Steve Schleimer, Calpine; Susan Bruce, McNees Wallace & Nurick; Joe Bowring, Monitoring Analytics © RTO Insider

“The competitive wholesale market was designed to address and ensure reliable supply and an efficient market that includes resource adequacy issues,” Chao started off. “It was not designed to accommodate many other social objectives, like a clean environment. Here the question is: As these policy challenges are upon us, are there things that the PJM electricity markets can change to accommodate positive externalities?”

Playing off of one of Glazer’s analogies, McAlister said that just one kitchen tool — a blender — can’t make every dish.

“Unlike a real competitive market, the current PJM capacity construct is not sufficiently robust to accommodate unforeseen events,” McAlister said. “Adding another tweak to the 24 major adjustments since 2010 will only add another layer of complexity and uncertainty. It is time to look at simpler constructs that would be more resilient in the face of constant change.”

At Thursday’s Markets and Reliability Committee meeting, AMP’s Ed Tatum will be seeking support for an initiative to consider an overhaul of the capacity market. (See related story, Co-ops, Munis Call for Reset of PJM Capacity Model.)

Wilson agreed that changes to the capacity market are needed.

PJM’s changing resource mix is creating a need for flexible capacity, he said. “All of that is valued properly in the energy and ancillary services markets” he said, but not in the capacity market.

Schleimer took a different view, saying that without the capacity market, there would be no independent power producers, and consumers would be shouldering the risk of building generation under state integrated resource plans.

“When you have more apples on hand than you will ever need, costs are always going to be low. You can either have an energy market with scarcity pricing, or you can have a capacity market to allow investors a reasonable opportunity to recover their capital,” he said. “Where do we want to end up 10, 20 years from now? In a world where new investment is only made from rate base?”

“I don’t know if we have a strong view decided on this because it’s such a difficult question and the history of this issue is so important to it,” responded Bruce.

She recalled 1997, when Pennsylvania’s Electricity Generation Choice and Competition Act went into effect. “The ideas of markets and shifting the risk away from customers was something attractive to industrial customers,” she said. “The driver was to reduce cost, reduce risk for customers.”

The Origin of the Markets

Bowring agreed. “The markets have worked very well. You have to remember where restructured markets came from — they’re an alternative to a regime in which public utilities commissions made decisions, many opaque, various policies of many kinds,” he said. “It was a conscious decision to move to markets.”

He said there exist ways aside from subsidies to achieve public policy goals. For example, he said, “If you want to deal with carbon, have a carbon price; don’t subsidize nuclear, have a carbon price.”

He was referring to New York’s recent adoption of the Clean Energy Standard, which includes a zero-emission credit for struggling nuclear power plants. (See New York Adopts Clean Energy Standard, Nuclear Subsidy.)

“Markets can’t handle the recent attempts to intervene in the market in Ohio on behalf of companies that wanted subsidies in their favor,” Bowring said. “That’s fallen by the wayside for various reasons, but we do need tools to address that type of intervention. We need to continue to react to change. The market has to be flexible, and the market designers have to be flexible.

“The reason we have markets is to provide power to customers at the lowest possible [cost]. We have to be careful not to let other aspects of the debate interfere with that or undermine them. Markets are more fragile than we all think, and they could go away fairly easily.”

Capacity Market at Risk?

The third panel, moderated by Vince Duane, PJM’s senior vice president for law, compliance and external relations, hosted William Berg, vice president of wholesale market development for Exelon; Peter Fuller, vice president of market and regulatory affairs for NRG Energy; Stu Bresler, PJM’s senior vice president of operations and markets; Raymond DePillo, senior director of market development for PSEG Energy Resources and Trade; and John Moore, senior attorney for the Sustainable FERC Project.

© RTO Insider pjm public policy, competitive markets
Left to right: Vince Duane, PJM; Stu Bresler, PJM; Ray DePillo, PSEG; Peter Fuller, NRG Energy; John Moore, NRDC; William Berg, Exelon © RTO Insider

Asked if the capacity market is at risk, Bresler said, “I certainly think a do-nothing approach going forward puts the goals of the markets in general at risk. The risk of a do-nothing approach is a detrimental effect on the long-term price signal.”

“Yes, I do think we are putting the capacity market at risk,” DePillo said. “We’re going through what is effectively a fleet transformation. How do we do that in the most effective way possible? We are going to need uneconomic retention,” he said, referring to state initiatives such as New York’s nuclear subsidies.

“The more we attempt to use the capacity market, particularly in isolation, to solve all the blender issues we are facing today, the more distorted it gets,” Berg said.

He advocated a holistic approach. “That starts with an honest conversation about what constitutes a subsidy so onerous it needs to be subject to mitigation,” he said.

For his part, Moore said the Sustainable FERC Project supports a goal of 80% carbon reduction by 2050.

“There are a lot of good state policies that get us a long way that we should protect,” he said. “I wonder if we’re going down the wrong fork in the road adding complexities to the capacity market.”

Bresler introduced an idea for a two-stage capacity auction that would integrate subsidized resources but prevent them from impacting the prices of other generators. Fuller welcomed PJM’s effort to respond to out-of-market state policies but expressed concern that the model would place all of the risk of state policy implementation on resources at the margin, which could defeat the goal of protecting price formation.

The concern, which PJM’s proposal acknowledges, is that resources will bid zero to ensure they clear in stage 1; those that don’t won’t receive any capacity revenue through the second, higher-priced stage, clearing after subsidized units are removed. “It is unclear whether this potential would have any significant impacts on resource offer behavior in the capacity auctions,” PJM said.

Berg wasn’t so sure. “My first thought is if there was ever any doubt that … resources will bid zero, this is it amped up on steroids,” he said.

PJM CEO Andy Ott closed out the session, saying, “I see this issue as fairly large for us.” He added, “It’s no secret that PJM feels strongly about its competitive markets.”

Stakeholders can expect the dialogue to continue, he said.

“Don’t worry,” he reassured the audience. “We’re not going to make a filing tomorrow.”

MISO Planning Advisory Committee Briefs

MISO said it will work to improve the role of the Planning Advisory Committee in interregional matters following complaints that the committee was hearing after the fact about Interregional Planning Stakeholder Advisory Committees (IPSAC) decisions.

Interregional Study Process Adding in PAC (MISO) - miso planning advisory committee

Eric Thoms, MISO manager of planning coordination and strategy, said the PAC’s seven voting sectors should decide the RTO’s IPSAC vote on study approvals or whether potential interregional projects should proceed to regional review. However, Thoms said those votes should continue to be conducted at IPSAC meetings.

The MISO-SPP IPSAC’s nonbinding votes — one vote from each RTO — are taken under advisement by the MISO-SPP Joint RTO Planning Committee, a group of RTO staffers that has ultimate say over what interregional issues the RTOs pursue.

For interregional matters involving PJM, the PAC will continue to provide advice and recommendations to MISO planning staff participating in the MISO-PJM Joint Planning Committee. No votes are conducted in the MISO-PJM IPSAC.

Thoms © RTO Insider
Thoms © RTO Insider

To become more proactive, MISO plans to make presentations to the PAC on issues scheduled at subsequent IPSAC meetings. “We need to do our due diligence to get out in front of PAC with a list of issues that we’re going to present,” Thoms told the committee during an Aug. 17 meeting. “We will give you forewarning in person. We need to come in front of you with these topics beforehand.”

Transmission Owners sector representative Cynthia Crane expressed reservations with the PAC’s vote being conducted in the IPSAC where she said a different set of stakeholders are in attendance. She said fewer sector representatives typically attend IPSAC meetings versus the PAC.

“I think you may end up with a different vote. I have some concerns,” Crane said.

PAC Chair Bob McKee agreed with the voting concern. “It’s tough to have this sort of conversation in front of a different body,” he said.

Sean Brady of Wind on the Wires asked for a timeline on what interregional efforts MISO is undertaking, such as scopes, study and approval processes. Thoms said he would take the comments under advisement.

MISO-SPP Coordinated Study Focusing on 5 Interregional Areas in Dakotas

Thoms also said MISO is proposing to look at five needs in its coordinated study with SPP, focusing on potential project spots along its seam with SPP’s Integrated System in North Dakota, South Dakota and Iowa. The study is currently expected to last through April. The final scope discussion is expected at the Sept. 7 joint meeting with SPP.

“Once we identify the needs, we can hit the ground running,” Thoms said.

Adam McKinney of the Missouri Public Service Commission questioned why MISO would embark on this study when it couldn’t approve a single interregional project after the 2015 study. (See “MISO Rethinks Coordinated Study with SPP,” MISO Planning Advisory Committee Briefs.) He likened it to an ill-matched girlfriend and boyfriend getting married. “It’s like if I go on a trip with my girlfriend for three days, and we can’t stand each other, then we decide to get married for five years,” he said.

MISO, Planning Advisory Committee

McKinney also said he didn’t want smaller projects set aside in a quest to identify larger projects only. “I want my smaller problems fixed, and I don’t want them ignored in some big overlay bonanza.”

Thoms said that threshold for conducting regional reviews of projects with SPP is low: a requirement to reduce congestion by 5% or more on either side of the seam.

This newest study will take place as MISO considers making changes to align its study timeline with SPP and scrapping the “triple hurdle” of interregional and separate regional reviews of joint projects. (See MISO, SPP Disagree on 2016 Joint Study.)

Thoms asked for stakeholder feedback on the coordinated study by Aug. 24.

He also told stakeholders that MISO and PJM are working on a cost allocation method for a new project type: targeted market efficiency projects, short-term projects of $20 million or less to relieve congestion. (See MISO, PJM Unveil JOA Process for ‘Targeted’ Market Efficiency Projects.)

Thoms said MISO will report to the PAC once it determines how to split costs within the RTO. “We haven’t quite figured out the cost allocation yet,” Thoms said.

Longer, More Detailed Tx Overlay Study in Works

Citing a changing resource mix, MISO this year has set out a more detailed regional transmission overlay study, which identifies transmission needs and the most efficient solutions.

MISO said the draft scope for the multi-year study will use the three futures developed for MISO’s 2017 Transmission Expansion Plan (MTEP) to “identify regional needs and develop long-term overlay roadmaps.” (See MISO Proposes 3 New MTEP 17 Futures.)

MISO plans to finalize the overlay scope at the Sept. 21 PAC meeting.

The study will result in a list of regional transmission needs by the end of 2017 and identify transmission project candidates in 2018. In 2019, MISO envisions setting up business cases and cost allocations on selected projects.

McKee said the overlay scope resembled the vetting process for the market efficiency project (MEP) and multi-value project (MVP) portfolios.

PAC liaison Jeff Webb said the overlay may fit some of the MEP and MVP criteria as MISO’s changing fleet is driving a more detailed study.

“It’s not something we ought to do every year, but our fleet is changing,” Webb said. “If it looks similar, that’s because it is, but I don’t want to judge it just yet. Let’s see what the analysis shows. … We haven’t done the analysis yet so let’s not get ahead of ourselves.”

$104 Million in MISO South Projects Recommended to Board

MISO’s Market Congestion Planning Study has identified five projects totaling about $185 million to recommend to its Board of Directors.

Arash-Ghodsian-(RTO-Insider)
Ghodsian © RTO Insider

Arash Ghodsian, of MISO’s economic studies department, said four of the five projects being submitted for recommendation are in MISO South. The four are spread across Arkansas, Mississippi, North Louisiana and Southeast Louisiana, and Ghodsian said none of them meet the 345-kV voltage threshold to become an MEP:

  • The $7.6 million, 6.5-mile long rebuild of the Trumann–Trumann West 161-kV line in Arkansas comes with a benefit-to-cost ratio of 13.36 and an estimated 2018 in-service date.
  • The $6.7 million relocation of the existing 500/230-kV Lakeover transformer near Jackson, Miss., has a 1.43 B/C ratio and is estimated to be in service by 2020.
  • Upgrading the Minden–Sarepta 115-kV terminal equipment in northern Louisiana will cost about $1.9 million with a 1.83 B/C ratio and is estimated by 2020.
  • The construction of a new 230-kV transmission line and substation south of the existing Ninemile substation in Southeast Louisiana will cost about $88 million and have a B/C ratio ranging from 1.96 to 42 with an in-service date by 2022.

Ghodsian said the projects will be reviewed to see if any should be expedited.

Zheng Zhou, with MISO’s economic studies department, said the RTO also intends to recommend the $81 million Huntley–Wilmarth 345-kV line project from Minnesota to Iowa as an MEP in MISO North. The line, expected to be in service in early 2022, comes with a 2.02 B/C ratio.

Zhou said stakeholders generally supported the Minnesota project.

PAC liaison Jeff Webb said if the projects are approved by the board, they will move into MTEP 16.

MISO asked stakeholders provide opinions on the five projects to the Economic Planning Users Group by Aug. 24.

MISO: MVP Savings Top $10 Billion

MISO says it received $10.5 billion to $35.8 billion in net benefits from in-service MVPs since authorizing them in 2011.

The results are part of MISO’s second annual limited review of MVPs. The RTO said congestion and fuel savings account for 75% of overall MVP benefits.

Davey Lopez, MISO advisor of planning coordination and strategy, said the MVP B/C range is about 2 to 2.7, in line with expectations when the RTO approved the 17 MVP projects in 2011.

— Amanda Durish Cook

Company Briefs

nipscomitchellplant(nipsco)Northern Indiana Public Service Co. announced that it will demolish its Dean H. Mitchell power plant on Lake Michigan and conduct an environmental cleanup.

NIPSCO will spend $18 million and two years demolishing the Gary, Ind., coal plant, built in 1955 and taken offline in late 2001. The company said it plans to work with city officials to develop the site.

“This is a positive step forward for the community, our customers and the environment as we clear the path for new investments and opportunities for the future,” NIPSCO Executive Vice President Violet Sistovaris said in a statement.

More: Post-Tribune

Consumers Opens Solar Plant at Mich. Campus

Western_Michigan_University_wordmarkConsumers Energy’s new 8.5-acre solar array located in Western Michigan University’s Business Technology and Research Park has begun generating power.

The 1-MW solar plant is Consumers’ second large-scale project in Michigan. The first was a 3-MW solar plant opened in April at Grand Valley State University.

Both projects are part of the company’s Solar Gardens program. Ratepayers who subscribe to the program receive a varying credit on their monthly bills depending on how much power is produced at the plants.

More: MLive

Consumer Group Calls for Deeper Ameren Rate Decrease

ameren illinoisConsumer advocate group Citizens Utility Board is arguing that Ameren’s proposed 2017 cut in electric rates for its Illinois customers is not enough.

CUB, along with an industrial customer group, says ratepayers are owed $30 million, more than double the $14.4 million cut that Ameren set forth in its filing. The group is urging the Illinois Commerce Commission to approve a more substantial decrease.

“We are glad that Ameren Illinois has proposed a rate cut for its customers, but our expert testimony shows that customers deserve double the decrease,” Citizens Utility Board Executive Director David Kolata said. “We’re going to do everything we can to make sure customers get a fair rate cut.”

More: The Southern Illinoisan

JCP&L to Invest $387M in Infrastructure by Year-end

jcplproject(jcpl)Jersey Central Power & Light plans to complete $387 million in infrastructure projects in its northern and central service areas by the end of the year.

The FirstEnergy subsidiary already has spent $233 million to pay for the final phase of a 115-kV transmission line through Mercer, Middlesex and Monmouth counties, a substation expansion in Morris County and 2,000 miles of tree trimming.

“Last year, JCP&L experienced its best service reliability in over a decade, and our goal is to make our system even better,” said Jim Fakult, the company’s president.

More: FirstEnergy

LP&L Management Considers Building Compatibility Study

lubbockpower(lubbock)Lubbock Power & Light is hiring a contractor to take a closer look at concerns that many downtown buildings may not be able to connect to new power lines that are being buried underground.

The municipal utility told the Lubbock Electric Utility Board that the contractor would identify the number of structures that are and are not compatible with the new system. The utility is moving downtown aerial wires to underground conduits in a series of phases.

More: A-J Media

SWEPCO Issues RFP for 100 MW of Wind Energy

American Electric Power’s Southwestern Electric Power Co. subsidiary has issued a request for proposals for up to 100 MW of wind power capacity.

SWEPCO wants to buy wind assets that can be put into commercial operation by 2019. The assets must be interconnected to SPP and located in the states of Arkansas, Louisiana, Texas, Oklahoma, Kansas or Missouri.

Bids will be accepted through Sept. 15. The application forms and additional information can be found here.

More: SeeNews

Texas PUC Grants ERCOT, SPP More Time to Study LPL Move

By Tom Kleckner

The Public Utility Commission of Texas last week granted ERCOT and SPP staff’s request for a five-week extension before reporting back on how they will together study Lubbock Power & Light’s planned move to ERCOT.

Commission Chair Donna Nelson acknowledged the complexity of analyzing LP&L’s integration into ERCOT and its impact on SPP’s neighboring grid. “We have to assume [ERCOT and SPP] are moving as quickly as they can,” Nelson said during the PUC’s Aug. 18 meeting. “We’ll give you this extension, but don’t ask for another.”

The commission last month detailed specific issues the RTOs should analyze and asked them to produce a study scope before its August open meeting. The PUC has regulatory oversight of ERCOT and would have to approve LP&L’s migration to the Texas grid (Docket No. 45633). (See PUCT Asks ERCOT, SPP to Coordinate on Lubbock P&L Move.)

Lubbock Power & Light Service Territory (Lubbock Power Light) PUCT, ERCOT, SPP

ERCOT’s director of system planning, Warren Lasher, and SPP’s vice president of engineering, Lanny Nickell, responded with a joint letter Aug. 11 saying they were “not yet able” to provide a firm schedule for completing the analyses. They promised a “more definitive response” for the commission’s Sept. 22 open meeting.

“At that time, ERCOT and SPP expect to be able to provide more information regarding the coordinated studies, including technical details and a more informed estimate of the study schedule,” they said.

“I look forward to hearing from them. Go forth and do good,” Nelson said.

According to the letter, staff have met four times since the July 20 PUC meeting, comparing their transmission-planning study processes and discussing study approaches and project schedules. Lasher and Nickell noted the two RTOs have not worked together on transmission-planning studies in the past and said differences in their study processes meant they would not be able to supply the requested details before last week’s PUC meeting.

The two officials said the study could be completed as early as the second quarter of 2017.

Last September, LP&L announced its intention to disconnect 430 MW of its load from SPP and join ERCOT in June 2019. An ERCOT study completed in June indicated it will cost $364 million and take 141 miles of new 345-kV right of way to incorporate LP&L.

El Paso Electric, SWEPCO Settlements

In other actions, the PUC approved a settlement with El Paso Electric allowing the utility to build a voluntary community solar pilot program (Docket No. 44800) and a settlement in which Southwestern Electric Power Co. will pay $23,000 for violating reliability and service standards when it fell behind in tree trimming (Docket No. 46117).

The SWEPCO order gave Commissioner Ken Anderson a chance to speak out on one of his pet peeves. “Tree trimming needs to be done on an annual basis,” he told SWEPCO representatives. “You’re in East Texas, where things actually grow.”

PUC staff are working on a study evaluating Texas utility tree-trimming practices.

Cost Allocation for Seams Projects

Nelson and Anderson also briefly discussed holding a special meeting involving MISO and SPP staff to gather their input on allocating costs for seams projects. Anderson, a member of the Organization of MISO States, said Missouri representatives have questioned whether the interregional planning changes FERC ordered for MISO and PJM should also apply to MISO’s seams with SPP and ERCOT.

Acting on a complaint by Northern Indiana Public Service Co., the commission in April ordered MISO to reduce its minimum voltage threshold for interregional economic transmission projects from 345 kV to 100 kV and to eliminate the $5 million cost threshold for such projects. It also ordered the removal of the requirement for a third, separate benefit-cost analysis for the combined regions (EL13-88). (See FERC Orders Changes to MISO-PJM Interregional Planning.)

Federal Briefs

Deepwater Wind announced it has completed the 30-MW, five-turbine Block Island Wind Farm, an announcement that drew the praise of the National Ocean Industries Association and others, including the Sierra Club.

Block Island Wind large (Deepwater Wind)“The completion of any offshore energy project is no small feat; the road from concept to completion can be very lengthy and rife with challenging regulatory hurdles, unanticipated permitting delays, and vocal environmental opposition alongside enthusiastic public support,” NOIA President Randall Luthi said.

“Our untapped offshore wind energy potential is enormous and it holds the key to creating thousands of good paying clean energy careers, cleaning up the dangerous fossil fuel pollution endemic in many our coastal cities, and provides another effective solution to addressing the climate crisis,” said Mary Anne Hitt, director of Sierra Club’s Beyond Coal Campaign.

More: Morning Consult; USA TODAY

EIA: CO2 from Natural Gas to Surpass Coal

eia(gov)For the first time in more than 40 years, carbon emissions from natural gas this year are expected to exceed those from coal, according to data released last week by the Energy Information Administration.

Though natural gas is less carbon-intensive, Americans are using more of it, as the country eases its reliance on coal-fired generation.

At the same time, annual carbon intensity rates have been decreasing, in part because of the growing consumption of carbon-free generation such as nuclear and renewable power.

More: StateImpact

DOE: US a World Leader In Wind Generation

berkeleylabs(gov)The U.S. remains No. 1 in the world for electricity generated by wind power and No. 2, behind China, for wind power capacity, according to an annual report released last week by the Energy Department and its Lawrence Berkeley National Laboratory.

Nearly 8,600 MW of wind capacity were installed in the U.S. in 2015, a 77% increase over the previous year’s installations.

By comparison, China installed 30,293 MW of wind capacity last year.

More: Windpower Engineering & Development

River Group Sues Portland General over Dam Operation

portlandgeneralelectric(portland)An Oregon environmental group has sued Portland General Electric in federal court, alleging that the utility’s dam operations along the Deschutes River are violating the Clean Water Act.

The focus of the lawsuit is a $100 million, 273-foot underwater tower and fish-collection facility that PGE built in 2009 in partnership with the Confederated Tribes of Warm Springs, co-owner of the Round Butte Dam.

The Deschutes River Alliance alleges the tower’s operation violates standards for water temperature and dissolved oxygen, while also contending that the Oregon Department of Environmental Quality is not enforcing water quality standards. The utility countered that the facility is intended to restore salmon and steelhead runs and that restoration will entail a long-term effort.

More: The Bulletin

NASA Study Shows Methane Hot Spot Comes from Natural Gas Leaks

nasa(gov)Researchers say an unusual concentration of the atmospheric methane over the Southwest appears to come mostly from leaks in natural gas production.

NASA’s Jet Propulsion Laboratory and the California Institute of Technology released a report Aug. 15 that listed more than 250 sources of a methane hot spot over the Four Corners region, including gas wells, storage tanks, pipelines and processing plants. Only a handful were natural seeps from underground formations, according to researchers. The study said about 25 locations are responsible for most of the methane leaks.

Evidence of the hot spot dates back to 2003, and a satellite image released in 2014 showed it in vivid color, but the origin wasn’t clear until recently. The new study identified the sources with spectrometers aboard aircraft that flew 3,000 to 10,000 feet above the ground over about 1,200 square miles in the Four Corners in April 2015.

More: The Associated Press

Dakota Access Says It Will Halt Until Hearing

standingrock(standingrock)Developers of the Dakota Access Pipeline said last week they will halt construction on the $3.8 billion oil pipeline that is to run from North Dakota to Illinois pending a hearing in federal court in D.C. this week. The Standing Rock Sioux Tribe is suing regulators for issuing permits for the pipeline that the tribe says goes through sacred land and poses a threat to its drinking water.

Members of the tribe and its supporters blocked construction equipment last week while it waited for its request for a temporary injunction, which was approved this week.

More: The Associated Press

Judge Erred in Blocking BLM Fracking Rules, Law Profs Charge

Law professors arguing for the Obama administration said that a judge was mistaken when he ruled against the Bureau of Land Management’s rules concerning fracking on federal land.

The bureau in 2015 issued rules that would have required energy companies to disclose what materials they used in the fracking process. District Judge Scott Skavdahl of Casper, Wyo., vacated the rules, saying the bureau didn’t have the authority to regulate fracking.

In his ruling, Skavdahl pointed to an article written by Florida State University professor Hannah Wiseman to support his conclusion. Wiseman, however, joined 35 other law professors in a brief filed with the 10th U.S. Circuit Court of Appeals, saying the judge misinterpreted her piece.

More: The Associated Press

NRC Reports Violations at Entergy’s FitzPatrick Plant

The Nuclear Regulatory Commission released a report citing Entergy’s James A. FitzPatrick nuclear plant for two violations of “very low safety significance,” including sending workers into high radiation areas without first meeting with the plant’s radiation protection department and for failing to address a long-term radioactive leak.

The report, which covered the second quarter of 2016, said an atmospheric control system failed and was not addressed within the required 30 days. It also cited the plant for allowing radioactive material to escape from a filter sludge tank in the radioactive waste building, though no radiation was leaked into the atmosphere.

Entergy says it has developed a corrective action that will be implemented within the next month.

More: CNY Central