November 17, 2024

Quebec-NYC Tx Line Clears Final Regulatory Hurdle

By William Opalka

A 1000-MW merchant transmission line that would deliver Canadian hydropower to New York City has completed its federal environmental review, clearing the way for construction.

The U.S. Army Corps of Engineers on Tuesday issued a permit to Transmission Developers Inc. that allows the Champlain Hudson Power Express project to be placed in U.S. waters along the proposed route. The entire 333 miles from the Quebec border to the Astoria neighborhood in Queens will be underground or underwater, including sections beneath Lake Champlain and the Hudson River.

TDI said the project has secured all of the federal and state siting permits necessary to proceed with construction, which could start next year. The permit authorizes TDI to construct the project under Section 10 of the Rivers and Harbors Act and Section 404 of the Clean Water Act.

champlain hudson power express

The estimated $2.2 billion project would boost Canada’s interest in exporting electricity to New York and New England. (See Hydro-Quebec Seeks to Boost Exports to Northeast.)

“The terms of the permit reaffirm that our project will take appropriate steps to protect New York’s environmental and commercial resources, and we are excited to have moved substantially closer to the moment when we will begin to deliver cleaner, lower-cost power to New York’s residents and businesses,” TDI CEO Donald Jessome said in a statement.

The project has been under development since 2008. Its proponents claim it could reduce energy costs for consumers and businesses by $650 million a year.

The Independent Power Producers of New York, a trade association whose members would be in direct competition with imported energy sources, opposed the project. IPPNY insists the project is not financially viable without subsidies from Canadian power producers and an above-market-rate contract with New York utilities transmitting the energy.

The New York Public Service Commission has rejected those claims.

TDI plans to finance the project through private equity and support from shippers and contractors. TDI’s lead investor is the Blackstone Group.

PJM Staff Picks LS Power for Artificial Island Stability Fix; Dominion Loses Out

By Suzanne Herel

VALLEY FORGE, Pa. — PJM planners will recommend to the Board of Managers that LS Power build a new 230-kV transmission line from New Jersey’s Artificial Island to Delaware to address stability issues at the nuclear complex, they announced Tuesday at a special meeting of the Transmission Expansion Advisory Committee.

LS Power’s commitment to limit construction costs to $146 million was a driving factor of the decision, said Paul McGlynn, general manager of system planning. PJM also felt the proposal has the best chance of being able to secure permits.

“It is our opinion that the LS Power proposal provides greater flexibility and can mitigate some of the permitting risk involved in siting,” he said. “It is staff’s intent to recommend installing a 230-kV line under the Delaware River using horizontal directional drilling technology and designate that to LS Power.”

Public Service Electric & Gas and Pepco Holdings Inc. were chosen for necessary connection facilities. Dominion Resources and Transource Energy, which were among the finalists, were not included in PJM’s recommendation. PJM will make the recommendation to the Board of Managers after May 29, the deadline for stakeholders to submit comments.

artificial island
PJM planners recommended the selection of LS Power to build a new 230kV circuit from Salem to a new substation near the 230kV corridor in Delaware, using horizontal directional drilling the bury the line under the Delaware River. The new line would tap the Red Lion-Cartanza and Red Lion-Cedar Creek 230 kV lines. (Source: PJM Interconnection LLC)

Sharon Segner, vice president for LS Power, said in an interview that she appreciated PJM recognizing the value of being able to choose from an overhead or submarine crossing.

“It’s going to be a difficult river crossing. We go into it with our eyes wide open,” she said. Yet, she said she was confident the company would be able to complete the four-year project within the cost cap. “We’ve assessed the situation, assessed the risks and feel very comfortable in the commercial feasibility of our project.”

Roles for PSE&G, Transource

PSE&G would be responsible for expanding the Salem substation and building a static VAR compensator (SVC) upgrade at New Freedom. Pepco Holdings Inc., Transource’s partner, would oversee interconnecting the new substation to the existing Red Lion-Cartanza and Red Lion-Cedar Creek 230-kV lines.

PSE&G and PHI together would be responsible for optical ground wire (OPGW) upgrades.

The SVC upgrade project is estimated at $31 million to $38 million, and the OPGW work at $25 million.

Home to the Salem and Hope Creek nuclear reactors, Artificial Island is the second largest nuclear complex in the country. Special operating procedures that historically have been used to maintain stability in the area have become increasingly difficult to implement while respecting the system’s other operational limits.

First Order 1000 Solicitation

The call for proposals for a fix, which went out two years ago, signaled PJM’s first competitive transmission project under the Federal Energy Regulatory Commission’s Order 1000.

Last summer, PJM planners recommended PSE&G for the job, but the Board of Managers reopened the bidding following an outcry from losing bidders, environmentalists and New Jersey officials.

PSE&G was a finalist in the new round of bidding, along with LS Power, Transource and Dominion.

“We’re disappointed with the outcome,” Jorge L. Cardenas, PSE&G vice president for Asset Management & Centralized Services, said after the meeting. “We will put our comments together in the next 30 days.”

All of the projects include new transmission lines connecting the nuclear complex to Delaware. LS Power and Transource offered a southern, submarine crossing of the Delaware River, with LS Power also including an overhead option. Dominion and PSE&G proposed a northern, overhead crossing. (See Artificial Island Finalists Face Off in Tense Meeting.)

All are expected to be met with permitting obstacles.

Planners had expected to make a recommendation in January but held off so consultants could look into concerns that Dominion’s proposed use of thyristor controlled series compensation (TCSC) could threaten reliability.

At the last TEAC meeting, PJM said that Siemens Power Technology International had completed a sub-synchronous resonance analysis of Dominion’s proposal and found it could result in “negative damping” for several resonant frequencies.

Exponent, an engineering and science consulting firm hired by PJM to review the Siemens study, expressed its own concerns with the Dominion plan, which proposes a 90% post-contingency TCSC compensation — well above the usual 70 to 80% compensation used in the industry.

PSE&G Challenge

Still outstanding is a complaint PSE&G submitted to FERC accusing PJM of breaking its own rules in the bid solicitation process (EL-15-40). PJM in March asked FERC to defer ruling on the matter until it had chosen a bidder for the project. (See PJM: PSE&G’s Remedy for Artificial Island Bid Process ‘Draconian,’ ‘Self-Serving’.)

“We still have our complaint in to FERC, and we will pursue that and hope for the best,” Cardenas said.

FERC OKs PJM Request to Delay Capacity Auction

By Rich Heidorn Jr.

The Federal Energy Regulatory Commission Friday granted PJM’s request to delay May’s Base Residual Auction, allowing the RTO more time to seek FERC approval for its Capacity Performance proposal.

“PJM’s request for waiver will allow the commission to consider the additional information submitted by PJM in support of its Capacity Performance proposal, as well as comments and protests regarding that additional information, while also providing clarity regarding the timing under which PJM will conduct its auction following commission action on that proposal,” the commission said.

PJM filed the request on April 7, after FERC issued a deficiency letter over the Capacity Performance plan (ER15-623). It sought a waiver from the Tariff requirement that the auction be held in May. It said it would hold the auction 30 to 75 days after a commission order on the merits of the proposal, but no later than the week of Aug. 10-14.

The proposed delay drew more than two dozen comments, mostly from supportive stakeholders, but also from critics who said a postponement would create more market uncertainty than it is seeking to quell. (See PJM Bid to Delay Capacity Auction Draws Flurry of Support, Criticism.)

In granting the delay, the commission ruled that PJM’s request was of limited scope, remedied a concrete problem and would not harm third parties (ER15-1470). (The commission later issued an errata to fix its incorrect reference to the in paragraphs 1 and 2, which should have referred to the 2018/19 delivery year.)

FERC acknowledged the delay would result in “some uncertainty.”

“We recognize that some protestors argue that delaying the auction will harm them by increasing their costs to participate in the auction. We acknowledge these concerns, but agree with PJM that it is important that the commission have the opportunity to consider the full record in the Capacity Performance proceeding prior to PJM running this year’s auction.”

The commission said PJM’s commitment to conduct the auction no later than mid-August mitigates the potential impacts on market participants, and noted that “any additional costs incurred by participating resources may be included in their capacity sell offers, to the extent permitted by the rules in place for the auction.”

 

Entergy Out-of-Cycle Requests Win MISO Board OK

By Chris O’Malley

CARMEL, Ind. — Over the objections of transmission developers and independent power producers, MISO’s Board of Directors voted unanimously Thursday to approve Entergy’s request for $217 million in out-of-cycle transmission projects.

There was no discussion by the board nor comments from stakeholders on the topic.

The outcome seemed all but certain following a unanimous vote Tuesday by MISO’s Board of Directors System Planning Committee to recommend that the full board approve Entergy’s requests.

Most of the opposition centered on the largest of the Entergy projects, a $187 million project to serve additional load in the Lake Charles, La. industrial zone in the midst of an economic revival.

Opposing stakeholders have alleged the increased load is speculative, that the project is beyond what is needed for a base reliability upgrade and that there was inadequate stakeholder review.

They also wanted a shot at competing for the project.

On Tuesday MISO staff outlined a checklist of steps taken that they say conforms with tariff and business practice manual procedures.

The bulk of the controversial Lake Charles project involves adding a 500 kV tap line that will extend seven miles to a new substation in Lake Charles, where Entergy said numerous industrial customers have committed to adding facilities.

MISO studied alternatives, including upgrading a 230 kV line and providing supply from more distant sources, but concluded they were less effective, said MISO Director of Planning Jeff Webb. “This is a straightforward, and I think ideal, solution,” Webb told the committee last week.

The committee pointed to an April 2 letter from Louisiana Public Service Commissioner Eric Skrmetta that expressed dissatisfaction with the review of the projects at MISO, calling on MISO to streamline the out-of-cycle approval process.

“Nothing should be permitted to interfere with the location of significant new load in southwest Louisiana and the economic benefits it will bring to the people of this state,” wrote Skrmetta. “…The consideration of these projects has gone on long enough. Second, numerous stakeholders have expressed dissatisfaction with MISO’s out-of-cycle consideration and approval process.”

Webb told the committee that MISO had 16 OOC projects last year and seven in 2013. Director Baljit “Bal” Dail, who is not a member of the committee but sat in on Tuesday’s meeting, asked Webb why Lake Charles was so controversial.

Webb cited the size of the project and said he recalled only one other controversial project over the years — also one of substantial size.

Clearly, large projects would be more lucrative for transmission developers hoping for a competitive project. MISO staff have maintained that Lake Charles is a reliability project, which would be ineligible for competition.

Board Chairman Judy Walsh — who substituted as chair of the meeting due to a medical issue involving chair Mike Evans — said the OOC process is designed to prevent MISO from becoming a “stumbling block” to needed reliability upgrades.

“In order for this process to work it has to be fast. It has to be efficient,” she said.

Earlier this month, in response to the controversy over Entergy’s request, MISO launched discussions that could lead to refinements in its procedures for handling out-of-cycle requests. (See MISO Seeks Stakeholder Input on Out-of-Cycle Process amid Entergy Controversy.)

MISO to Consumer Sector: No Money for You

By Chris O’Malley

CARMEL, Ind. — MISO has declined a request by the Public Consumer Advocates sector for $200,000 to help cover its legal costs in a fight over MISO transmission owners’ return on equity.

The decision was announced Wednesday at the MISO Advisory Committee.

“We don’t have a mechanism to send them money,” said MISO General Counsel Stephen Kozey, adding there was no show of stakeholder support for such funding.

The Public Consumer Advocates sector consists of both non-profit groups and government agencies that represent consumers in utility cases before state regulators.

MISOIt decided to enter the ROE battle after settlement talks ordered by the Federal Energy Regulatory Commission between industrial customers and TOs broke down last year. It is the consumer sector’s first-ever litigation in a FERC case.

The consumer sector made the request at the Advisory Committee in February, saying it lacks the deep pockets for legal costs.

Robert Mork, deputy consumer counselor for the Indiana Office of Utility Consumer Counselor, said the Consumer Advocates sector has been supportive of MISO over the years. “We have to say we’re surprised and disappointed by MISO’s decision on this,” Mork said.

He reminded the committee that FERC Order 719 was created in part to improve the responsiveness of RTOs to electric consumers.

Mork didn’t elaborate on the group’s response to the funding denial but said that the consumer sector would have further discussions with MISO, the Organization of MISO States and with FERC.

MISO industrial customers initiated the ROE dispute last year, contending that transmission operators’ current base ROE — 12.38% except for American Transmission Co., at 12.2% — is too high (EL14-12). On April 3, the consumer advocates asked FERC for approval to amend the group’s intervention by adding allies from Arkansas, Kentucky, Louisiana, Montana and Illinois. (See MISO TOs Seek Base ROE of 11.39%.)

Federal Energy Review Calls for Billions of Dollars in Spending on Infrastructure

By Suzanne Herel

The Obama administration’s first Quadrennial Energy Review presents a roadmap for returning the U.S. to a post-World War II level of investment in infrastructure, creating 1.5 million jobs while transforming the nation’s electric grid and oil and gas pipelines, Vice President Joe Biden said Tuesday from PECO Energy headquarters in Philadelphia.

“The U.S. is in the midst of an energy transformation that will allow us to remain the energy epicenter of the world,” Biden said. “To maintain that position, we need a 21st-century infrastructure.”

President Obama ordered the review — similar to the Pentagon’s Quadrennial Defense Review, a widely followed assessment of the nation’s defense — to provide a comprehensive “multi-year roadmap” for U.S. energy policy, with an assessment of current policies and recommendations for additional executive and legislative actions, including priorities for research, development and demonstration programs to support innovation. A White House task force, headed by the president’s top science, technology and climate change advisors and including more than 20 federal agencies, took part in the project, which included public meetings with stakeholders around the country. (See Looking to Build Infrastructure, Moniz Comes to Wall Street.)

The effort is intended “to provide policymakers, industry, investors and other stakeholders with unbiased data and analysis on energy challenges, needs, requirements and barriers that will inform a range of policy options, including legislation.” Each installment of the report will focus on one part of the energy “value chain.”

The 348-page report released Tuesday focuses on the energy transmission, storage and distribution system, which is facing new challenges from climate change, environmental policies and innovations in oil and natural gas production.

[metaslider id=”102305″]

New Sources

Since 2008, solar electricity generation has increased 20-fold, Biden said, and wind energy has more than tripled. In that time, the U.S. has become the world’s No. 1 producer of natural gas, and the nation has reduced its dependency on foreign oil.

Meanwhile, new challenges have emerged regarding national security, increasingly strict clean energy standards and an aging transmission system that isn’t geographically aligned with the needs of renewable generation.

“Changes in the geography of domestic energy production stress the ability of existing infrastructures to move both liquid fuels and electricity from supply regions to demand centers,” the White House said in a fact sheet. “Congestion in the nation’s ports, waterways and rail systems affect the timing and cost of moving not just energy products, but all commodities.”

Aging Infrastructure, Need for Resiliency

Biden noted that half of the nation’s 2.6 million miles of gas pipelines were constructed in the 1950s and 60s, and it would cost about $270 billion to repair them all.

The solution, he said, includes permitting new pipelines more quickly and finding ways for companies to recover their investment without burdening ratepayers.

The system also needs to gird for events such as 2012’s Superstorm Sandy, said Biden, citing it as evidence of climate change.

Between 2003 and 2012, an estimated 679 widespread power outages occurred, he said, costing from $18 billion to $33 billion per year, depending on the nature of the event, he said.

“The threat’s real,” he said. “We’re expecting sea levels to rise by 2030.” In some places, he said, “we will need to literally raise the substation.”

The report cites estimates of billions of dollars to achieve its recommendations. Grid modernization alone is expected to run $3.5 billion annually over 10 years.

Workforce Impacts

Biden stressed the positive effect the investments will have on the workforce.

About 1 million people were employed in energy transmission, storage and distribution jobs in 2013 and over the next five years, about 15% of them will be eligible to retire. The administration says infrastructure spending could add 1.5 million additional energy sector jobs.

“These are middle-class jobs,” he said. “These are the jobs that used to exist at the turn of the 20th century.

“Investing in our infrastructure creates of a virtuous cycle of creating good-paying jobs and attracting companies.”

Accompanying the announcement were two related executive actions.

The U.S. Department of Energy has created the Partnership for Energy Sector Climate Resilience, aimed at strengthening the system against extreme weather and climate change impacts. It will kick off with an April 30 meeting with the CEOs of 17 member companies, including Exelon, Dominion Virginia Power, Pepco Holdings Inc., Public Service Electric & Gas, the New York Power Authority, the Tennessee Valley Authority, National Grid and Entergy.

In addition, the U.S. Department of Agriculture introduced a plan to spend $72 million to support six new rural electric infrastructure projects.

Entergy Out-of-Cycle Request Wins Committee OK; Full Board Approval Likely

By Chris O’Malley

CARMEL, Ind. — MISO’s Board of Directors System Planning Committee voted unanimously Tuesday to approve Entergy’s request for $217 million in out-of-cycle transmission projects, setting up a likely approval by the full board Thursday.

The competitive transmission developer and independent power producer segments have steadfastly opposed the largest of the Entergy projects, a $187 million project to serve additional load in the Lake Charles, La. industrial zone in the midst of an economic revival.

They’ve alleged the increased load is speculative, that the project is beyond what is needed for a base reliability upgrade and that there was inadequate stakeholder review. They also would like a shot at competing for the project.

But once again, MISO staff outlined a checklist of steps taken that they say conforms with tariff and business practice manual procedures.

The bulk of the controversial Lake Charles project involves adding a 500 kV tap line that will extend seven miles to a new substation in Lake Charles, where Entergy said numerous industrial customers have committed to adding facilities.

entergy

MISO studied alternatives, including upgrading a 230 kV line and providing supply from more distant sources, but concluded they were less effective, said MISO Director of Planning Jeff Webb. “This is a straightforward, and I think ideal, solution,” Webb told the committee.

No stakeholders spoke in opposition.

The committee pointed to an April 2 letter from Louisiana Public Service Commissioner Eric Skrmetta that expressed dissatisfaction with the review of the projects at MISO, calling on MISO to streamline the out-of-cycle approval process.

“Nothing should be permitted to interfere with the location of significant new load in southwest Louisiana and the economic benefits it will bring to the people of this state,” wrote Skrmetta. “…The consideration of these projects has gone on long enough. Second, numerous stakeholders have expressed dissatisfaction with MISO’s out-of-cycle consideration and approval process.”

Webb told the committee that MISO had 16 OOC projects last year and seven in 2013. Director Baljit “Bal” Dail, who is not a member of the committee but sat in on Tuesday’s meeting, asked Webb why Lake Charles was so controversial.

Webb cited the size of the project and said he recalled only one other controversial project over the years — also one of substantial size.

Clearly, large projects would be more lucrative for transmission developers hoping for a competitive project. MISO staff have maintained that Lake Charles is a reliability project, which would be ineligible for competition.

Board Chairman Judy Walsh — who substituted as chair of the meeting due to a medical issue involving chair Mike Evans — said the OOC process is designed to prevent MISO from becoming a “stumbling block” to needed reliability upgrades.

“In order for this process to work it has to be fast. It has to be efficient,” she said.

Last week, in response to the controversy over Entergy’s request, MISO launched discussions that could lead to refinements in its procedures for handling out-of-cycle requests. (See MISO Seeks Stakeholder Input on Out-of-Cycle Process amid Entergy Controversy.)

FERC Backs Oklahoma Coal Unit on EPA MATS Delay

By Ted Caddell

Operators of an Oklahoma coal-fired generator seeking a temporary reprieve from the Environmental Protection Agency’s mercury rule received an assist from federal energy regulators last week.

GRDAThe Federal Energy Regulatory Commission told the EPA on Thursday that Unit 1 of the Grand River Dam Authority’s 490-MW Grand River Energy Center near Chouteau, Okla., is necessary to preserve system reliability in SPP.

EPA’s Mercury and Air Toxics Standards (MATS), which took effect in 2012, gave generators three years, until April 16, 2015, to comply. State environmental regulators were permitted to grant one-year extensions, which the Oklahoma Department of Environmental Quality did for the GRDA plant.

GRDA asked EPA to issue an administrative order allowing an additional one-year delay to April 16, 2017, saying it needs the time to complete construction of a new, gas-fired combined-cycle unit at the site.

Without Unit 1, according to the authority, it will be unable to meet SPP’s 12% required reserve margin. The authority also noted that the plant was called on for voltage support six times in 2014.

“The reliability of the bulk power system depends in part on whether utilities meet an appropriate planning reserve margin,” FERC told the EPA. “Absent a significant change in future circumstances, our view is that GRDA’s Unit No. 1 is needed as requested by GRDA to maintain electric reliability.”

The need for Unit 1’s output also was confirmed by SPP. In a letter attached to GRDA’s petition to EPA, SPP said that it “concurs with GRDA’s assessment regarding GRDA Unit 1’s criticality for reliability absent other system changes.”

GRDA said that it sometimes has problems obtaining transmission service to deliver power from outside of the GRDA balancing area when one or both of its existing units are offline.

The final decision on the waiver will be made by EPA.

State Briefs

Delmarva Customers May Have to Wait Months for One-Time Credit

DelPSCSourceGovExelon has promised $40 million for one-time customer credits in Delaware as part of a settlement to get approval for its takeover of Pepco Holdings Inc., but there is no telling when customers will see the credit. Public Service Commission spokesman Matthew Hartigan said the PSC first has to lend final approval to the settlement. The commission is awaiting developments in merger settlements the Chicago energy giant is having with regulatory agencies in Maryland and D.C.

More: The News Journal

ILLINOIS

Grain Belt Express Seeks Approval for State Part of 780-Mile Tx Line

Clean LineHaving already received the approval of Kansas and Indiana, the developers of a 780-mile transmission line project that spans the Midwest are going to Illinois for approval. Houston-based Clean Line Energy, which has already garnered the approval of the Commerce Commission for a line that is to run from Iowa to Illinois, is seeking the commission’s ruling on the Grain Belt Express. The line is designed to carry energy produced by vast wind farms in the Great Plains to markets in the East. The Missouri Public Service Commission is expected to release its ruling on the line within the next few months. The Grain Belt Express is expected to be in service by 2019 if it gets the final approvals it needs.

More: St. Louis Post-Dispatch

ICC Ruling Preserves View at Frank Lloyd Wright House

The Commerce Commission has ruled that Commonwealth Edison’s Grand Prairie Gateway transmission line doesn’t need to abut a Frank Lloyd Wright farmhouse. The ICC said property covenants associated with land sold by the owners of the farmhouse to the Muirhead forest preserve are strong enough to force ComEd to choose a different route. ComEd agreed to shift the path of the $200 million project to move it away from the preserve. The 345-kV line is to run from a substation in Byron to another near Wayne.

More: Daily Herald

MAINE

Solar Promotion Policies Controversial

Gideon

The state’s policies on solar energy put it behind its neighbors, advocates say, so proposals to overhaul its approach are intended to help it catch up. A bill sponsored by state Rep. Sara Gideon (D-Freeport) would require 2.5% of the state’s electricity mix to come from solar by 2022 and offer financial incentives to help homeowners and businesses more quickly pay off their solar installations.

But utility representatives, the Office of the Public Advocate and the Energy Office warned that the proposals could add to ratepayers’ bills. Central Maine Power, for instance, estimated that ratepayers would be paying $55 million in solar subsidies by 2022. The state installed 4.5 MW of solar energy in 2014, an 80% increase. Public Advocate Timothy Schneider said that while his office believes adding more solar energy to the state’s grid is positive, the office opposed the bill based on the potential costs to ratepayers.

More: Portland Press Herald

MANITOBA

Manitoba Not Ready to Join Cap-and-Trade … Yet

Selinger
Selinger

Premier Greg Selinger said the time is not right for the province to join in a cap-and-trade system with neighboring Ontario and Quebec, but it could happen. “It’s still something we’re looking at,” he said in an interview with the Winnipeg Free Press. “There is a lot of work to get there.”

It has been five years since Selinger said he would introduce cap-and-trade legislation in the province. In 2008, the province committed to cutting total greenhouse gas emissions by 6%, compared with 1990 levels, by the year 2012. But a year after the deadline, the province admitted it wasn’t going to come close to the goal and abandoned the plan.

More: The Carillon

MARYLAND

Lawmakers Pass Bills to Foster Community Solar Projects

A pair of bills aimed to make it easier to plan, develop and activate community solar projects have passed in the House and Senate. If signed by Gov. Larry Hogan, the state will be the 10th in the U.S. to allow community solar projects. The bills would allow multiple parties to invest in a single solar project. Investors or subscribers would become eligible for credits to be used against their electricity bill.

The bills allow for a three-year pilot program permitting construction of community solar projects. A study of the projects will be presented to the General Assembly to consider a permanent program.

More: FierceEnergy

MASSACHUSETTS

Acadia Center Report Outlines Benefit of Solar in State

Acadia Center has released a study that quantifies the grid and societal benefits of solar photovoltaic systems in the state.

Acadia Center assessed the value of six hypothetical solar PV system configurations that determined that the value of solar to the grid ranges from 22-28 cents/kWh, with additional societal values of 6.7 cents/kWh.

Solar PV provides unique value to the electric grid by producing clean energy and avoiding generation and related emissions from conventional power plants. The overall grid value of solar is the sum total of these different benefits.

The benefits vary based on the time and location of output from solar panels. Acadia Center examined these variations in the study, including the impacts of orientation (i.e. west- or south-facing arrays) on the value of solar PV. One key finding is that under traditional net metering, west-facing arrays — which maximize output during periods of peak demand — would receive approximately 20% less credit than a comparable south-facing system, despite the fact that they produce approximately the same overall value to the grid.

More: Acadia Center

DPU Scraps Rule Requiring Bill Recalculations if Switching

MassDPUSourceGovIn an attempt to reduce confusion for customers switching electric suppliers, the Department of Public Utilities has scrapped a rule requiring utilities to recalculate customers’ bills if they were leaving their “basic service” plans. The rule often resulted in small “surprise” bills — but sometimes credits — for residential and small business customers.

The rule had been in place for the past 15 years, but more light was shed on it as a result of last winter’s higher energy bills that spurred more customers to seek competitive suppliers. The rule called for recalculations to be done if the customer was in the middle of a six-month service period, which sometimes resulted in an additional charge being reflected because of variable costs charges. Some utilities, including Eversource Energy, said the cost of dealing with customer confusion was higher than the cost of eliminating the “true-up” from recalculations.

More: The Boston Globe

MICHIGAN

Group Tries to Get Anti-Fracking Measure on Ballot for 2016

MichFrackingBanSourceCBFA grassroots organization is trying to get a statewide anti-fracking measure on the ballot for the 2016 election. It will be the third attempt to do so: the group failed to get the necessary 250,000 signatures in 2012 and 2013. “This time we’re going to go all the way,” LuAnne Kosma, chairwoman of the Committee to Ban Fracking, said on Friday. “We have the resources that we need this time to get to 250,000. We’re getting a lot more people involved, and we definitely have more awareness of the issue statewide.” The state’s Board of State Canvassers will review the forms prepared for the collection of signatures, a requirement before the group can begin gathering names.

So far in Michigan, there has only been test drilling for fracking operations.

More: Detroit News

Sens. Urging US to Oppose Canadian Plan to Bury Nuclear Waste

BruceNuclearSourceCanadaU.S. Sens. Debbie Stabenow and Gary Peters are asking the Obama administration to oppose a plan by Canadian authorities to bury nuclear waste near the shores of Lake Huron. “Building a permanent nuclear waste dump in such close proximity to Lake Huron could cause significant, lasting damage,” Peters wrote. “The Canadian government should seek out an alternative site, and I urge the State Department to take action to keep this troubling project from moving forward.”

The plan calls for Ontario Power Generation to bury 7.1 million cubic feet of low- and intermediate-level waste from its Bruce Power nuclear generating station about 2,230 feet below ground. Opponents fear the waste could contaminate groundwater, which would then flow into Lake Huron.

More: Associated Press

Lansing Leaders Contemplate Answers to Aging Powerhouse

Lansing city leaders are pointing fingers at former management of the Board of Water & Light’s Eckert Power Plant for letting it deteriorate to the point where at least $100 million will be needed for infrastructure investment over the next six years.

The aging coal-fired plant near the city’s downtown area can’t be replaced without generating capacity and upgrades to the board’s transmission infrastructure, its interim general manager told the city this month.

The Lansing State Journal reported that part of the capital plans include doubling connections to the grid, which would help provide additional resources in the event the plant experienced a generation disruption.

The aging plant supplies power to about 97,000 customers.

More: Lansing State Journal

MINNESOTA

Enbridge’s Sandpiper Pipeline Gets Nod from Judge; PUC Ruling Pending

EnbridgeSourceEnbridgeEnbridge’s proposed $2.6 billion Sandpiper pipeline — designed to carry North Dakota crude oil across Minnesota to refineries in the East — has received approval from a state administrative law judge who ruled it was necessary. The project still needs approval from the state Public Utilities Commission, but the recent ruling was seen as a defeat to environmentalists opposing the line. North Dakota already has approved its portion of the 610-mile route.

More: Star Tribune

NEW HAMPSHIRE

Lawmakers Ask for Extension for Northern Pass Comment Period

NorthernPassSourceISONEThe state’s congressional delegation says a 60-day comment period is not enough time for what is expected to be a voluminous environmental impact report on the proposed Northern Pass transmission project, a 187-mile transmission project that would cut through North Country forest on its way from the Canadian border to a substation in Deerfield with 1,200 MW of new hydroelectricity from Quebec.

The delegation has asked the federal Department of Energy to extend the time to 90 days. Sens. Jeanne Shaheen and Kelly Ayotte, along with Reps. Annie Kuster and Frank Guinta, have written to energy officials in anticipation of the release this spring of a report they say will exceed 2,000 pages. They say it’s “imperative” that the department allow more than the usual 60-day period before the start of public hearings on the report.

There is no set date for the report’s release.

More: New Hampshire Public Radio

Seacoast Line Raises Concerns

The Seacoast Reliability Project being developed by Eversource is nothing like the scale of Northern Pass, but Seacoast community members have labeled the project “the Northern Pass of the Seacoast.” They’ve raised concerns about noise, interference with telephone, television or radio reception, health risks, and effects on real estate values.

The project would follow a 13-mile existing distribution corridor from Madbury to Portsmouth, mostly through Durham. The Eversource right-of-way is now occupied by 40-foot wooden poles, but these would be replaced by larger metal poles ranging in size from 60 to 108 feet, which would support the 115-kV line.

More: Manchester Union-Leader

NEW JERSEY

BPU Approves $95 Million More Energy Efficiency Spending by PSE&G

BPUSourceGovThe Board of Public Utilities has approved a plan by Public Service Electric & Gas to spend another $95 million in energy efficiency programs for health care facilities, apartment buildings, small businesses and nonprofits. This is on top of the $227 million already invested on energy efficiency programs in those areas. The utility will be allowed to recover the investment in its rates.

“These three programs are targeted at segments that can achieve significant bill reductions from energy efficiency programs but were held back from making these investments for a number of reasons,” said Joe Forline, vice president of Customer Solutions for the company.

More: Philly.com

NORTH CAROLINA

Judge Grants Extension to Duke for Coal Ash Plea

Ash Spill (Source: Duke Energy)Duke Energy has received a four-week extension to enter its guilty plea to Clean Water Act violations relating to the massive Dan River spill last year. The guilty plea was to be part of the $102 million settlement the Charlotte-based company reached with federal authorities over the incident, in which up to 39,000 tons of coal ash and 27 million gallons of coal slurry gushed into the Dan River in February 2014. Duke filed a motion seeking the extension after saying it was concerned that a guilty plea, and a sentence of probation for the company, could prohibit it from continuing to supply electricity to two military bases in its territory – Fort Bragg and Camp Lejeune.

The company says it is negotiating with the Environmental Protection Agency to have that limitation lifted from the terms of probation. State authorities are continuing to investigate Duke’s role in the environmental disaster, and no settlements or plea deals have been announced. Separately, a federal investigation into possible criminal charges relating to the spill is reportedly ongoing.

More: Los Angeles Times

Professor Gets $500,000 Grant to Further Wind-borne Energy Research

A University of North Carolina-Charlotte professor researching ways to create electricity by using tethered, wind-borne generators has received a $500,000 grant from the National Science Foundation. Chris Vermillion, an assistant professor of mechanical engineering, is working on ways to develop kite- or wing-borne wind energy systems that would carry turbines into the sky, while remaining connected to the ground. Such technology could generate 30 to 200 kW of energy.

“This is the only platform in the world — at such a small scale — that replicates both the flight dynamics and the control of airborne wind-energy system lifting bodies,” Vermillion said. The professor and students at the college are developing 1/100th-scale models of the lifting bodies and using the university’s water channel facility to test them. The idea is to develop a model that could replace some of the earthbound wind turbines currently used.

More: Charlotte Observer

TEXAS

State Considers Scratching RPS, Renewable Zone Initiative

Fraser
Fraser

While other states are increasing their renewable energy sources, the Senate voted to do away with the state’s Renewable Portfolio Standard and end its Renewable Energy Zone initiative. Senate Bill 931, introduced by Republican Sen. Troy Fraser, was passed 21-10 and now goes to the House. Fraser, in defending the bill, noted that the state’s renewable energy goal of 10,000 MW of wind and solar by 2025 was attained in 2010. Texas now boasts having 12,800 MW just in wind. “We’re No. 1 in the nation by a long shot,” he said during a Senate session. “We have the lines there. We can handle another 6,000 or 7,000 MW of wind and solar.”

More: FierceEnergy

WISCONSIN

FERC Approval ‘the Easy Part’ for Wisconsin Energy-Integrys Merger?

WisconsinEnergySourceWEThe Federal Energy Regulatory Commission earlier this month approved Wisconsin Energy’s $9.1 billion purchase of Integrys Energy Group — but that approval may have been a cakewalk compared with the uproar before state regulators, who still must vote on the deal.

The Wisconsin Paper Council and Wisconsin Industrial Energy Group, along with retail ratepayer watchdog Citizens Utility Board, have told the Public Service Commission they’d like to see a guarantee of monetary concessions for ratepayers in light of relatively high rates.

The Milwaukee Journal Sentinel reported that a consultant for Wisconsin Energy has estimated that the merger could result in annual savings to customers of $78 million to $138 million after five or 10 years.

But the utility stopped short of offering a guarantee and said such concessions would amount to overreaching and illegally penalizing shareholders.

The Citizens Utility Board told the state commission Wisconsin Energy has shown “outsized influence, hubris and preference for protecting shareholders at the expense of customers … particularly when it expresses gall at customers’ attempts to secure actual, quantifiable benefits and meaningful protections from the transaction.”

More: Milwaukee Journal Sentinel

Ex-OMS, PSC Head Joins Law Practice

Former Public Service Commission Chairman Eric J. Callisto has become a partner at the Madison office of Michael Best & Friedrich.

Callisto will represent client interests in energy-related legislation in Congress. Callisto has served as president of the Organization of MISO States and held leadership positions in the National Association of Regulatory Utility Commissioners.

“His extensive background in regional and national energy matters and his recognition as a thoughtful regulator provide him with unique experience and perspective that will benefit the firm’s present and future energy clients,” said Dan Sanford, managing partner of Michael Best’s D.C. office.

More: Michael Best & Friedrich

Compiled by Ted Caddell

PJM Bid to Delay Capacity Auction Draws Flurry of Support, Criticism

By Suzanne Herel

PJM’s request to delay May’s Base Residual Auction has drawn more than two dozen comments — mostly from supportive stakeholders, but also from critics who say a postponement would create more market uncertainty than it is seeking to quell.

pjm
(Click to zoom.)

The RTO asked the Federal Energy Regulatory Commission for a Tariff waiver allowing the delay on April 7 (ER15-1470) after responding to FERC’s deficiency ruling over its proposed Capacity Performance plan (ER15-623). (See PJM Responds to FERC Queries on Capacity Performance, Requests Approval.)

Among those opposing the delay are American Municipal Power, Old Dominion Electric Cooperative and Southern Maryland Electric Cooperative. “The commission should not allow PJM to create destabilizing market uncertainty by holding the BRA hostage until it secures a Capacity Performance ruling to its liking,” they said in a joint filing.

“Indeed, PJM’s transparent attempt to blame the commission for the uncertainty — by requiring that PJM provide additional support for its deficient Capacity Performance proposal — only underscores that it is PJM, through the filing of its waiver request, that has created the very uncertainty it now asks the commission to cure.”

Supporters, however, not only urged FERC to grant the waiver, but to approve the Capacity Performance proposal in time for a delayed BRA. The proposal would increase capacity payments for over-performing participants and penalties for non-performers.

AES, Calpine, Dynegy, Exelon, FirstEnergy, PPL, Public Service Enterprise Group, Topaz Power Management, AEP Generation Resources, East Kentucky Power Cooperative and NRG Energy filed a joint statement saying that holding the auction under the current Tariff “will expose our customers and the PJM market to unacceptable reliability risks.”

“Additionally, further delay in approving these reforms creates significant market uncertainty given the myriad business decisions that depend on clear market rules and price signals,” they said. “State default procurements, retail contracts and capital investment decisions all hinge on knowing both when to expect commission resolution and what the commission has decided.”

Transitional Incremental Auction

Rockland Capital and others opposing the delay suggested that if FERC approves a version of the Capacity Performance plan, it should allow PJM to hold a transitional Incremental Auction for the 2018/19 delivery year.

PJM filed a response opposing that proposal.

“At bottom, protestors ignore the essential ‘phase-in’ nature of the transition auctions and are in reality simply seeking to put off Capacity Performance reforms for at least another year. That patently does not achieve the purposes of PJM’s requested waiver of preserving a genuine opportunity to implement Capacity Performance for the 2015 BRA and therefore should not be deemed an acceptable alternative to the waiver,” PJM said.

In its protest to the waiver, Panda Power Funds said it would create “significant uncertainty not only as to the timing of the BRA, but also as to the capacity products to be offered in the BRA, the costs of participating in the BRA and other rules related to the BRA. Postponement of the BRA also threatens to delay the completion of needed new capacity and thus prevent PJM from meeting its own reliability objectives.”

Others opposing the waiver request include several environmental organizations, the Advanced Energy Management Alliance, energy trading companies, state regulators in Maryland and New Jersey and some consumer advocates. Utilities largely supported PJM’s request.

“By granting PJM’s waiver request, the commission mitigates market uncertainty by allowing market participants to know what the performance requirements are in order to value risk accordingly,” said the Public Utilities Commission of Ohio.

Shell Energy took the opportunity to urge FERC against a “hasty roll-out” of PJM’s plan, while noting it does not oppose “these much-needed reforms.”

“In addition to the direct effects of the Capacity Performance proposal, the commission must provide a fair opportunity for market participants to assimilate the indirect effects of the proposal as approved on bilateral transactions, such as off-take agreements or agreements involving long-term hedges of retail electric supply,” it said.

Shell requested a technical conference in which PJM and the Independent Market Monitor would make presentations on the details of the program and answer questions on the record.

In its filing, PJM said that if FERC does not respond by April 24, it will consider the waiver withdrawn and proceed with the May 11 BRA as scheduled.