November 17, 2024

FERC Requests More Info on NYISO Voltage Compensation Change

By William Opalka

The Federal Energy Regulatory Commission says a filing made by NYISO to calculate payments for voltage support services (VSS) is deficient (ER15-1042).

The commission Friday requested more information before it can consider amendments to NYISO’s Market Administration and Control Area Services Tariff.

NYISO proposed paying VSS providers $2,592/MVAr for both leading and lagging capability, with annual increases based on the consumer price index (CPI). MVAr is the unit of measurement for reactive power capability. (See NYISO Rejects Protests on Voltage Compensation.)

FERC asked NYISO for more explanation of the methodology and assumptions used to determine the proposed rate. It also ordered the ISO to provide documentation demonstrating that the proposed amendments maintain the approximate total dollar value of the current VSS program in the near term.

The Independent Power Producers of New York and Dynegy Marketing and Trade filed separate protests asking FERC to order the ISO to increase the compensation rate to reflect inflation since the existing rate was set in 2002.

NYPSC Rejects Opponents’ Request for More Time in Ginna Rate Review

By William Opalka

Opponents of a financial lifeline for the R.E. Ginna nuclear plant were rejected Monday in their bid for more time to  prepare their challenges.

Environmentalists and industrial consumers contended the current schedule will deny ratepayers due process in a case that could cost them $175 million.

The New York Public Service Commission has ordered initial “issue statements” by April 15 in a review of the ratepayer impact of a reliability support services agreement between Rochester Gas & Electric and Exelon’s Constellation Energy Nuclear Group, the plant’s owner. (See Action on Ginna RSSA Delayed 4 Months.)

The PSC ordered the utility to make a deal to keep the plant operating after regulators and NYISO determined the plant was needed to maintain system reliability. A flurry of filings have been made over the past two weeks as supporters and opponents of the deal vie for position (14-E-0270).

Those filings “have not established a basis for us to conclude that an extension of the deadline for submitting issue statements is necessary,” administrative law judges overseeing the case wrote. They also cited the coming summer peak demand, the reliability needs provided by the plant and Ginna’s right to cancel the agreement on July 1 as reasons to keep to the established schedule.

The judges said they were being asked to make rulings on the merits of the agreement in what is meant to be a procedural phase of the case. “We must establish a schedule that preserves the full range of possible outcomes for commission review and decision, without, in practical effect, deciding substantive issues,” they added.

Opponents asked the PSC for more time to make their case against the deal, while the utility, plant owner and PSC staff want to maintain a schedule that would close the case by July 29. If approved, the agreement would be retroactive to April 1 and last through September 2018.

Tginnahe Alliance for a Green Economy and Citizens Environmental Coalition joined the opposition in an April 1 filing in which they also challenged the hearing schedule. The groups said the April 1 effective date of the contract was arbitrary.

“It is unreasonable to saddle Rochester-area customers with retroactive costs and interest payments that will start accruing before there has been time for [the] public to comment on the proposal or for the Public Service Commission to review the case,” they said.

They added that in a “major rate proceeding,” the PSC staff and interested parties have three to four months to conduct discovery. “The relief sought in this case is distinguishable from that which is sought in a typical major rate filing,” the judges wrote, citing the PSC order and the limited issue it posed.

The Utility Intervention Unit of the state’s Consumer Protection Bureau also challenged the effective date, “which was arrived at without the benefit of the parties’ input, [and] should not be used as a justification for limiting the parties’ due process opportunities to participate effectively in this proceeding.”

About 60 commercial, industrial and institutional customers said they support a one-month delay as a “reasonable” time frame to resolve issues before hearings with administrative law judges.

The PSC staff disagreed, saying that the schedule — which allowed 45 days for public comments — meets state law and balances the need to provide adequate time for the public to comment.

Tx Developers Challenge PJM Choice on Pratts Project

By Suzanne Herel

VALLEY FORGE, PA — Two competing transmission developers are challenging PJM’s selection of Dominion Resources and FirstEnergy to resolve reliability problems near Pratts, Va. (See Dominion, FirstEnergy Recommended for Pratts Solution.)

pjm
(Click to zoom.)

ITC Holdings and Northeast Transmission Development sent PJM letters questioning the decision and arguing in favor of their own proposals.

In its letter, dated March 24, Northeast Transmission, a unit of LS Power, said the two proposals it submitted are more efficient and cost-effective than PJM’s choice.

“NTD does not believe that PJM appropriately considered the cost cap provided by NTD relative to cost ‘estimates’ for alternative proposals,” it said.

It also asked PJM to consider two project combinations, either of which it said would save an estimated $28.8 million to $58.8 million and provide cost containment. One of the combinations also would offer reduced risk through use of an existing right-of-way, the company said.

ITC’s letter, dated April 7, called on PJM to reconsider its proposal, which it called “nearly identical” to the one from Dominion and FirstEnergy.

“To resolve this issue equitably, and ensure the evaluation of proposals on an even playing field, we request the PJM perform additional analysis to compare the ITC proposal with the Dominion-FirstEnergy proposal before making a recommendation to the PJM board.”

Four developers suggested 16 proposed solutions, but PJM concluded only six of the proposals solved the violations. PJM said the Dominion-FirstEnergy proposal was selected in part because the companies own the substations involved and most of the rights-of-way required. In addition to project risk, PJM said it considered performance and cost-effectiveness in its selection.

Paul McGlynn, PJM general manager of system planning, told the Transmission Expansion Advisory Committee that planners will review the competitors’ letters and consider changes to their recommendation “if they are in fact warranted.”

McGlynn said planners will return the issue to the TEAC for another discussion before making a final recommendation to the PJM board.

Sharon Segner, a vice president for LS Power, questioned why the Dominion-FirstEnergy proposal should receive a preference for owning substations and rights-of-way when any developer selected would be able to invoke eminent domain to acquire needed land. She added later that Virginia has established precedent that new entrants can obtain public utility status.

“You’re certainly entitled to your opinion,” McGlynn responded.

Segner also said PJM should consider identifying the top three or four most important criteria it will consider when it issues future competitive solicitations, as she said is the practice in CAISO’s Order 1000 process.

McGlynn said performance, cost effectiveness and risk will always be top priorities although their relative weighting may vary from project to project.

ISO-NE Error Could Cost GenOn Millions

By Rich Heidorn Jr.

The owner of a Massachusetts generating plant says ISO-NE is forcing it to pay millions in unnecessary capacity costs because the RTO mistakenly underestimated the plant’s capacity.

GenOn Energy Management, a unit of NRG Energy, asked the Federal Energy Regulatory Commission last week for relief from what it called an “anomalous, illogical and patently unfair circumstance” (EL15-57).

genon
Canal Generating Plant

GenOn said ISO-NE credited its Canal 2 oil- and gas-fired generator in Sandwich, Mass., with capacity of only 303 MW — rather than the plant’s actual 556.5-MW output — in the March annual reconfiguration auction (ARA) for the 2015-2016 capacity commitment period.

As a result, the RTO submitted a demand bid on GenOn’s behalf for the difference, forcing the company “to buy out of a capacity supply obligation that Canal 2 is fully capable of fulfilling.” Only a portion of the demand bid cleared because supply offers filled only two-thirds of the demand bids entered.

The company redacted specifics of how much it estimated the error could cost it, but based on the ARA’s clearing price of $11.466/kW-month, and the prorated apportionment of cleared bids, GenOn could be forced to spend more than $22 million.

GenOn said the plant’s output was derated after the failure of a step-up transformer in July 2013, but that it returned to full capacity in May 2014, as documented by the RTO’s capacity audits. The company noted that it offered the plant’s full capacity in Forward Capacity Auction 9 in February.

The company asked FERC to force the RTO to correct the “obvious mistake on ISO-NE’s part” or grant it a waiver to allow it to escape the capacity charges.

It asked for FERC action by May 25 so that ISO-NE can ensure that the appropriate capacity supply obligations are in place before the beginning of the 2015/16 capacity commitment period on June 1.

MISO TOs Seek Base ROE of 11.39%

By Chris O’Malley

MISO transmission owners have told the Federal Energy Regulatory Commission it should order only a modest reduction in their base return on equity to 11.39%, not the 9.15% sought by industrial customers.

On April 6, the TOs filed an analysis contending 11.39% represented “a logical and supportable estimate of the cost of equity.” Omitting the FERC-approved ROEs for ITC Holdings — the only publicly traded transmission-only company in the U.S. — would result in an “absolute minimum” base ROE of 10.8%, the analysis said.

miso

MISO industrial customers initiated the ROE dispute last fall, contending that transmission operators’ current base return on equity — 12.38%, except for American Transmission Co. at 12.2% — is too high (EL14-12).

The industrials contend the base ROE for TOs should not exceed 9.15%, citing changes in financial markets and other factors. They say the lower base ROE would cut transmission rates by about $327 million annually.

The dispute last year went into settlement discussions, but talks broke down in December.

After it became clear the case would not settle, the MISO Public Consumer Group sector joined in the fight, in what is its first-ever litigation in a FERC rate case.

In February the sector — which includes both non-profit groups and government agencies that represent consumers in utility cases before state regulators — asked MISO for $200,000 to help cover its legal costs in the dispute. (See MISO Advisory Committee Briefs.)

MISO spokesman Andy Schonert said last week that the RTO “continues to consider stakeholder feedback [on the request] and will be finalizing [its] decision quickly.”

On April 3, the consumer advocates asked FERC for approval to amend the group’s intervention by adding the Arkansas Attorney General’s Consumer Utility Rate Advocacy Division; the Kentucky Attorney General’s Office of Rate Intervention; the Louisiana-based Alliance for Affordable Energy; the Montana Consumer Counsel; and the Illinois Attorney General.

“As the outcome of the joint consumer advocates funding request has not yet been determined, it is even more important to broaden consumer advocate engagement in this proceeding in order to build up resources to support the Consumer Advocates’ participation in this case,” wrote Jennifer Easler, an attorney in the Iowa Office of Consumer Advocate.

The dispute follows FERC’s ruling last June that introduced a new, two-step method for calculating transmission owners’ ROEs. Ruling in a case involving New England TOs, FERC tentatively set the “zone of reasonableness” at 7.03 to 11.74%.

Morningstar: PJM to Hit Record Spark Spreads in 2015-16

The next year will be a good one for natural gas-fired generators in PJM, according to Morningstar Commodities Research.

A new report by Morningstar analyst Jordan Grimes predicts on-peak prices at PJM’s West Hub will result in “historically high” spark spreads in delivery year 2015-16. Spark spread, a measure of gas plants’ gross profit margin, is the difference between the price received by a generator for power and the cost of the gas needed to produce it.

spark spread

Grimes says physical reserve margins will tighten due to the retirement of more than 10,000 MW of older coal, gas and oil capacity before June 1.

“New combined-cycle capacity will replace some of this lost capacity, but much of the physical capacity will be replaced with demand response, renewables and expected imports from neighboring ISOs,” he wrote. “When DR replaces physical capacity, it will steepen the supply curve at the same time physical reserve margins drop this summer.”

For a gas plant with a 7,000 Btu/kWh heat rate purchasing gas at Tetco-M3 and selling power at PJM West, that could lead to spark spreads averaging $25/MWh in calendar year 2015 and $22/MWh in 2016, Grimes predicts.

But he says spreads will decline to $18 in 2017 and $16 in 2018 as more new combined-cycle plants are built in PJM and pipeline expansions allows Marcellus gas producers to obtain higher prices from more distant customers.

“There are a few scenarios … that would help keep spark spreads elevated in 2017 and 2018, but the most likely scenario is lower spark spread clears, given the new, more efficient supply stack and higher Tetco-M3 gas prices,” Grimes said.

PJM Operating Committee Briefs

An unexpected geomagnetic disturbance (GMD) March 17 caused brief spikes on PJM’s grid but no operational problems, RTO officials told the Operating Committee last week.

pjmSome of PJM’s approximately 50 geomagnetically induced current (GIC) meters recorded spikes of more than 20 amps, but the jumps were short-lived and did not cause PJM to direct conservative operations.

The National Oceanic and Atmospheric Administration, which normally provides one to three days’ advance notice of such events, didn’t warn PJM and other grid operators until the morning of the 17th, said Chris Pilong, manager of dispatch.

NOAA predicted “a glancing blow” centered at 50 degrees latitude — near Winnipeg, Manitoba. As it turned out, the solar storm was a bit more intense than expected and centered a bit farther south, Pilong said.

Still, the incident did not pass PJM’s threshold for initiating conservative operations — a rise of 10 amps for more than 10 minutes. Pilong said the longest spikes lasted no more than four minutes.

“This is the highest measurement I can recall seeing in some time and we saw no impact on the system,” he said.

NOAA initially predicted a G-3 (strong) event for three hours beginning at 8 a.m. ET. It upgraded the storm to a G-4 (severe) with a lower latitude of 45 degrees — near Montreal — and a six-hour duration.

The GIC meters recorded their biggest spikes between 9 and 10 a.m. and 7 and 7:30 p.m. (See graphic.)

The incident came less than two weeks before the North American Electric Reliability Corp.’s Geomagnetic Disturbance Operations Standard (EOP-010-1) took effect on April 1. The standard requires reliability coordinators to review the GMD operating procedures or processes of transmission operators (TOPs) within their areas to mitigate the effect of GMDs on the grid.

The Federal Energy Regulatory Commission approved the standard, the first phase of rules to protect the grid from GMDs, last June. (See FERC OKs GMD, Training Standards; Proposes Modeling Rule Change.)

PJM: New Rule on Lost Opportunity Costs Would Exclude 1/5 CTs

About 20% of PJM’s combustion turbines, representing 30% of its CT capacity, would be barred from receiving lost opportunity costs under a rule change awaiting a shareholder vote, PJM officials told the OC last week.

Adam Keech, director of wholesale market operations, said PJM conducted the analysis after the Markets and Reliability Committee last month tabled voting on the proposal.

The delay came after some stakeholders complained that the changes — which would generally limit lost opportunity costs to units with start-up and notification times of no more than two hours and minimum run times of two hours or less — were too restrictive. (See PJM Tables Rule Change on CT LOCs.)

Keech said that if the minimum-run-time threshold were increased to four hours from two, only 10% of CT units and capacity would be excluded from lost opportunity costs.

PJM officials told the OC they had no operational concerns about the changes.

One generation operator, who declined to be quoted by name, said the new rules would create “perverse incentives” for generator operators, resulting in some units running under self-schedules for an additional hour after the two-hour limit. “I will submit a schedule that meets your payment parameters, but on operations I need to do what I need to do,” he said.

“Instead of using a carrot approach, you’re using a stick approach,” he added.

Keech said that the change, which is supported by PJM and the Independent Market Monitor, was intended to eliminate incentives at odds with PJM’s needs. Under the current rules, he said, “you get paid more if you don’t run [in real-time] than if you do.”

Louis Slade, a senior policy manager for Dominion Resources, questioned whether PJM’s data would be accurate in the future, saying most new CTs are 150 MW or larger and have minimum run times of longer than two hours. “Two hours potentially puts a lot of the newer CTs outside of that range,” he said.

Director of Stakeholder Affairs Dave Anders said the Energy Market Uplift Senior Task Force, which overwhelmingly approved the proposed change in February, may consider “friendly amendments” at its April 17 meeting.

The MRC is expected to vote on the issue at its next meeting, April 23.

Too Much of a Good Thing? PJM Concerned Fast Response Regulation Crowding Out Traditional Resources

pjm

PJM operators are concerned that fast response regulation resources are taking too large a share of the RTO’s overall regulation response.

PJM’s Danielle Martini presented a proposed problem statement on the issue to the OC last week.

Fast-responding RegD are providing more than 42% of total response on average, with shares as high as 70% during some events, Martini said. That leaves less room for slower-responding RegA resources.

“Too much RegD looks like it hurts performance because it affects how much RegA we procure,” Mike Bryson, executive director of system operations, explained after the meeting.

PJM is considering whether to use a different regulation signal for energy-limited resources such as participating in the regulation market.

“This scenario is seen most frequently when the RTO experiences high or low [area control error] during periods of rapid load changes during the morning and evening periods,” the problem statement said. “During these times, the regulation signal is utilized to maintain ACE control if the load ramp briefly and instantaneously ‘slows down’ or ‘speeds up.’ During these times, larger sized units are coming on line and offline (hydro, CTs, etc.) to keep up with the load, and regulation is critical in correcting for the instantaneous changes in load and generation.

“When the regulation signal ‘times out’ for RegD resources and there is a large amount (>42%) of RegD providing the regulation service, the dispatcher is left with limited resources with which to maintain control of the system. This may lead to increased periods of ACE/BAAL excursions and increased reliance on synchronized reserves to supplement the temporarily depleted regulation reserves.”

PJM Ponders Expansion of Winter Generator Testing

PJM is considering stakeholder suggestions that it expand the winter generator testing it initiated last winter.

That testing was voluntary and limited to units that hadn’t run for the prior two months. It was credited with reducing generator outages to a peak of 10% in January 2015, compared with a high of 22% a year earlier.

Mike Bryson, executive director of system operations, told the OC that some stakeholders have suggested the testing be made mandatory.

In early November, PJM identified about 55,000 MW of generation that was eligible for testing because it had not operated for the prior two months. The number dropped to about 44,000 MW after some of the units were dispatched during an early November cold spell.

Owners of about half of the remaining units submitted them to PJM for testing, but the RTO ended up testing only about 9,000 MW because of a 1,000-MW cap on tests per day and because warm weather prevented testing on some days.

The temperature threshold “knocked most of the days out” for testing in the Dominion zone, Bryson said.

PJM officials plan to discuss the issue internally before bringing a proposal to stakeholders, Bryson said.

New Info on Planned Outages to be Shared

PJM plans to start posting additional information on scheduled transmission outages in its OASIS system in response to requests for such details.

Beginning with the third-quarter eDart release in September, the following information will be available: the queue number; the time that the outage equipment can be returned to service at PJM’s request; and a “questionable approval” indicator, which will inform market participants that the outage may not be approved by PJM.

 — Rich Heidorn Jr.

Deadline Looms for Decisions in Exelon-Pepco Deal

By Suzanne Herel

Supporters and critics of Exelon’s proposed $6.8 billion takeover of Pepco Holdings Inc. are churning out newspaper opinion pieces, resolutions and public relations campaigns as the last holdouts to the deal approach deadlines to render decisions.

Delaware regulators last week agreed on a final settlement but will wait to sign it until deals have been finalized with Maryland and D.C.

exelon
Pepco Holdings Inc. CEO Joseph Rigby testifies before D.C. Public Service Commission.

Evidentiary hearings were scheduled to end last week in D.C., but two more days of testimony were added for April 20-21. The Public Service Commission will close the record on May 13. (See CEO Crane to DC PSC: Exelon Committed to Jobs, Ratepayers.)

In Maryland, hearings are set for Wednesday, Thursday and, if necessary, Friday. The PSC has a deadline of May 8 to reach a decision.

The acquisition already has been approved by the Federal Energy Regulatory Commission, the New Jersey Board of Public Utilities and the Virginia State Corporation Commission.

Exelon has promised all jurisdictions equivalent concessions, the bulk of which address customer benefits, workforce retention and commitments to energy efficiency. It also conceded items of particular interest to some jurisdictions, such as recreational trails in Maryland and a feasibility study of wind generation in Delaware’s southern counties.

Delaware PSC on Board

Under the terms of the settlement outlined before the Delaware Public Service Commission last week, electricity users will share a one-time credit this summer totaling $40 million instead of a larger payout that would have been distributed over 10 years. Exelon also committed to spend $2 million for a low-income energy efficiency plan for PHI’s Delmarva Power & Light customers.

One intervener initially skeptical of the deal, University of Delaware professor Jeremy Firestone, withdrew his opposition at last week’s hearing, saying he was pleased to have helped negotiate the lump sum credit and the study of wind generation in Kent and Sussex counties.

PJM’s Independent Market Monitor, represented at the hearing by General Counsel Jeffrey Mayes, said the merger should be conditioned on several measures designed to ensure competition, including a promise to remain in the RTO indefinitely and to make property paid for by ratepayers available to competitive transmission developers. The suggestions, however, gained no traction among the commissioners.

Although the commission did not vote on the agreement, none of the commissioners expressed opposition.

State Rep. John Kowalko, who did not act in time to become an intervener, was the lone voice of dissent during public comments at the hearing, saying the interests of Delaware’s 250,000 residential ratepayers will be lost among the total of 9.6 million customers affected by the acquisition. “We will be the proverbial flea on the elephant’s back,” he said.

Opposition Grows in DC

The deal is facing stiff opposition in D.C., where nearly half of the District’s Advisory Neighborhood Commissions last week passed measures against the takeover, including every ANC in Ward 4, home to Mayor Muriel Bowser. None of the groups has come out in support of the deal.

“Some of D.C.’s electricity consumers have long suffered from poor reliability, and allowing our power decisions to be made by an out-of-state energy conglomerate with a sizeable roster of high-priced nuclear power plants would not be in our community’s best interest,” Douglass Sloan, commissioner of ANC 4B09, said in a statement released by Power DC, a coalition of electricity customers concerned about rates, reliability, renewable energy and local control.

Three of the 12 members of the D.C. Council — Mary Cheh, Elissa Silverman and Charles Allen — filed a letter with the PSC opposing the merger. The Office of People’s Counsel is also advising against approval.

Exelon has fared better in Maryland, where two key counties — Montgomery and Prince George’s — agreed to support the acquisition in return for promises to fund customer bill credits, grid reliability improvements, renewable energy projects, energy efficiency programs and help for low-income consumers. (See Exelon, Pepco Ink Deal with Md. Counties, but Critics Stand Firm.)

However, the Montgomery County Council split from County Executive Ike Leggett and unanimously passed a resolution saying that the settlement “does not adequately address the overarching issues that have led the state, the Office of People’s Counsel, the environmental community and other public interest organizations to maintain that the merger is contrary to the public interest.”

The acquisition also is opposed by state Attorney General Brian Frosh.

If the deal is approved, it will create the Mid-Atlantic’s largest electric and gas utility.

SPP Market Monitor Protests Make-Whole Promise for Gas Units

By Rich Heidorn Jr.

SPP’s Market Monitoring Unit asked the Federal Energy Regulatory Commission last week to reject a proposal that would bar the RTO from canceling commitments of gas-fired generators if they are not needed.

SPP’s proposal would result in “an inefficient transfer of gas market risks to SPP’s load,” wrote Catherine Tyler Mooney, the MMU’s manager of market analytics (ER15-1293).  “… This commitment may impose uneconomic production on the market, impacting market prices, uplift, congestion, transmission congestion rights payments or market-to-market settlements.”

At issue is SPP’s March 16 proposal to codify its historical practice of not de-committing generators committed out of its multi-day reliability assessment during emergency operations. The Tariff change would bar SPP from decommitting such units unless they presented a reliability risk.

SPP proposed the change after some gas-fired generators in PJM complained that they suffered “stranded gas” losses in 2014 when they bought fuel at high prices in response to transmission operators’ directions that were not needed by the market later. (See PJM Backs Duke’s $9.8M ‘Stranded Gas’ Claim.)

SPP said it filed the Tariff revisions in response to “stakeholders’ request for clarity on whether and how resources may be committed” under its multi-day reliability assessment if SPP has implemented conservative operations under its emergency operating plan. The proposal was approved by the RTO’s Members Committee and Board of Directors in January.

The MMU said the proposed change was problematic for several reasons. “First, it may be difficult for SPP to verify the legitimacy of unused fuel cost claims. Second, generator operators are in the best position to effectively minimize fuel costs.”

The MMU said that SPP should have the ability to reevaluate its need for generation during emergencies — if, for example, weather forecasts change.

“Avoidable adverse consequences should not be imposed on the market to lessen the predetermined cost exposure of individual generators,” the MMU said. “It is not a cost-minimizing market outcome. If SPP staff, its members and the commission believe that an uplift payment for unused fuel is necessary to preserve system reliability during emergencies, SPP should pursue that particular issue.”

PJM Planners Set April 28 for Artificial Island Recommendation

By Suzanne Herel

VALLEY FORGE, Pa. — PJM planners said last week they will announce their revised recommendation to address stability problems at the Artificial Island nuclear complex at a special Transmission Expansion Advisory Committee meeting April 28.

Planners recommended Public Service Electric & Gas for the project last June, but the Board of Managers reopened the bidding to finalists Transource Energy, Dominion Resources and LS Power after criticism from environmentalists, New Jersey officials and spurned bidders.

All of the potential solutions involve new transmission lines connecting Artificial Island to Delaware. LS Power and Transource have proposed a southern crossing of the Delaware River. Dominion and PSE&G offered a northern route with an overhead crossing.

Planners had hoped to announce their revised selection in January but delayed their decision to allow consultants to investigate concerns that Dominion’s proposed use of thyristor controlled series compensation (TCSC) could threaten reliability at the island, home to the Salem-Hope Creek nuclear complex. (See Further Study Delays PJM’s Artificial Island Decision.)

PSEG Nuclear, which operates the nuclear plants, contends Dominion’s proposal would use unproven technology that could result in damage to turbine generator shafts.

Planners told TEAC members last week Siemens Power Technology International had completed its sub-synchronous resonance analysis of Dominion’s proposal and found that the TCSC could result in “negative damping” for several resonant frequencies.

However, Exponent, an engineering and science consulting firm that reviewed the Siemens study at PJM’s request, said it was “inconclusive” because of limits in the data available.

Exponent expressed its own concerns with the Dominion proposal. It said Dominion is proposing a 90% post-contingency TCSC compensation — well above the 70 to 80% compensation used by others in the industry.

Responding to questions from stakeholders who suggested more study might be needed to verify the feasibility of the Dominion proposal, Steve Herling, vice president of planning, said Siemens had identified the “potential for an issue.”

“It’s not a fatal flaw,” he said.

“[I]t’s an issue going forward,” said Thomas Leeming, director of transmission operations and planning for Exelon’s Commonwealth Edison. Not “having wrestled this to the ground could be an issue.”

“We understand what needs to be done if we go that way,” Herling responded. “We recognize that if we go with this solution there’s more work to be done. We’ve already talked to a number of manufacturers about all these issues.”

Planners said their current schedule would result in a recommendation to the Board of Managers’ Reliability Committee on May 19.